Projects

2,100 m3 poured in a weekend

Text Tjerk van DuinenImage Verboon Maasland, Mobilis

“In total, we used grabs to remove 1,200 cubic metres of contaminated sediment from the excavation and dispose of it under controlled remediation conditions.”
“In total, we used grabs to remove 1,200 cubic metres of contaminated sediment from the excavation and dispose of it under controlled remediation conditions.”

Steel-fibre-reinforced underwater concrete floor for RIF010

Removing contaminated material and excavating a wet construction pit, followed by pouring an underwater floor using steel-fibre-reinforced concrete, is nothing out of the ordinary for Verboon Maasland. The location is another matter: a canal in the heart of Rotterdam, where RIF010 is being built. A great project for Tom Maaskant, project manager for Specialist Projects at Verboon Maasland, which is responsible for creating a clean, solid base for this wave pool. The work was carried out in close collaboration with main contractor Mobilis, foundation contractor Kandt bv and diving company DISA International.

The gravel layer was surveyed from a boat using a multibeam system and converted into a digital terrain model.

Verboon Maasland was able to start work as soon as Kandt had completed the sheet-pile walls around the wet construction pit. Maaskant: “The first part of our task was to remove the layer of contaminated sediment from the canal bed. In total, we used clamshell buckets to remove and dispose of 1,200 m3 of contaminated sediment from the pit under remediation conditions. The peat and clay layers in the construction pit were excavated separately using GPS. The cofferdams were then cleaned and the bed cleared of silt. This last step was a major challenge, as there was no possibility of creating a wet stockpile in the area. Thanks to the expertise of our team, we ultimately completed the work on schedule. During excavation, a diving team from DISA International carried out bed and civil engineering inspections on our behalf. This was no easy task, as visibility was only 30 cm. Archaeological samples were also taken in between, a mandatory part of the process in this area. Fortunately, we didn’t come across an old city wall.”

2,100 m3 of steel-fibre-reinforced concrete was poured in just under a day and a half.

Spread in a single pass

To save time, excavation of the construction pit was carried out in stages and in close collaboration. Maaskant: “We started excavating on the Markthal side, where the cranes were unloaded. Once there was enough safe working space, Kandt started installing the piles behind us. With good coordination, you can avoid getting in each other’s way, even when working with heavy equipment in a small space like this construction pit. With some of the piles in place and part of the pit cleared down to the base, our diving team could remove grout residue from the piles and clean them thoroughly. The pit was then ready for the gravel to be spread. The 30 cm-thick gravel layer traps any remaining silt, preventing it from mixing with the underwater concrete and compromising its quality. The gravel was spread using a wide bucket and the same machines used for excavation. During spreading, levels were checked manually with a sounding line to provide an immediate result. The entire pit was covered in a single pass, within tolerance. This was no easy task on a bed with slopes and changes in angle.”

Digital terrain model

Before Verboon Maasland could begin pouring, divers first measured all pile heights and positions, and Verboon used a multibeam system to convert the gravel layer into a digital terrain model. A number of reinforcing cage strips were then welded to the piles underwater, and anchors were attached to the sheet-pile walls to prevent the concrete from pulling away from them. In addition, the sheet piles at the interface with the underwater concrete floor were thoroughly cleaned with a high-pressure washer to ensure the best possible bond. 

The peat and clay layers in the construction pit were excavated separately using GPS.

Steel-fibre-reinforced concrete

“Only once you’ve ticked off the entire checklist are you ready to pour the underwater concrete floor,” says Maaskant. “The pour started at four o’clock on Friday afternoon and continued until just after midnight on Saturday. That’s 2,100 m3 of steel-fibre-reinforced concrete in just under a day and a half. The concrete has a strength class of C30/37 and contains 30 kg/m3 of steel fibres. You can pour a maximum of 80 m3 per hour, otherwise you risk the steel fibres getting stuck in the pipes. The entire 75 cm-thick floor was poured in one go, within tolerance.”

“That was the end of our work,” the project manager concludes. “The follow-up measurements from the monitoring instruments showed that the concrete was curing as expected. We’re proud to have laid a strong foundation for this remarkable project in such a challenging environment.” 

A business enquiry for Kandt Aannemings- en Funderingsbedrijf BV? Get in touch

Who worked on the RIF010 wave pool

  1. clientStichting RiF010Mentioned in Surfing in Rotterdam city centre
  2. architectMorfis Architecture & UrbanismMentioned in Surfing in Rotterdam city centre
  3. main contractorMobilisMentioned in Surfing in Rotterdam city centre
  4. structuresWSPMentioned in Surfing in Rotterdam city centre
  5. sheet pilingKandt bvMentioned in Teamwork and preparation take centre stage
  6. wave systemHellebrekersMentioned in Surfing in Rotterdam city centre
  7. diving companyDISA InternationalIn this story
  8. Groundworks contractorVerboonMentioned in Teamwork and preparation take centre stage
  9. Development2D VastgoedMentioned in Surfing in Rotterdam city centre
  10. DevelopmentGemeente RotterdamMentioned in Surfing in Rotterdam city centre
  11. Wave systemsD. Bastenhof ConsultancyMentioned in Surfing in Rotterdam city centre
  12. Surf pool designSurflochMentioned in Surfing in Rotterdam city centre
  13. SteelworkBuchinhorenMentioned in Surfing in Rotterdam city centre

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectRIF010
  • SubjectProjects
  • CompanyDISA International
  • CompanyKandt Aannemings- en Funderingsbedrijf BV
Share this article

Advertisement

Follow on Beton & Staalbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.