Road concrete with the lowest possible environmental cost
Tekst Roel van GilsFotografie Den Ouden Groep

Den Ouden Groep is placing all the road concrete on the N395 in situ. During the preparation phase, considerable attention was paid to selecting the right mix designs, both to shorten the project duration and to achieve a favourable environmental cost indicator (MKI) score. We spoke to Sjoerd van Ingen, project manager at Den Ouden Groep.

“BAM Infra Nederland approached us in 2020 to submit a binding tender for this project,” says Van Ingen. “We have successfully worked on several roundabouts in the past, and the collaboration has always been very good. We work well together and provided input at an early stage on the planning and, above all, on the mixes we could use to reduce CO2 emissions as much as possible. Together with our concrete supplier, Mebin, we sought to achieve the lowest possible MKI score. BAM scored well on this in its MEAT tender.”
Faster
Linear elements, printed concrete, the road surface on the dumbbell roundabout and the cycle paths: all of it is being cast in situ. “That was a deliberate choice,” says Van Ingen. “The reconstruction of the N395 is being carried out in phases, largely while traffic is still using the road. That means the duration of each phase is limited. You can imagine that machine-laying more than 9,000 metres of kerbs is many times faster than using precast elements, which have to be laid by hand by a pavior. The tight schedule also led us to use structural fibres for the dumbbell roundabout instead of a design with continuous reinforcement. That saves around five days per phase on placing the reinforcement.”
More sustainable
In this case, casting the road concrete for the N395 in situ is also a more sustainable choice, and delivers a stronger end result. The project uses Den Ouden 2.0 mix. “It has considerably lower CO2 emissions. This gives us a low MKI score without compromising on quality. The only drawback is that the mix takes longer to harden,” Van Ingen acknowledges. “Where the schedule is tight, we use a mix with a higher Portland cement content, such as for part of the road surface on the dumbbell roundabout. At the initiative of the province of North Brabant, an additional item was also included to gain experience with geopolymer concrete, which helps reduce CO2 emissions further. Around 2,000 m2 of cycle path will be built using this product, in collaboration with the A. Jansen plant.”
Not only are the project durations extremely short, but changing circumstances also mean that the schedule sometimes has to be adjusted. “Fortunately, as an organisation we can respond flexibly and tailor the mixes accordingly. That way, we ensure the concrete hardens sufficiently at the right times, allowing others to continue their work. There is no room for delays.”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
N395
- betonleverancierMebin
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectN395
- ThemaMinder CO2 in beton en staal
- OnderwerpGeneral
- BedrijfMebin
- BedrijfJansen B.V.


















