Significant time savings with state-of-the-art foundation techniques
Tekst Philip DoutreligneFotografie Votquenne Foundations

Since its foundation in 2006 by civil engineer Bart Cloet, Votquenne Foundations has grown into a leading player in foundation and shoring techniques. Alongside the manual foundation techniques offered by its sister company Votquenne, Votquenne Foundations specialises in machine-based foundation techniques. The company now employs 45 people and has its own transport company, VQ Logistics, and a spin-off, Revyson, which carries out site investigations and drilling.
Two of its recent projects deserve particular attention. The first, commissioned by Alinso/Willy Naessens Industriebouw nv, involves foundation work for a building that will be used by Johnson & Johnson as part of its first European cell therapy production centre in Belgium, a new way of treating cancer. The second project is Bellecour Residence, a prestigious complex of 98 apartments with a three-level underground car park in the centre of Braine-l’Alleud.

Exceptionally stringent safety requirements
Janssen Pharmaceutica, a subsidiary of Johnson & Johnson, will begin developing treatments for blood cancer at its new facility in Zwijnaarde/Ghent Technology Park in 2023. The foundation work had to meet exceptionally stringent safety requirements, which are fully in line with our commitment to VCA standards. To improve safety on all its sites, Votquenne Foundations also regularly commissions external audits. The annual VCA audit once again confirmed that safety is a priority on site and that the company’s efforts in this area are one of its strengths.
Transport presented an additional challenge. The two LRB355 foundation machines, each weighing 130 tonnes, had to be completely dismantled and reassembled on site, a task never before carried out in Belgium. The site could only be accessed via several bridges that could not support such a total weight. Revyson, a sister company that operates entirely independently, carried out the additional ground investigations and site surveys required. The project is being directed by several engineering and inspection firms, with a particular focus on minimising settlement. This means only the largest piling rigs are suitable for carrying out the demanding drilling work. The foundation work comprises the installation of 1,700 screw piles and floor piles to a depth of 18 metres. Work began in mid-October this year and is due for completion by the end of January 2022.
A new landmark in the heart of the town
Bellecour Residence is an apartment building rising in the centre of Braine-l’Alleud, on the site of the former Royal Athenaeum. Votquenne Foundations carried out all the foundation work. It installed over 300 linear metres of secant pile walls, with piles extending to a depth of 18 m. This required the company’s most powerful foundation machine, the 130-tonne LRB355.
It also installed over 375 cased piles and 2 to 3 rows of anchors up to 21 m long, a total of 400 across 2 to 3 levels. A further 50 linear metres of Berlin walls were installed. Given the central location in the town, disruption to the surrounding area had to be kept to a minimum. Speed and efficiency, two of Votquenne Foundations’ strengths, were therefore crucial, requiring the use of compact yet powerful machines.
Key considerations for Votquenne Foundations on this site included working speed, the strict schedule, the comprehensive engineering design and the specialist techniques available in-house, enabling the company to respond quickly and appropriately in every situation.

Short construction periods
Votquenne Foundations prides itself on consistently guaranteeing the shortest possible construction periods. This is due in part to the expertise and professionalism of its staff, the availability of the most efficient machines for each job and the integration of various project stages within the company. For Bellecour, it needed just 30 working days to install the secant pile walls, 20 working days for the anchors and 20 working days for the piles. The Alinso project will take barely 3 months.
Een zakelijke vraag aan Willy Naessens Group? Neem contact op
Bedrijven in dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- OnderwerpFoundation techniques
- BedrijfWilly Naessens Group



















