Treatment & protection

Silent sand transport

Tekst Roel van GilsFotografie Moors Constructie en machinebouw Bergharen

In het ontwerp is rekening gehouden met de vereisten van het verzinken: er zijn optimalisaties gezocht om de totale constructie zo economisch mogelijk te kunnen verzinken.
In het ontwerp is rekening gehouden met de vereisten van het verzinken: er zijn optimalisaties gezocht om de totale constructie zo economisch mogelijk te kunnen verzinken.

More than 25 million tonnes of sand and gravel will be extracted from the Geertjesgolf sand and gravel pit in Winssen over the next fifteen years to supply construction materials.

Rather than using a large fleet of lorries, the sand is transported from Winssen to Deest via a 2-kilometre-long pipe conveyor. As a regular partner of Moors Constructie en machinebouw Bergharen, Coatinc Mook hot-dip galvanised all the steel frames in just six months, protecting the structure against the elements.

The pipe conveyor is a closed system with two lines, one above the other, and a single-piece belt.

All possible scenarios for transporting the sand over a distance of 2 kilometres were considered for Geertjesgolf, says Barry Moors, director of Moors Constructie en machinebouw Bergharen (MCB). “To minimise disruption to the surrounding area, a conveyor system with a capacity of 1,200 tonnes per hour was soon identified as the best option. Handling this volume would require 60 lorries to make repeated trips. So that was out of the question. A conventional open system was unsuitable because of the many transfer points required and the risk of losing sand and gravel ‘along the way’ due to the effects of the weather. Ultimately, the decision was made to opt for a closed pipe conveyor, which we developed and manufactured entirely in-house.”

The belt opens up during loading and unloading, but as soon as it leaves the depot, it folds into a tube with an internal diameter of 350 millimetres.

Hot-dip galvanising

The pipe conveyor is a closed system with two lines, one above the other, and a single-piece belt. “The belt opens up during loading and unloading, but as soon as it leaves the depot, it folds into a tube with an internal diameter of 350 millimetres,” Moors explains. “This allows us to keep the so-called hexagonal frames, through which the belt runs, relatively small. All the frames are hot-dip galvanised. This was a deliberate choice. As well as giving them a neat, clean finish, galvanising makes them more impact-resistant than a coating. After all, the project is designed to operate for at least fifteen years. You don’t want to have to keep repairing the structure. The hot-dip galvanising was carried out by our regular galvaniser, Coatinc Company, which is well equipped to handle structures of this size.”

Rather than using a large fleet of lorries, the sand is transported from Winssen to Deest via a 2-kilometre-long pipe conveyor.

Running smoothly

Coatinc Company hot-dip galvanised 250 frames, each 12 metres long, in just six months. In total, the project involves almost 600 tonnes of steel, according to Moors. “The design took the galvanising requirements into account. In other words, we looked for ways to optimise the process so that the entire structure could be galvanised as economically as possible. It is essentially a large Meccano set, assembled with bolts and nuts. We use a total of 225,000 M12 x 30 bolts to assemble all the frames. All the steel is hot-dip galvanised, except for the 24,000 rollers. These are powder-coated. It was purely a cost-based decision. They won’t rust anyway, even if the coating wears off. The rollers are constantly in motion, as the conveyor belt runs six days a week, 12 hours a day.”

Coatinc Company hot-dip galvanised 250 frames, each 12 metres long, in just six months.

Most of the frames were hot-dip galvanised by Coatinc Company between May and October last year. “A full lorry was collected and delivered each time,” Moors explains. “We could then assemble the frames in our workshop and install them on site. Following an extensive testing period, the pipe conveyor will be commissioned in June.”   

Vraag over dit verhaal? Stel je vraag

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • OnderwerpTreatment & protection
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.