Projects

New underpass to improve traffic flow and safety

Tekst Ramona KezerFotografie ProRail/Mobilis-Hegeman

De onderdoorgang komt op de plek van de oude overweg.
De onderdoorgang komt op de plek van de oude overweg.

On behalf of ProRail, the Mobilis-Hegeman contractor consortium is currently building the Ouddiemerlaan railway underpass in Diemen. The old level crossing caused dangerous situations and delays for road traffic. Construction began in August 2020, and the project is due for completion in early 2023. 

The P&R facility is on the left, the diverted Ouddiemerlaan in the middle and the excavation for the Ouddiemerlaan underpass, with its props (steel tubes), on the right.

The Ouddiemerlaan is a key access road for Diemen, which is surrounded by numerous roads and railway lines. Luuk van Hengstum, project manager at ProRail, says: “Previously, there was a level crossing with a station platform on either side at Diemen station. This constrained train traffic and caused delays for road traffic. It was therefore decided to replace the crossing with an underpass. There was no room to relocate it, and the municipality wants to develop the area further. The underpass will therefore be built where the existing crossing was.”

Work continued overnight during the railway possessions.

Tendering

A project of this scale involves a range of stakeholders. Alongside ProRail, the municipality, the Ministry of Infrastructure and Water Management and NS are also involved. The plans were developed further in collaboration with an engineering consultancy. Van Hengstum says: “A tender was held, and in summer 2020 we were able to award the contract to the Mobilis-Hegeman consortium, which has extensive experience with projects of this kind. We call them structures. The consortium applied for the permits and began building a new P+R facility and relocating the level crossing. This also required a diversion road. The railway deck was then built and moved into position during a railway possession, and construction of the tunnel began. The final stage will be fitting it out with lifts, bicycle racks, tiles and benches, as well as creating an ecological zone along the railway. The new underpass will open in early 2023.”

The project began at around the same time as coronavirus emerged in the Netherlands. Jaap van Beek, project manager for the Mobilis/Hegeman construction consortium, says: “Working from home had a considerable impact, particularly during the preparation and design phases. We are proud that we were able to complete these phases successfully despite that. These challenges have had less of an impact during construction.”

Work in progress.

Unsafe situations

The new underpass will also serve as a station. It will include platforms, a station square, lifts, stairways and NS ticket gates, including cabling and security systems. To create an attractive, green slope, the tunnel sections will be widened beyond the railway. The underpass will have two traffic lanes, a cycle path and a footpath. Van Hengstum says: “Traffic on that line was getting busier, and many schoolchildren have to cross it, which could lead to unsafe situations. That is why we opted for an underpass.”

To prevent disruption to road users and rail passengers, temporary facilities were installed during three weekend railway possessions. Van Beek says: “During those weekends, the crossing was relocated after the platform, platform canopy and noise barriers had been demolished. The excavation and piles were also installed beneath the railway, and the railway deck was moved into position. Our partner Volker Rail carried out all the track work and work on cables and pipelines during those weekends, including relocating the technical room. We had around a hundred people working at the same time. These are exciting and important moments: trains have to be running again on Monday morning. As a project team, we are proud to have completed this successfully, and ProRail was very satisfied too. Thanks to the exceptionally thorough preparation, everything went smoothly.”

Construction of the tunnel itself began last September. Van Beek says: “We are consistently on schedule, which is no small achievement for a project with a three-year period from contract award to completion. We have also had no problems with material deliveries. We plan carefully and place orders in good time.”   

Moving the railway deck into position.

Subsidy for sustainable concrete

Sustainability plays a major role in construction. A subsidy for sustainable concrete was made available for this project. Van Hengstum says: “The contractor had experience with sustainable geopolymer concrete, but the technology was not yet fully developed. We are using the subsidy to test geopolymer concrete on this project in accordance with the new draft guidelines for binders. This type of concrete will eventually be available for use by other parties too, helping them achieve better scores against environmental requirements. I expect it to become a standard concrete type for our projects within a few years.”

This sustainable concrete uses geopolymers, which perform the same function as cement, in place of cement. Cement extraction and production have a significant environmental impact. However, this innovative solution does have one drawback, Van Beek explains. “The challenge with geopolymer concrete is that it takes longer to harden, so the formwork has to stay in place for longer. Normally, you can remove it after two days; in this case, it takes four. The cast floor also cannot be loaded with vehicles as soon, which affects logistics. Both types of concrete are fully hardened after 28 days. In this project, we are using it in the top floor section.” 

The excavation and the connection between the railway deck and the construction pit, formed by sheet piles and piles.

So far, both parties are very satisfied with the collaboration. This is not the first time Mobilis-Hegeman has undertaken a project of this kind. The consortium has previously built underpasses in Assen, Bilthoven, Heiloo and Elst, among other places. Van Beek says: “I am very proud of my team and our collaboration with ProRail. We deliver quality and work safely and on schedule. We have received no complaints from the local community either, thanks in part to ProRail’s good communication.”  

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Ouddiemerlaan in Diemen

  1. aannemerscombinatieMobilis-Hegeman
  2. spoorwerkVolker Rail

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectOuddiemerlaan
  • OnderwerpProjects
  • BedrijfMobilis-Hegeman
  • BedrijfVolker Rail
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.