Innovative floor creates space at height

Tekst Tjerk van DuinenBeeld Dutch Engineering en Van Pommeren Las & Montagebedrijf

De nieuwe vloeren in de Evenementenhal betekenen een extra vloeroppervlak van 1.100 m2.
De nieuwe vloeren in de Evenementenhal betekenen een extra vloeroppervlak van 1.100 m2.

Midden Nederland Hallen event venue

There is a hive of activity at Midden Nederland Hallen in Barneveld. In September, 40-45, De Musical premiered in the brand-new theatre hall. Right next door, the existing event venue received a major upgrade this summer and a new name: Evenementenhal. This multifunctional space has all the technical facilities for conferences and events for up to 750 people. Van Pommeren Las & Montagebedrijf built two new mezzanine floors with four breakout rooms in the hall, giving client Midden Nederland Hallen even more options for meetings and breakout sessions, for example. Van Pommeren used the latest version of the ComFlor 210+ floor system.

The steel in ComFlor 210+ is more securely bonded to the concrete and makes a greater contribution to reinforcement, with greater stiffness in its composite action with the concrete. (Image: Dutch Engineering)

The new floors at Evenementenhal add 1,100 m2 of floor space. “That is a substantial increase on the existing 2,200 m2,” says Gerrit van Leeuwen, Project Manager at Van Pommeren Las & Montagebedrijf. “The two floor areas are more than six metres above ground and are linked by a walkway at a height of three metres. Two precast concrete staircases and a lift provide access to the new level. Steel staircases were considered unsuitable because of noise. The composite steel deck floors are supported by steel beams and columns. Van Pommeren Las & Montagebedrijf installed new foundations for them. First, openings were made in the existing floor, then steel tubular piles were driven in and pile caps installed to support the new columns.”

Preparations for pouring the walkway.

Propping-free construction

The two floors and the walkway were built using the ComFlor system. Van Leeuwen: “Structural engineer JVZ specified these composite steel deck floors from Dutch Engineering in the tender documents. They are easy for us to work with and allow us to build without temporary props. The structural engineer saw them mainly as a lightweight, strong alternative to much heavier hollow-core slabs. We were also able to use ComFlor 210+, an upgraded version of the 210 with improved properties.”

Shear resistance

The steel floor decking is supplied on behalf of Van Pommeren by Dutch Engineering of Zoeterwoude. Managing Director Henk Prins explains what changes make the ComFlor 210+ an upgrade to the 210. “The 210 series comprises deep steel decking for long spans without temporary propping, making it particularly suitable for upper floors. The new version has a dovetail-like vertical angle at the top, which anchors it to the concrete section. This gives the steel a stronger bond with the concrete, a greater contribution to reinforcement and greater stiffness in composite action with the concrete. We commissioned TU Delft to test the floor for composite action. For the same contact area, shear resistance is around four times higher than with the old 210 deck. This means a stiffer, stronger floor structure that can carry greater loads.” 

Underfloor heating and reinforcement on the ComFlor 210+ decking.

The design load for the new upper floors in Barneveld was 500 kilograms per square metre. Underfloor heating (double mesh) was cast into the concrete layer. The 100 m2 walkway was built using ComFlor 100, a floor system with a relatively very low self-weight. “Another advantage of the 210+ is the screws,” Prins concludes. “They protruded in the previous version. A redesigned side-lap detail now encloses the screw points within the floor section, which architects generally find more attractive.”   

The composite steel deck floors are supported by steel beams and columns.

Een zakelijke vraag aan Dutch Engineering? Neem contact op

Wie eraan werkte

Hal Midden Nederland Hallen in Barneveld

  1. VloerVan Berlo
  2. OpdrachtgeverMidden Nederland Hallen
  3. architectAGB Global Design
  4. ConstructeurJVZ
  5. DirectievoeringHPM Advies
  6. StaalwerkBrink Staalbouw
  7. SandwichpanelenHardeman Isolatie
  8. stalen vloerplatenDutch Engineering

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectHal Midden Nederland Hallen
  • ThemaVloeren in beton en staal
  • OnderwerpSteel
  • BedrijfDutch Engineering
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.