Steel

9,000 m2 of composite steel deck floors for the garage of the future

Tekst Lieke BousemaBeeld Tullingh & Partners

De staalplaat-betonvloeren in Mobilis hebben per verdieping een oppervlakte van circa 4.500 m2 en kenmerken zich door een lage profilering.
De staalplaat-betonvloeren in Mobilis hebben per verdieping een oppervlakte van circa 4.500 m2 en kenmerken zich door een lage profilering.

Multifunctional, innovative and sustainable. An ambitious project is taking shape at the junction of Industrielaan and Paepsemlaan in Anderlecht: Mobilis, the garage of the future. On a 10,400 m² site, a unique 35,000 m² building is being created, with a flexible structure that brings together green and urban ambitions, extensive logistics services and bold architecture. The lower levels will house sales areas and showrooms for Volkswagen, Skoda and Seat/Cupra, while the other floors and the roof will accommodate a range of urban activities. The permits for Mobilis were issued in late January 2021, and Alheembouw began construction just three months later. The main contractor appointed Tullingh & Partners to design, engineer and build the composite steel deck floors.

A distinctive feature is that all the steel deck sheets for Mobilis have a white PVDF coating on the underside. The composite steel deck floors will remain exposed as ceilings after completion.

Slim, fast and highly efficient

Significant weight savings, minimal concrete use, better building connections, and perfectly coordinated logistics and installation. But also shorter lead times and lower overall project costs. It is no coincidence that Tullingh & Partners’ composite steel deck floors are widely used in new-build, renovation, conversion and extension projects. Hybrid composite steel deck floors are particularly suitable for (usable) roofs, while uninsulated composite steel deck floors are generally used for intermediate floors in indoor settings and for car parks. This is also the case at the garage of the future in Anderlecht, which has four storeys in total. “The second and fourth floors of Mobilis are in-situ cast concrete floors, known as waffle slabs,” says Charles van Oldenbarneveld of Tullingh & Partners. “For the first and third floors, composite steel deck floors with a special fixing system were selected. The steel structures for these intermediate floors are suspended beneath the concrete floors using a cable-supported structure. We then install the composite steel deck floors on top, for which we prepared a bespoke design for construction.”

Fully bespoke

The composite steel deck floors at Mobilis each cover an area of around 4,500 m² and have a shallow profile. “The floors had to have a low self-weight of no more than 200 kg/m²,” says Van Oldenbarneveld. “There were also specific requirements for the maximum imposed load (500 kg/m²) and fire resistance (120 minutes). Based on these criteria, and working closely with Alheembouw, we engineered the structural floor in detail.” Designing the floors to a depth of 15 cm made it possible to integrate services such as the climate control systems perfectly, he explains. “On completion, Mobilis must meet the BREEAM ‘Outstanding’ criteria and operate as a 100% energy-neutral building. Along with photovoltaic solar panels, a green roof and rainwater reuse, the climate control systems make an important contribution to this.”

33,500 welded shear studs

The average span in this project is 4 metres, says Van Oldenbarneveld. “A large part of the floor slabs are installed without propping. For this reason, lightweight concrete is used, for example. To connect the floors to the underlying steel structure, no fewer than 16,750 welded shear studs are fixed on each floor, 33,500 in total.”

Distinctive design

The garage of the future has a distinctive, dynamic shape that follows the street alignment. “The building’s form is a pleasure to look at, but it also posed challenges,” says Van Oldenbarneveld. “For example, all the flashings and fittings were cut to shape in advance, based on structural information from the BIM model. The rest of the floor build-up is made to fit on site.” Tullingh & Partner is working to a tight installation schedule. “For construction, the building has been divided into quadrants. It takes us about a week to install and finish the profiled sheets in each quadrant on each floor. All the studs are then welded over a two-week period.” Since the concrete floors on the second and fourth storeys have already been cast, there is no clear headroom above. All the steel deck packs are therefore lifted onto the steel structure from below using telehandlers.

Finally, a distinctive feature is that all the steel deck sheets for Mobilis have a white PVDF coating on the underside. “The composite steel deck floors will remain exposed as ceilings after completion,” says Van Oldenbarneveld. “As part of the floors cantilever outwards, the coating thickness has been carefully selected to suit the external environment. This brings protection and an attractive finish together perfectly.” 

Een zakelijke vraag aan Tullingh & Partners BV? Neem contact op

Wie aan Mobilis garage van de toekomst werkte

  1. staalplaat-betonvloerenTullingh & PartnersIn dit verhaal
  2. hoofdaannemerAlheembouwIn dit verhaal
  3. architectXaveer De Geyter Architects (XDGA)Genoemd in Multifunctional, flexible, energy-neutral and exceptionally sustainable: the garage of the future is in Anderlecht
  4. voorgespannen welfselsNervaGenoemd in Prestressed hollow-core slabs in a pioneering circular construction project

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectMobilis garage van de toekomst
  • ThemaVloeren in beton en staal
  • OnderwerpSteel
  • BedrijfTullingh & Partners BV
  • BedrijfAlheembouw
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.