Temporary tram depot built with sustainability as the top priority
Tekst Tjerk van DuinenBeeld Vic Obdam

A tram depot for historic trams from Amsterdam was built on the edge of the Zuidas in just sixteen weeks. The temporary facility is linked to the redevelopment of the Havenstraat area, where the depot will have a permanent home. The Municipality of Amsterdam called for a circular solution for the 100-metre-long depot. Steel contractor Vic Obdam and main contractor Witte Bouw delivered on this challenge in 16 weeks.
Trams have been a familiar sight on the streets of Amsterdam since the 1910s. Many old trams are still in service and are based at the Electric Museum Tram Line Amsterdam, next to Haarlemmermeerstation. The Havenstraatterrein is undergoing major redevelopment, including the construction of a new home for the museum tram line. A temporary location was therefore needed for the trams. One was found on the Zuidas at Jachthavenweg, where a temporary tram depot has been built over the existing museum tram line track.

Minimal environmental impact
The project was awarded to Witte Bouw through a tender run by the Municipality of Amsterdam. The contract was for a 100-metre-long tram depot over a single track along Jachthavenweg. The contractor brought in Vic Obdam for the steel structures. “Witte Bouw approached Vic Obdam because we are willing to go out on a limb when it comes to sustainability,” says Jan Smit, circularity coordinator at the steel contractor. “CO2 reduction was central to the tender, and it is an area in which we are keen to distinguish ourselves. This is a temporary project, so you want to keep the environmental impact to a minimum.”
XCarb steel
The long, narrow structure has a gabled roof and is made up of steel portals with external cladding made from residual material from the steel industry. “To minimise the environmental impact, the ideal solution would of course be to use donor steel throughout,” says Smit. “But the tight schedule made it impossible to find reclaimed material; in our experience, that takes a lot of time. We do know how to produce new steel as sustainably as possible. ArcelorMittal makes XCarb steel in an electric arc furnace using green electricity and at least 95% scrap. This delivers a 60% reduction in CO2 emissions. We made the 26 steel portals from this XCarb steel. The depot is due to remain in place for five years, which also influenced the choice of steel finish. Coating or galvanising would not be a sustainable solution in this case. We opted for nothing but a bio-based primer from Baril Coatings, in a suitably green colour.”

Offcuts
The unusual façade finish was the idea of architect Bureau van Eig. “Green-painted timber sheet cladding forms the basis of an outer skin made from profile-cut plates, offcuts from the metal industry. These CNC-cut plates are untreated and screwed onto the timber walls. Together with the green walls and portals, they will create a combination that blends in beautifully with the leafy surroundings. A total of 102 plates were used. With their different dimensions and numerous cut-out shapes, they made for quite a puzzle.”
The project was completed in a very short time. Smit concludes: “The first foundation pad for the portals was laid in mid-April this year. By August, the first tram was already sheltering beneath the roof. A fine sustainable project that we have delivered on the Zuidas.”
Vraag over dit verhaal? Stel je vraag
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ThemaMinder CO2 in beton en staal
- OnderwerpSteel


















