Van der Valk Exclusief Woerden is a hotel for the next generation
Tekst Tjerk van DuinenBeeld P.A.M. Teunissen Architectenbureau & Tjerk van Duinen

Plans for a Van der Valk Exclusief hotel in Woerden date back to 2018. Five years of preparation, planning, navigating procedures and meetings later, an agreement was finally reached with the municipality to build a new hotel for the hospitality group close to the A12. Naturally, it is a prime site with excellent visibility, something the family has a knack for securing. The first pile was driven into the marshy ground in October 2023, and the first guests are expected in spring 2026 at the hotel, which has seven, no, eight, or perhaps ten storeys in the longer term.
Van der Valk Woerden consists of a wide, two-storey podium housing the lobby, a wellness area with a gym and swimming pool, a large restaurant and a conference centre. A tower containing the hotel rooms rises above it. “The initial plan was for 125 rooms, with the option to expand later,” says Rik van der Valk, who forms the management team with his sister Nikki. “Covid led to steep price increases and, as a result, a different business case. To recoup the additional investment, we discussed the possibility of adding extra floors with the municipality and neighbouring businesses. During construction, we received planning permission for an additional storey, bringing the total to 144 rooms. The tower may gain another two storeys in the longer term, as the structure has been designed to accommodate them. For now, we’ll see how things go here and focus on making money.”

Curved forms
The hotel differs from most other Van der Valk properties. “It’s similar to Deventer (completed in 2021; ed.), but with rounded corners,” Van der Valk continues. “It was designed by our in-house architect Teunissen, and I think the result is excellent. The curved forms are also echoed inside, for example in the swimming pool. The layout and guest experience also draw on everything we’ve learnt from our other hotels. Each new one is the best yet. We’re building for the next generation of guests and their modern expectations, so the hotel will serve us for decades and can then pass to the next generation. I’m also learning a great deal from the entire construction process. I’m mainly overseeing the structural work myself, while Nikki and my sister-in-law Amber are handling the interior. I can always turn to my parents for advice.”

Keeping flexibility
Project planner Arnoud van Broekhoven and site manager Maarten Bolle know that Van der Valk is no ordinary client. Both work for contractor Van Omme & De Groot and have already delivered a number of Toekan hotels. Nineteen years ago, in 2005, Nootdorp was Van Broekhoven’s first project, and also the first in the Van der Valk Exclusief series. Bolle has worked on a succession of new-build projects and extensions since 2007. “You soon learn that things can change along the way,” Van Broekhoven begins. “Van der Valk wants to retain flexibility for as long as possible, because the market can change quickly, whereas we prefer to have everything agreed as soon as possible. Much of the value we bring lies in the considerable flexibility we can offer. In return, we have a fair amount of freedom to develop and optimise the designs.”

Pile caps
The foundations are supported by piles driven to depths of 12.5 to 18 metres. Pile caps, beams, lift pits and the swimming pool were constructed on top, followed by the basement floor. Bolle: “The water board allowed us to pump out a maximum of 100 m3 per hour, which meant we couldn’t build the swimming pool shell and a large pile cap beneath the lift pit at the same time. We had to adjust the programme and site logistics accordingly. From ground-floor level onwards, we split the high-rise and low-rise sections into separate workstreams.”
The structural frame combines in-situ and precast concrete. The foundations, basement floor, walls and columns were cast in situ. The stairs, landings, lift shaft walls, balcony slabs and parapets were precast. The upper floors were built using lattice girder slabs. To create a column-free conference hall, 40 cm thick, 14.70 m long hollow-core slabs were used, topped with an 8 cm concrete topping. Bolle: “The square columns were formed using conventional formwork, while the round columns, up to 7 metres long, were made using Monotube. Concrete classes range from C50/60 for the 80 cm thick columns on the lower floors to C30/37 for the 50 cm thick columns on the upper floors. Slaman van der Zwet set up an impressive production line for the hotel floors. The extra storey, which was added mid-project, was even completed within the structural work period originally planned.”

Parapets
Precast parapets with vertical brick slips are used at ground, 1st and 2nd-floor level. They are fixed to the floor edges with heavy-duty angle brackets. Van Broekhoven: “On the 3rd and 8th floors, precast balcony slabs, complete with parapets, were cast into the floors using Isokorven connectors. The parapets were made in the factory beforehand and then placed upside down in the balcony slab moulds. After the balcony slabs had been cast, they were turned through 180°, allowing us to lift them straight from the lorry into position on site. If one or two extra floors are added later, the precast roof slabs with their cast-in parapets can be cut off at the Isokorven connectors and moved up to the top floor. A steel frame will then need to be built to support them.”

Tanks
During the structural phase, building services contractor Linthorst came up with an idea: install a few hot-water buffer tanks in or beside the building, fill them when there is surplus electricity or energy is cheap, and use the stored hot water during peak demand, between 6 and 7 pm, with only a small amount of additional heating. “With a payback period of ten to twenty years, Van der Valk initially agreed to the idea,” says Van Broekhoven. “We then proposed using the unused space beneath the terrace. By lowering the foundation beams under the terrace slightly and continuing the basement floor beneath it, we created the perfect space for the tanks. Because of the 8.5 m-long tanks’ delivery time, the ground-floor slab had to remain open until they arrived. Given the tanks’ large diameter, around 3.20 m, we decided to use hollow-core slabs for the ground floor above them. Van der Valk then changed its mind and switched back to lattice girder slabs, only to agree again three weeks later. Just in time to include the hollow-core slabs.”

Logistics
The hotel is now at the façade-closing and fit-out stage. Plans can change at this point too. Van Broekhoven: “The shaft walls were originally to be built entirely from calcium silicate blocks. Since the shafts can only be closed at a later stage, by which time the dry fit-out will be well under way, you don’t really want to be laying and plastering calcium silicate blocks as well. It was also impractical from a logistics point of view, as the blocks would have had to be brought up using a construction hoist. So, in consultation with Van der Valk, we decided to use dry construction with metal stud walls. The wall between the rooms and the shafts is still made of calcium silicate blocks. The bathroom and toilet walls are made from Ytong panels, which were delivered to the floors during the structural phase.” Standing beneath the impressive steel structure of the main entrance, Bolle and Van Broekhoven look forward to the rest of the project with confidence. “Once you’re used to working for Van der Valk, you’re not easily caught off guard, and you come to appreciate the freedom to get on with the work. We’d be happy to have another client like this.”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Van der Valk Exclusief Woerden in Woerden
- opdrachtgeverVan der Valk
- ontwerpP.A.M. Teunissen Architectenbureau
- adviseursPieters Bouwtechniek
- staalconstructiesPiso
- hoofdaannemerVan Omme & De Groot
- installatiesLinthorst Techniek
- installatiesBenschop Installatietechniek
- betonwerkSlaman van der Zwet
- prefab betonLammers Beton
- staalLuiten Staalconstructies
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectVan der Valk Exclusief Woerden
- OnderwerpProjects
- BedrijfVan der Valk
- BedrijfP.A.M. Teunissen Architectenbureau
- BedrijfPieters Bouwtechniek
- BedrijfPiso
- BedrijfVan Omme & De Groot


















