Searching for hidden damage to prestressing in the Faroe Islands

Text Roel van GilsImage Nebest

The Streymin-brug is a distinctive crossing over the Streymin river in the Faroe Islands, which flows into the Atlantic Ocean.
The Streymin-brug is a distinctive crossing over the Streymin river in the Faroe Islands, which flows into the Atlantic Ocean.

The Faroe Islands are home to Streymin Bridge, a striking link between two islands spanning the River Streymin, which flows into the Atlantic Ocean. A routine inspection identified concrete damage and corroding reinforcement in the bridge girders. Although this damage was not directly related to the prestressing, its combination with the age of the bridge prompted the asset manager to commission further investigation. This was all the more important given that incidents such as the bridge collapse in Dresden have once again highlighted how critical the condition of prestressing can be. Experts from Nebest were flown in to investigate the prestressing.

Streymin Bridge dates from the 1970s, has nine spans and is approximately 220 metres long. The bridge deck comprises 54 concrete girders with internal prestressing. “In a prestressed structure, a significant part of its load-bearing capacity lies deep inside the concrete,” says Remco van Osch, a specialist in non-destructive concrete testing at Nebest. “So you cannot simply see its condition from the outside, even if one or more tendons are on the verge of breaking. And if something goes wrong, the consequences are serious. Recent incidents in Dresden and Genoa have clearly demonstrated that.”

Op zoek naar verborgen schade aan voorspanning op de Faeröer Eilanden

Ultrasonic testing

Nebest combined several techniques to investigate the prestressing. “First, we used radar to map the prestressing ducts,” Van Osch explains. “We then used ultrasonic pulse-echo measurements to examine the ducts for voids in the grout. The measurements were assessed using advanced phase analysis. This allows us to determine whether the ducts have actually been properly filled. Poorly grouted prestressing ducts carry an increased risk of corrosion to the high-strength prestressing steel.”

Op zoek naar verborgen schade aan voorspanning op de Faeröer Eilanden

Inspection openings

Nebest carried out a representative sample survey on approximately 15 per cent of all the girders. “Where the measurements indicated a need, we followed up with small-scale destructive testing,” says Gert Wilgenburg, a concrete testing consultant at Nebest. “In total, we made around 44 inspection openings.” Van Osch adds: “It is a bit like going to the dentist. First you take an X-ray, then decide where to look more closely. There is no need to open up every girder completely.” The inspection openings were used to check, among other things, the condition of the prestressing steel, any breaks and voids in the ducts. After inspection, the openings were repaired and protected.

Nebest combineerde bij het onderzoek naar de voorspanning verschillende technieken.
Nebest combined several techniques to investigate the prestressing.

Asset management decisions

The combination of visual inspection, radar, ultrasonic testing and inspection openings provided crucial information. “We provided our findings to the asset manager so that the structural engineer can use them to recalculate the bridge,” says Wilgenburg. “This will form the basis for the repair plan.” Nebest carried out the measurements in June 2026 and submitted its report to the bridge’s asset manager at the end of August.

Op zoek naar verborgen schade aan voorspanning op de Faeröer Eilanden

Preventive investigation

The issues investigated in the Faroe Islands are also relevant closer to home. “Many prestressed bridges in the Netherlands are now between fifty and eighty years old. Structures built in the 1960s, 1970s and 1980s deserve particular attention. Prestressing was still developing rapidly during that period, and experience was being gained with techniques such as grouting prestressing ducts,” says Van Osch, drawing on his experience. He advises: “Do not wait until damage appears on the outside. By then, it may already be too late. Just as you have periodic X-rays at the dentist to detect problems early, we should also carry out further investigations of prestressed bridges as a preventive measure.”

Work is now under way in the Netherlands on a guideline intended to provide asset managers and engineering firms with clearer guidance on investigating prestressed bridges. Streymin Bridge shows why this development is needed: sometimes the most important part of a bridge is precisely the part you cannot see.

A business enquiry for Nebest BV? Get in touch

Who worked on it

Streymin-brug

  1. research into prestressingNebest

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectStreymin-brug
  • ThemeMaking bridges and civil structures last longer
  • SubjectProjects
  • CompanyNebest BV