Projects

A complex structure: the basis of a multifunctional sports boulevard

Tekst Liliane VerwooldFotografie De Vries en Verburg

De ijsbaan is voorzien van een lekwaterconstructie, die smeltwater in goede banen leidt.
De ijsbaan is voorzien van een lekwaterconstructie, die smeltwater in goede banen leidt.

A full-scale sports boulevard is being built along the Vliet in Leiden. Visitors will find an outdoor swimming pool first, followed by an indoor swimming pool and ice rink combined in a single building. There will, of course, also be catering facilities and all the associated amenities.

The central section of the building, with the entrance, catering facilities, changing rooms and toilets, will connect the indoor swimming pool and ice rink.

De Vries en Verburg is building the new indoor swimming pool (35×25 metres) and ice rink (a 250-metre oval track, a 30×60-metre ice surface and a 45×20-metre practice ice surface). The central section of the building, with the entrance, catering facilities, changing rooms and toilets, will connect the indoor swimming pool and ice rink.

A complex structure

De Vries en Verburg is currently constructing the building, which combines concrete and steel and is quite complex. “The concrete structure alone comprises 35 cast-in-place floor slabs,” says Guido Jongebreur, project manager at De Vries en Verburg. “The most challenging is undoubtedly the cast-in-place upper floor on which the ice rink will be built. It is cantilevered, 60 centimetres thick and includes a 10-centimetre-thick insulation layer, topped by a 10 cm concrete floor containing the cooling pipes.”

In the right order

This complex floor is being built in accordance with a dedicated method statement prepared by Hiber, and with the aid of numerous temporary support structures. The floor will then provide the base for the steel structure on the uppermost level. While erecting both structures, De Vries en Verburg must carefully monitor the sequence of work. The structural elements will fit together smoothly only if they are installed in the right order. 

The two separate sections will ultimately form a single whole.

Meltwater drainage

The ice rink’s drainage system also calls for careful planning. Jongebreur says: “When the ice in the rink is melted, the water must not enter the concrete structure. The concrete would expand as it froze, causing cracks to appear. To prevent this, measures are being taken to channel the meltwater safely away.”

The concrete structure comprises more than 35 cast-in-place floor slabs.

Sustainable and circular

The sustainability ambitions for the combined building are high. The municipality of Leiden has opted for an all-electric, energy-neutral building, incorporating the latest thinking on circularity. More than 3,400 solar panels on the roof will achieve an A++++ energy rating. The remaining roof area will be planted, slowing the flow of rainwater into surface water. The smart heat exchange between the ice rink, indoor pool and outdoor pool also plays a key role in making optimal use of energy. “Waste heat released while cooling the ice rink will be used to heat the indoor swimming pool. This will also allow the renovated outdoor pool to operate without gas. ‘We’re progressing well according to schedule,’ Jongebreur concludes. ‘As things stand, we can complete the project in spring 2023. Leiden will then have a top-class training and competition venue with a 250-metre oval track.’” 

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Sportboulevard Leiden in Leiden

  1. OpdrachtgeverGemeente Leiden
  2. ArchitectSlangen + Koenis
  3. ConstructeurPieters Bouwtechniek
  4. AannemerDe Vries en Verburg
  5. InstallateurBRI
  6. InstallateurLotec
  7. InstallateurNijssen

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectSportboulevard Leiden
  • OnderwerpProjects
  • BedrijfGemeente Leiden
  • BedrijfSlangen + Koenis
  • BedrijfPieters Bouwtechniek
  • BedrijfDe Vries en Verburg
  • BedrijfBRI
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.