Projects

Foundation repair and strengthening at the Binnenhof using grout and gel

Text Tjerk van DuinenImage VSF, Keller, RVB, Tjerk van Duinen

Work around the Ridderzaal. (Image: VSF)
Work around the Ridderzaal. (Image: VSF)

The renovation of the Binnenhof is a huge and sometimes extremely complex operation. The complex, covering around 90,000 m2, consists of a series of buildings ranging in age from 35 to as much as 800 years, and is full of surprises. These are often underground, where archaeologists have been working for years during the many excavations. This fifth instalment in the series about the Binnenhof also focuses on work below ground. At this stage of the project, foundations are being strengthened in phases and at various locations. This work is needed, among other things, for the construction of a basement box beneath the square in front of the Ridderzaal and large trenches for various services to the buildings around the Ridderzaal. It is also required because many foundations and structures are in poor condition or their location or condition is unknown.

Schematic overview of the Binnenhof. (Image: Rijksvastgoedbedrijf)

The modernisation and sustainability upgrades at the Binnenhof involve the installation of many new systems. Deep trenches are needed across the site to connect all the buildings to the new services. Excavating alongside old buildings can affect their foundations. To prevent possible damage, various techniques are being used to strengthen the foundations. 

Arches

Construction consortium Heijmans Burgy, responsible for the Eerste Kamer and Raad van State cluster, has now strengthened the arches of the galleries around the square. Tubular piles were installed in the ground alongside the arches. Steel beams with jacks were welded onto the piles to hold the arch structure in place. Electronic levelling measurements (Fides) enable settlement to be monitored accurately during the excavation work. 

Hard-gel injection is carried out entirely using electric equipment. (Image: VSF)

Ridderzaal

VSF, the foundation engineering company of Van Hattum en Blankevoort, is currently using a very different technique around the Ridderzaal to protect this 13th-century (!) building from unwanted settlement. Project manager Jens de Vries explains the aim: “Archaeologists need the opportunity to investigate what lies underground. A trench will soon run around the Ridderzaal, making the remains of old foundations and structures inaccessible. To make these accessible, they have to be excavated. First, the foundation of the Ridderzaal will need to be stabilised. The Binnenhof complex, particularly its oldest parts, is largely founded on a natural bearing stratum rather than piles, on an old beach ridge. We are stabilising it using hard-gel injection, a two-component technique in which sodium silicate and a hardener are pumped into the sand layer at low pressure.    

This is done very precisely through small holes in pre-installed sleeve pipes placed beneath and alongside the foundation of the count’s halls. This creates a temporary mass of sand grains and injection material, forming a structural soil body that reinforces the foundation. We drill relatively small-diameter holes to install the pipes. It is inevitable that these will also pass through old building remains, but the archaeologists are primarily interested in what is there and in being able to document it. It is not a problem if old building remains are locally damaged to some extent, if that means the building itself can be preserved, as that is the most important thing. A test area was drilled first and the approach agreed with the archaeologists.”

The liquid components are stored, mixed and pumped on site, as are all the records and quality checks.

Hard-gel injection

For this foundation technique, the drilling and injection crew first uses fully electric equipment to install a 114 mm-diameter drill casing with drilling fluid. A sleeve pipe is then lowered into it, with a perforated hole every 30 cm, each covered by a rubber sleeve. The drill casing is then withdrawn, allowing the drilling fluid to set and secure the pipe in place. A few days later, an injection hose is positioned inside the sleeve pipe. Using the so-called packer at the end of the hose, which has an inflatable section on either side of the injection outlet, a predetermined volume of hard gel is pumped in, starting at the lowest sleeve and working upwards. This forms a ball of a set diameter in the ground around each sleeve. The next sleeve up is then injected, until a column is formed from the stacked balls. Overlapping columns can be used to create a wall or a solid mass. By monitoring the pressure, the operator can tell whether a sleeve is in sand or stone. “All the sleeves and pipes are mapped in 3D in our system, and we know exactly how much we pump in at each point,” says De Vries. “We draw the liquid components from storage containers on site, where they are also mixed and pumped.” All the records and quality checks are carried out there too. 

A complete jet-grouting plant was on the Hofvijver from June to October 2025.

Sandy soil

Hard-gel injection around historic buildings is a delicate operation, but VSF has extensive experience with it. De Vries says: “We recently used this proven sleeve-pipe technique elsewhere in the Binnenhof complex, as well as at the Mauritshuis and Paleis Het Loo, because it is highly suitable for situations involving sandy soil where a historic building or structure needs to remain stable.” The gallery and the walls of the Tweede Kamer building have also been strengthened with hard gel. VSF is also likely to use both injection and jet grouting for the excavation pit for the new entrance to the Tweede Kamer on Hofplaats and for deepening the lift shaft in the Perstoren.

Container on supports for the return grout above the passageway of the Stadhouderspoort. (Image: Keller)

Eerste Kamer

At the other end of the Eerste Kamer building, Keller Funderingstechnieken cleared its working platform in the Hofvijver at the end of October. A complete jet-grouting plant had been stationed there since June. Heijmans engaged Keller Funderingstechniek to strengthen the foundations of the Eerste Kamer. Keller had already been working at the Stadhouderspoort of the Binnenhof early last year. “That was an advance project: the gate had to be lowered so that lorries and heavy equipment could pass underneath it towards the square in front of the Ridderzaal,” says Marcel Mertens, Benelux operations manager for Keller Funderingstechnieken. “Next year we will start work on the Raad van State and Middenpoort.”

Jet grouting with a compact machine in the Eerste Kamer’s cramped, winding spaces. (Image: Keller)

Soilcrete®

Keller Funderingstechnieken, a global market leader in ground improvement and foundation strengthening, chose its own proprietary jet-grouting technique for the various subcontracts at the Binnenhof. Mertens says: “Soilcrete® is a method for creating all kinds of shapes underground using jet grouting. For example, beneath the Eerste Kamer and Stadhouderspoort, we formed lamellae by moving the jet nozzle back and forth through a limited angle, creating a triangular shape in plan view. A series of lamellae then supports the structure above. Once this has fully set, we fill the spaces between them with grout. If you did this all at once, the building could settle.” 

Concrete working floors 10 cm thick have been laid in all the rooms. (Image: Keller)

Cramped, winding spaces

Jet grouting in and around a centuries-old building is no easy task. “That is why it requires extensive preparation and investigation,” Mertens continues. “It is also a sensitive building with many defects. We therefore monitored it throughout using hydrostatic level cells, or liquid-level sensors, in addition to Fides’ electronic measurements. The façade along the Hofvijver was strengthened from a working platform using thirty boreholes.” Inside, things were more complicated. “At ground-floor level, the building is a series of cramped, winding spaces, each smaller than the last. When we excavated beneath the floors, we also uncovered the old foundation wall, which shows that the façade of the building once stood several metres further back. We then laid concrete working floors 10 cm thick in all the rooms, which also temporarily carry the forces from the walls. Core holes were drilled in these floors at the right positions for the subsequent jet grouting. For this, we used a compact KB1 machine that could fit through all the narrow corridors. Even so, it takes skill to avoid damaging either the building or the machine. There is a lot of moving back and forth because you cannot complete a room in one go, if only because the grout needs to set.”

The façade along the Hofvijver was strengthened from a working platform using the Soilcrete® method. (Image: Keller)

Return grout

A complete grouting plant was set up on the Hofvijver platform for this operation. “Everything was duplicated,” Mertens stresses. “In June there was still a bridge across the pond to the platform, but that has been removed. Replacing a failed pump was therefore not an option, which is why we duplicated everything.” The return grout also required a solution. “Lorry traffic is very difficult here, and we wanted to keep it to a minimum in this part of the city centre. So we came up with a way to collect the grout in a 23 m3 container. It stood on a purpose-built support above the passageway of the Stadhouderspoort. An agitator prevented the grout from setting. A vacuum tanker cleared it away in under four hours. This saved a great deal of space, time and money logistically.”   

Have a business enquiry for Keller Funderingstechnieken? Get in touch

Who worked on the renovation of the Binnenhof

  1. clientRijksvastgoedbedrijfMentioned in Renovating the former Ministry of the Colonies: a building from the Iron Age
  2. Multidisciplinary consultant for the Tweede Kamercomplexde Architekten Cie.Mentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  3. TBI construction consortiumJ.P. van Eesteren, Croonwolter&dros and Nico de BontMentioned in Site offices for 500 people on Plein for Binnenhof renovation
  4. construction consortiumHeijmans BurgyIn this story
  5. Lead structural engineerABTMentioned in World market leader at work on Binnenhof renovation
  6. structural engineering adviceArcadisMentioned in Steel mediates between old and new in the renovation of Binnenhof Building J
  7. Foundation contractorKeller FunderingstechniekenMentioned in World market leader at work on Binnenhof renovation
  8. steelwork contractorVic ObdamMentioned in Steel contractor rises to the challenges of renovating the Binnenhof
  9. circular steelVan Ee StaalspecialistenMentioned in Circular observation tower gives residents something back during Binnenhof renovation
  10. designBERNS architectuurMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  11. adviserBeersNielsen LichtontwerpersMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  12. adviserBremen BouwadviseursMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  13. adviserDGMRMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  14. adviserSmits van BurgstMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  15. adviserKarres en BrandsMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  16. adviserOngehinderdMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  17. adviserLevel AcousticsMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  18. adviserHospitality GroepMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  19. constructionJ.P. van Eesteren | TBIMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  20. building servicesCroonwolter&drosMentioned in 1913 architectural ingenuity uncovered during Binnenhof renovation
  21. contractorHeijmansMentioned in Site offices for 500 people on Plein for Binnenhof renovation
  22. designWDJArchitectenMentioned in Renovating the former Ministry of the Colonies: a building from the Iron Age
  23. acousticsLevel Acoustics & VibrationsMentioned in Renovating the former Ministry of the Colonies: a building from the Iron Age
  24. constructionNico de BontMentioned in Renovating the former Ministry of the Colonies: a building from the Iron Age
  25. Jet groutingKellerIn this story
  26. construction consortiumHeijmans Burgy construction consortiumIn this story
  27. Foundation contractorVSFIn this story
  28. architectVan Hoogevest ArchitectenMentioned in Steel mediates between old and new in the renovation of Binnenhof Building J
  29. concrete supplierDyckerhoff BasalMentioned in Renovating the Binnenhof: an anatomy lesson
  30. carbon additiveCarStorCon TechnologiesMentioned in Renovating the Binnenhof: an anatomy lesson
  31. recycled concrete aggregateUrban MineMentioned in Renovating the Binnenhof: an anatomy lesson
  32. architectBiermanHenketMentioned in Binnenhof renovation adds fifth historical layer to Eerste Kamer roof structure

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectBinnenhof renovation
  • ThemeBuilding in the existing city
  • SubjectProjects
  • CompanyHeijmans Burgy
  • CompanyKeller Funderingstechnieken
  • CompanyHeijmans Burgy construction consortium
  • CompanyVSF
Share this article

Follow on Beton & Staalbouw

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.