Projects

Drilling and sawing specialist Stenabo cuts lock wall into 12 sections

Drilling and sawing specialist Stenabo cuts lock wall into 12 sections

As a specialist in concrete drilling and sawing, Stenabo provided specific support for the repair work required at the Berendrecht Lock.

Herbosch-Kiere carried out the repair work required at the Berendrecht Lock on behalf of Havenbedrijf Antwerpen. Stenabo provided specific support as a specialist in concrete drilling and sawing. One of Stenabo’s notable tasks was to cut the damaged concrete wall into sections to make it easier to remove. “This was certainly no ordinary project, especially given the time pressure and tight deadline,” says Raoul Nabarro, project manager at Stenabo.

The lock wall, which was damaged in December last year, could not be removed in one piece. Stenabo was called in to make the task manageable. Its employees used a wire-sawing machine to divide the large concrete lock wall, measuring 16 by 7 m, into 12 smaller sections. Raoul Nabarro explains: “A machine like this uses a steel cable studded with synthetic diamonds. The cable is fed through a pre-drilled hole in the concrete and pulled upwards, creating the cut. Some sections still weighed 34 tonnes. A 280-tonne crane lifted the concrete sections and placed them on a pontoon in the water.”

Met de PlanDesk 360 Project Manager, op elk moment, op elke plek en op elke hardware inzicht in uw projecten.

The concrete drilling company from Kapellen worked continuously, 24 hours a day, for 10 days on this drilling and sawing assignment.

Creating space

Stenabo takes various factors into account when deciding how to carry out the work. “This is usually done in consultation with the client and/or main contractor, in this case Herbosch-Kiere,” says Raoul Nabarro. “We always look at the equipment available on site. For this project, there was a crane and a pontoon, which meant we could saw fairly large sections. In principle, we can cut sections weighing more than 34 tonnes, but that was not an option for the work at the Berendrecht Lock. The largest sections were under a bridge. The bridge was raised by a few centimetres to create enough space, but with even larger and heavier concrete sections, it would have been almost impossible to get them safely out from under the bridge and lift them onto the pontoon.”

Stenabo encountered no technical surprises during the repair of the Berendrecht Lock, but it was certainly no ordinary project. “The sawing itself is done by experienced people, but the setting is always different. That makes it interesting and challenging. Working on a lock is always a unique experience. From inside the dry dock, we sawed a section that is normally underwater. Even the thought of that is remarkable. On the inside of the lock, we had to take the lock’s structural work into account. The setting was quite unusual, including because the bridge had been jacked up.”

Stenabo

The large concrete lock wall, measuring 16 by 7 m, was divided into 12 smaller sections using a wire-sawing machine.

A special project

In addition to the concrete drilling and sawing, Stenabo’s team also carried out the chemical anchoring, enabling new reinforcing steel to be installed in the side walls and floor. The concrete drilling company from Kapellen worked continuously, 24 hours a day, for 10 days on this drilling and sawing assignment. “As a subcontractor, we regularly work on projects such as quay wall renovations. But repairs to a lock wall are relatively rare. This is an important part of the port infrastructure, essential to the smooth operation of the Port of Antwerp. That is also what makes this project so special for us,” explains managing director Stefan Nabarro.
Raoul Nabarro agrees: “We are always very proud of projects like this. Time pressure was certainly a challenge here, but because other sites had ground to a halt due to coronavirus, we were able to carry out the necessary preparatory work for the Berendrecht Lock. As a result, the work itself also went very smoothly. Communication with Herbosch-Kiere was very positive too. Working in shifts for 10 days, 24 hours a day, is very demanding and can take its toll, but the collaboration remained well coordinated throughout.”

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Berendrechtsluis in Antwerpen

  1. opdrachtgeverHavenbedrijf Antwerpen
  2. aannemerHerbosch-Kiere
  3. onderaannemerStenabo

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectBerendrechtsluis
  • OnderwerpProjects
  • BedrijfHavenbedrijf Antwerpen
  • BedrijfHerbosch-Kiere
  • BedrijfStenabo
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.