From milestone to milestone, with the surrounding community in mind
Tekst Roel van GilsBeeld Sjaak Boot Photograpy, TopView Luchtfotografie

Construction of the new A16 Rotterdam has entered its final phase. The De Groene Boog construction consortium is reaching one milestone after another. No sooner has one been reached than the next comes into view. The importance of community engagement on a major project like the A16 Rotterdam is beyond doubt. And De Groene Boog has certainly mastered it. Receiving no complaints from the surrounding community after the “open-heart surgery” over the long Ascension Day weekend is a considerable achievement.
Commissioned by Rijkswaterstaat, Dura Vermeer, Mobilis, Croonwolter&dros, BESIX NL, Van Oord, Rebel and John Laing are jointly responsible for the design, construction, financing and 20 years of maintenance of the A16 Rotterdam. “The works over the recent Ascension Day weekend were initially much smaller in scope,” says Jeroen Toet, project manager for Mobilis at De Groene Boog. “We were ‘only’ going to have to slide the new structure into place on the new slip road towards the A16 (KW52B). Eventually, the viaduct over Hoofdweg (KW58) was added. An inspection had established that the structure was at the end of its service life and that it would be irresponsible to keep using it. It therefore had to be replaced, which significantly expanded the scope at that point. Because it is located in the middle of the A16, it is vital to replace the structure with as little disruption as possible. The first steps were taken over the King’s Day weekend and later over the Ascension Day weekend.”

A mammoth task
KW58 lies at one of the most important and busiest junctions on the national motorway network. “It is impossible to close the A16 for an extended period. We therefore devised a plan with Rijkswaterstaat to divert traffic over temporary bridges, then build the new viaduct between them. The temporary bridge for southbound traffic was assembled away from the traffic flows and brought into use over the King’s Day weekend. On the eastern side, the temporary bridge was slid into place over the Ascension Day weekend, for which part of the existing viaduct was demolished that same weekend. It was a mammoth task with a major impact on the surrounding area and through traffic because of a 4-day closure of the northbound A16.”

Construction disruption
Work continued 24 hours a day for four days over the Ascension Day weekend. “That meant demolition in the middle of the night with seven machines, driving sheet piles by vibration, installing foundation piles and so on,” says Paul Eijking, community relations manager for Mobilis at De Groene Boog. “Given the nature of the work, we prepared the immediate community thoroughly for the construction disruption that might arise. Based on the expected noise levels, we also offered around 50 addresses the opportunity to spend several nights in a hotel. In the end, seven addresses took up the offer.”

Slip road closed for eighteen months
Bringing the temporary bridges into use also means that a major slip road onto the A16 will be closed for eighteen months. “Together with Rijkswaterstaat, the municipality of Rotterdam and Zuid-Holland Bereikbaar, we have been working since March 2023 to alert the surrounding community and visitors, including regular visitors, to nearby businesses,” says Eijking. “And that has certainly paid off.” The 4-day closure over the Ascension Day weekend was also widely publicised. “Even the national media covered it,” says Toet. “The impact of interventions like this is enormous. The signage plan for the temporary diversion routes that weekend alone demonstrated that, extending almost as far as Amsterdam. And when an operation like that brings no complaints from the surrounding community, you know everyone has done a good job.”
Military operation
The work over the Ascension Day weekend was therefore prepared almost like a military operation, says Toet. “The volume of activity that weekend was enormous: it was like an anthill. An organised anthill, mind you. You can only achieve that if cooperation within the construction consortium and with all the subcontractors is at its best. That also enables you to deal with any setbacks together. And when the road then reopens half an hour earlier than planned, all we can say is that it went well.”
The next milestone is already in sight. “At the end of this year, the first newly built section of KW58 will be brought into use, after which the eastern section will be built at a rapid pace, to be completed in September 2025. So we are moving rapidly from milestone to milestone, getting ever closer to the project as originally envisaged for completion. And we continue to keep the surrounding community informed throughout.” Eijking concludes: “The community knows what is going to happen, who to contact and what impact the work will have during each phase. We will continue to do that until the very end.”
Vraag over dit verhaal? Stel je vraag
Wie aan de nieuwe A16 Rotterdam werkte
- bouwcombinatieDe Groene BoogIn dit verhaal
- bekistingsspecialist
DokaGenoemd in Special formwork and steel frames for viaduct over busy motorway interchange - bouwcombinatieBouwcombinatie de Groene BoogGenoemd in Special formwork and steel frames for viaduct over busy motorway interchange
- aannemerMobilisIn dit verhaal
- aannemerBESIX NLIn dit verhaal
- aannemerVan OordIn dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectA16 Rotterdam
- OnderwerpProjects
- BedrijfDe Groene Boog
- BedrijfMobilis
- BedrijfBESIX NL
- BedrijfVan Oord


















