Mobility demand in the Randstad continues to grow, doing nothing was not an option
Tekst Jerry HelmersFotografie Jerry Helmers en Rijkswaterstaat

It may well be Rijkswaterstaat’s biggest restructuring project at present: widening the A9 between Badhoevedorp and Holendrecht, near Amstelveen and Ouderkerk aan de Amstel. Optimising Amsterdam’s ‘Second Ring’ is the final phase in a series of upgrades to the A9 between Amsterdam/Schiphol and Almere. “If we didn’t upgrade the road network here, the Randstad would grind to a halt,” says Lammert Postma, stakeholder manager at Rijkswaterstaat.
A9 restructuring near Amstelveen in the spotlight

In brief: the A9 is being widened from 2×3 to 2×4 lanes; three sections of the motorway near Amstelveen are being covered over; the motorway itself is being lowered; all noise barriers are being replaced with new, taller ones; and low-noise, two-layer ZOAB-fijn asphalt is being laid.
“The population in this part of the Randstad is growing rapidly. Employment is also expected to increase, so we can expect major mobility challenges to persist,” says Postma. “This section of the A9 is therefore a vital link. Of course, the project will give Amstelveen’s liveability a major boost. The north-south connection will be improved, and the motorway will no longer be seen as an intrusive barrier. Noise pollution will be reduced, and the Oude Dorp will once again be able to become a cultural hotspot, with plenty of green space and hospitality venues. So it’s not just motorists who stand to gain: local residents will benefit too.”

Three challenges
According to Postma, the project presented three major challenges. “First, we have a duty to ensure that motorists can continue to use the A9 throughout the construction work. Any disruption is a step backwards. We also need to keep the impact of the works on Amstelveen residents as acceptable as possible. Ideally, there should be no disruption at all. And some sections of the route have exceptionally poor ground conditions. How do we deal with that?”
Postma explains that several properties had to be purchased, mainly farms and homes, to make room for the widening. “VeenIX, the construction consortium, also came up with the so-called DDI (Diverging Diamond Interchange) at Amstelveen. We can now accommodate all traffic flows using just 50% of the space. It also came up with a good plan for a bypass, the ‘temporary A9’, which is now located south of the old central reservation. This ensures traffic continues to flow. It goes without saying that we didn’t rush into this. Major organisations and businesses are based in the area, including the Johan Cruijff ArenA, AMC and ZiggoDome, all of which depend on good traffic flow, especially when events are taking place. And you certainly don’t want a surgeon arriving late for an operation at AMC. We were sitting down with all the stakeholders from day one. There are an incredible number of interdependencies and interests here.”
Water management
Dealing with the poor ground conditions, particularly near Ouderkerk aan de Amstel, proved a challenge for Madrid-based Spanish company FCC. It is part of the VeenIX construction consortium, which won the European tender. “There is a lot of peat soil around the A9, as well as many small polders whose water management must be maintained. During the works, we need to prevent the beds of the ditches alongside the A9 from ending up higher than the surrounding ground. There are sixteen polders around Amstelveen.”

However, an important change was made during the process. “The original decision to build a tunnel was changed to a 1.6-kilometre sunken road with three covered sections. To keep the noise levels for the surrounding area in line with those of the (hypothetical) tunnel, where ‘you will be less affected by the new A9’, we had to install high noise barriers and lay the new, quiet, double-layer ZOAB-fijn asphalt. This brought us back into compliance with the Environmental Nuisance Act, which sets the maximum noise level permitted at your façade.”

Sustainability
In today’s climate, sustainability issues are of course unavoidable. Postma says: “Naturally, we asked ourselves what to do with the old concrete, for example from the A9 viaduct over Keizer Karelweg. We have a duty, including as Rijkswaterstaat, to consider recycling. We were able to organise the reuse of the concrete bridge beams effectively. They have been dismantled and are now being used, among other things, in a viaduct in Limburg, where they will be placed on a solid foundation. I think this is a good example of Cradle-to-Cradle, and it means we have avoided producing new concrete for those other locations in the Netherlands. That’s sustainable practice!”
“This section of the A9 may well also be one of the most energy-efficient motorways in the country,” says Postma. “Solar panel arrays are being installed at two locations. They will supply all the energy needed for the street lighting, the matrix signs and operating the Schipholburg for shipping.”
The kilometres of sheet piles naturally required a large quantity of steel to build a stable structure. “All the steel came from Ukraine. That is more difficult now. Everyone knows why. We are now literally looking all over the world for more steel. What I am particularly proud of are the steel bridge leaves for the new Schipholbrug. They are the largest movable bridge leaves built by Rijkswaterstaat in the Netherlands. But let’s be honest: motorists ultimately just want to get from A to B as quickly and safely as possible. And that’s what they’ll be able to do.”
The new A9 near Amstelveen is expected to be completed in 2027.
Vraag over dit verhaal? Stel je vraag
Wie aan Verbreding A9 tussen Badhoevedorp en Holendrecht werkte
- bouwconsortiumVeenIXIn dit verhaal
- bouwconsortium VeenIXFCCIn dit verhaal
- scan- en boorspecialisten
Interboor MidslandGenoemd in Widening the Schipholbrug: precision drilling and bonding between parabolic prestressing tendons - technisch adviseurWitteveen+BosGenoemd in Queen Máxima visits circular projects: A9 widening and Asphalt Recycling Train (ART)
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectVerbreding A9 tussen Badhoevedorp en Holendrecht
- OnderwerpFoundation techniques
- BedrijfVeenIX
- BedrijfFCC


















