Software & automation

Cycling through the Trees: AVEVA E3D Structural Design

Cycling through the Trees: AVEVA E3D Structural Design

Liemar Software is an agent for AVEVA E3D Structural Design. The programme integrates seamlessly with our ERP software for steel construction and metal fabrication.

The ‘Cycling through the Trees’ project was built using AVEVA E3D Structural Design and won several national and international awards.

‘Cycling through the Trees’ in Bosland offers a unique cycling experience, with a route that takes you up to ten metres above the ground and among the trees. This cycle path safely takes you to new heights. Literally: a double loop takes you right up among the treetops, as high as ten metres. The cycle path is 700 metres long in total. You experience nature in a completely different way and become, as it were, one with the forest. The path is also open to walkers and joggers.

The project is based on a steel structure. Frederic Sneyers of Smulders (Drawing Office Balen België) talks about the project’s technical challenges: ‘We were particularly interested in this project because of its complexity.’

What made this project complex?  

‘First of all, the location. It is a forest with narrow access roads and no facilities such as electricity. The calculations were also a major challenge. We had to ensure that the ground was disturbed as little as possible, and we were not allowed to use concrete decks to secure the columns. And this is a structure without bracing.’

The steel structure has already started to rust a little. Was this done to match the surroundings?

‘There are several reasons for this. The steel used is weathering steel (Corten steel). Its advantage is that it does not need a coat of paint and has that characteristic rust colour. The architect chose it specifically because the columns are intended to resemble pine trees. The colour of the steel is close to the natural colour of the tree trunks.

What were the main challenges on this project?

‘Because the project is in a forest, we had no storage area for the columns and deck sections. We therefore had to load the trailers so that the sections could be installed directly from the trailer in their correct positions. This also meant that the project schedule had to be spot on. The aim was to leave nature as untouched as possible, not to clear everything.’

‘This steel needs to be treated differently from ordinary steel. For example, all the parts had to be degreased, otherwise marks would remain visible after the rusting process. Special welding wire also had to be used, and nothing could be marked on the steel. Handle with care. The bolts used also had to be made of Corten steel. Our purchasing department had to source them in the US. When installing the bolts, insulating material was also needed to prevent interaction between the Corten steel and the stainless steel railing.’

‘Since we were not allowed to use a concrete deck to install the columns, we used screw piles approximately 2 metres long, driven into the ground, onto which we could mount a column. This disturbed the ground as little as possible. Only the two abutments had to be built on a concrete deck measuring 5 metres x 5 metres and 2 metres deep. This was because the two abutments provide the structure’s stability. They anchor the entire structure, so there is no bracing anywhere in the bridge.

‘The crane was positioned in the middle of the circle, so we needed one capable of placing approximately 7 tonnes at a distance of 50 metres. Crane operators with the right qualifications are not easy to find. At the end of the work, the crane also had to be able to get out of the circle, so we took this into account when planning the installation sequence. As a result, some columns were installed later. Almost no greenery was damaged during the work.

‘We installed one abutment first, and this had to be positioned with 100% accuracy. Then the two bridge sections were installed side by side, followed by the intermediate columns until the circle was complete. The final bridge section closes the circle. This method requires complete control over the accurate positioning of the columns. Even a deviation of just 0.5° would make it impossible to connect the sections correctly at the end of

the circle. After extensive internal discussions, we decided to use special temporary assembly trestles. This gave us confidence that the structure could be installed quickly and without a hitch. The stainless steel railing was set out on site and then expertly welded in the workshop. This was the only way to guarantee a perfect fit.’

‘Working with an architectural practice can also be a challenge when it comes to realising the visual design as effectively as possible. But we ticked every box successfully here too!’

How did AVEVA E3D Structural Design, as a design tool, help you tackle these challenges in a practical and clear way?

‘As the structure is curved and also slopes, AVEVA E3D Structural Design is ideal for drawing it. The coordinate system was also very useful for determining the exact locations of the ground piles, in both the x and y directions and in the z direction (height). The coordinate system was sent to our surveyor as an export file. The surveyor set out every ground pile to within a millimetre. The piles were then installed with millimetre accuracy at all 449 unique positions.’

How did you transfer the design to the machines? Did you do this directly from AVEVA E3D Structural Design?

‘We have an in-house ERP system that controls our machinery, and all the data comes from AVEVA E3D Structural Design. This includes, for example, lists and NC machine control data. Our production planning team processes this data and then operates the machines.’

Cycling through the Trees in figures

  • Bridge length: approximately 700 metres
  • Bridge diameter: 100 metres
  • Bridge height: 10 metres
  • Length of stainless steel railing tube: 2.8 kilometres
  • Length of stainless steel safety net: 2.8 kilometres
  • 449 unique Corten steel columns
  • 27 different deck sections (approximately 7 tonnes each)
  • Each deck section is approximately 13 metres long and 3 metres wide
  • Approximately 10,000 Corten steel bolts
  • Precision crane capable of safely positioning 7 tonnes at a distance of 50 metres

Een zakelijke vraag aan Liemar Software BV? Neem contact op

Wie eraan werkte

Fietsen door de Bomen in Hechtel-Eksel

  1. ontwerpBuroLandschap
  2. ontwerpDe Gregorio & Partners architecten
  3. agentLiemar Software
  4. staalconstructieSmulders

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectFietsen door de Bomen
  • ThemaDigitaal van ontwerp tot montage
  • OnderwerpSoftware & automation
  • BedrijfLiemar Software BV
  • BedrijfSmulders
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.