Projects

Brand-new chemical storage terminal built from 1,112 tonnes of steel

Tekst Tim JanssensFotografie Lucid

De Antwerpse terminal van STANDIC werd in een klein jaar tijd gerealiseerd.
De Antwerpse terminal van STANDIC werd in een klein jaar tijd gerealiseerd.

After Houston in the United States, the Port of Antwerp is the world’s second-largest chemical hub.

It is therefore no surprise that Dutch tank storage company STANDIC commissioned a new storage terminal at the Fifth Harbour Dock. The highly automated complex covers an area of 95,000 m², with tanks ranging in capacity from 500 to 3,500 m³, and was built by ASK Romein using 1,112 tonnes of steel. Excellent collaboration and a positive, constructive atmosphere on site resulted in a successful, sustainable project.

“We supplied and installed the steelwork for eight tank farms, including the walkways, guardrails, plastic grating and stairs,” says Jack van Iersel.

With a storage capacity of 230,500 m³ and 163 tanks in almost every type and size, STANDIC was already the leading name in the Netherlands for storing chemical products, biofuels and raw materials for lubricants. But with the completion of its new terminal in the Port of Antwerp, which adds a total storage volume of 230,000 m³, the company’s capacity has now doubled at a stroke. What prompted this ambitious multimillion-euro investment? Multimodal access and sustainable distribution. Transport by water, both inland and seagoing, and by rail is the ideal way to supply specialist chemical markets quickly, efficiently and with minimal environmental impact. “The Port of Antwerp is one of the world’s largest maritime chemical clusters. That is why we chose to expand in the city on the Scheldt. We hope this will enable us to further develop STANDIC’s specialist storage activities and serve customers from all over the world,” explains Ronald Ooms, director of parent company Hametha.

“We started erecting the steel structure alongside the excavation while the concrete foundations were being poured, allowing us to significantly shorten the project schedule,” says Jack van Iersel.

Major flagship project

STANDIC’s Antwerp terminal was completed by ASK Romein in less than a year. STANDIC project manager Raoul Cootjans had fond memories of a previous collaboration with ASK Romein, so the Dutch tank storage company once again turned to the renowned industrial contractor from Malle. “We also found it a very positive collaboration, so we were delighted that STANDIC entrusted us with this major flagship project,” says Jack van Iersel, project manager at ASK Romein. “We supplied and installed the steelwork for eight tank farms, including the walkways, guardrails, plastic grating and stairs. We also built an 18 x 30-metre building to house all the associated equipment and control systems. No less than 1,112 tonnes of steel were needed to build this highly automated, state-of-the-art terminal.”

“Since some tanks had to be commissioned earlier, we built the terminal in a criss-cross sequence, so to speak”

A complex puzzle

Most new-build projects follow a logical sequence of construction work. That was not the case here, Jack van Iersel points out. “Since some tanks had to be commissioned earlier, we built the terminal in a criss-cross sequence, so to speak. We also started erecting the steel structure alongside the excavation while the concrete foundations were being poured, allowing us to significantly shorten the project schedule. We did this despite having only a few metres of space between the quay and the foundations, some of which also had to remain accessible to construction traffic. We then lifted the pipe racks into position in one operation using two cranes and installed them, together with the stainless steel pipes, which we also fitted. We regularly met with the other contractors and subcontractors to work out the complex construction and logistics puzzle. Thanks to the positive, constructive atmosphere on site, we succeeded brilliantly! Everyone was motivated to go the extra mile. Both STANDIC and we are extremely satisfied with the result.”  

Client
Hametha (Oosterhout, the Netherlands)

Main contractor(s)
ASK Romein (Malle)

Vraag over dit verhaal? Stel je vraag

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • OnderwerpProjects
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.