Suzan Daniel Bridge nears completion
Tekst Philip DoutreligneFotografie Aelterman bv

The Suzan Daniel Bridge in Brussels is scheduled for completion before the end of the year. This will bring to a close more than 10 years of engineering, planning, preparation and construction.
The design work was carried out by engineering firm Greisch, while metal construction company Aelterman and Jan De Nul Group were responsible for the build, together with a number of subcontractors. The project was a unique achievement because the structure had to be built very compactly to minimise its impact on the surrounding area. The bridge will be accessible only to pedestrians, cyclists and public transport.
With the Suzan Daniel Bridge, client Beliris set out to provide a smooth and direct connection between Havenlaan and Willebroekkaai, near Tour & Taxis. The project is important to the further development and opening up of the Tour & Taxis site and Brussels’ recreational harbour area. It is a bowstring bridge, with steel arches carrying the weight of the deck.

An impressive structure
The Suzan Daniel Bridge consists of a central 60 m deck, with a 30 m approach span at each end, plus an 80 m ramp. This brings the structure’s total length to 200 m. For safety, the bridge deck has been divided into two separate sections. A 7 m-wide lane is provided for public transport, while a 6 m-wide zone is designated for cyclists and pedestrians. The pedestrian section, with a timber walking surface, is carried on a cantilever in the concrete. The entire structure weighs more than 1,200 tonnes, including approximately 290 tonnes for the steel arches and the two piers. The remainder is concrete.

Compact design to minimise impact
One of the main requirements was to keep the impact on the surrounding area to a minimum. This was also one of the reasons why the design and preparation phase took so long. After numerous changes, the final design differs considerably from the original concept. Mark Van Overbeke of Aelterman explains: “The need to minimise the impact resulted in an unusually low structure for a 60 m-long bridge deck. The large arches are just 4 m high, which is quite exceptional. This had implications for the grades of steel used (S355, S460 and S690), the plate thicknesses and the volume of welding required.”
Bram Van Renterghem of Jan De Nul Group says: “The architectural concept also presented a number of challenges for our company. The compact design and integration of the steel structure leave very little space for post-tensioning and reinforcement, and particularly strict tolerances had to be observed. The integration of the stainless-steel pedestrian structure, topped with a tropical hardwood deck, is also subject to very strict tolerances. To meet these requirements, a kind of clip system will be used for the stainless-steel and timber components. This structure will be fully assembled in advance and installed on site as a cantilever.”

Phased construction
The steel arches were prefabricated in 4 sections, each weighing between 55 and 65 tonnes. Together with the piers, they were transported by barge from Aelterman’s workshops at Kluizendok in the Port of Ghent. Jan De Nul Group was responsible for the preparatory work, foundations, construction of the bridge deck’s 3 spans, abutments, lighting, pedestrian section, 2 concrete side spans and all finishing works, including the road surface, railings and lighting.
To build the main span, one side of the bridge was placed on pontoons and transported across the waterway. 8 remotely controlled platform transporters were also used. Crane company Sarens, based in Londerzeel, carried out this work as a subcontractor, under the supervision of Jan De Nul Group and in collaboration with the Port of Brussels.
The bridge was then supported on temporary piers. To minimise disruption to the waterway, it was installed in just 2 days. In a subsequent phase, the 2 approach spans, each 30 m long, will be built on the quays and connected to the central bridge deck. The bridge will rest on permanent piers only after the side spans have been built. The final phase involves asphalting the bridge deck and installing the railings and lighting.
For six generations, Jan De Nul Group has shaped water and land. Around the world, it pushes the boundaries of maritime, civil engineering and environmental projects. Its creative and innovative approach delivers sustainable, successful results. In 2020, it achieved a turnover of 1.9 billion euros and employed more than 6,000 people.
Aelterman bv, based in Ghent, is a dynamic, family-owned SME with extensive expertise in steel structures. The company specialises in steel bridges, lock gates, weir gates, crane components and related welded structures for clients at home and abroad.
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Suzan Danielbrug in Brussel
- aannemersDe Nul
- aannemersAelterman
- onderaannemerSarens
- studiebureauGreisch
- bouwheerBeliris
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectSuzan Danielbrug
- OnderwerpProjects
- BedrijfBeliris


















