Projects

New rolling bridge at Brouwershaven marina nearing completion

New rolling bridge at Brouwershaven marina nearing completion

Since the end of June, cyclists, pedestrians and wheelchair users have once again been able to cross the lock at the marina in Brouwershaven, in the province of Zeeland. This has been made possible by the construction of a rolling bridge, a similar version of which is also located in Middelharnis. What makes this bridge special is that users can operate it themselves at the push of a button, without causing any inconvenience to shipping or boat owners. The rolling bridge, commissioned by the Municipality of Schouwen-Duiveland, is also the result of close collaboration between main contractor Hanse Staalbouw of Nieuwerkerk and machine builder Breston, based in Nieuwe-Tonge.

For years, the town council of Brouwershaven campaigned for a new harbour bridge. A footbridge once stood where the current bridge has been installed, but it was not put back after maintenance work. As a result, people had to walk all the way around the harbour to reach the other side of the lock. The rolling bridge, a steel structure connected to the lock, has now put an end to that inconvenience. In addition to providing a functional footbridge, the key challenge was to devise a solution that guaranteed the safety of users and shipping while keeping any disruption to a minimum. Hanse Staalbouw and Breston worked closely together throughout the project, with effective communication and coordination leading to the desired result.

Outdoor infrared scanner for presence detection.

Construction

Hanse Staalbouw, a versatile manufacturer of steel structures for sectors including construction, industrial construction and machine building, acted as main contractor and led the process of delivering the new facility. Mariëlle Verhoek (work preparer) and Martin van de Beek (site manager) were closely involved in the work. Since the end of June, the 14-metre-long, 1.20-metre-wide rolling bridge has spanned the 8.5-metre-wide lock at Brouwershaven marina, and users have been able to cross it. “The bridge deck was fully assembled in our workshop and consists of girders with cut and bent plates to accommodate the cabling, as well as supports for the railings,” says Van de Beek. “The railings, rails and platform transitions were also fully welded in our workshop, so on site we only had to position the structure and fit the railings. The entire steel structure was given a high-quality finish, allowing it to be coated with a C5M coating suitable for the salty climate.” Hanse Staalbouw not only manufactured the steel bridge structure, but also handled the engineering, foundation work, rail system and on-site installation.

Challenges

Verhoek and Van de Beek are pleased with the end result, although getting there was not entirely straightforward. “Although the steel structure itself is fairly simple, we faced a number of logistical and technical challenges during installation,” says Verhoek. “There was no crossing to the other side of the lock basin during the work. The 14-metre-long bridge, the platform transitions and the rails had to be brought in across the cycle path on the dike. In addition, 100 metres of hose was needed to deliver the concrete required for the foundations to the right place on the other side of the lock basin. Installing the cable duct also proved quite a challenge. There was an existing pipe, 50 years old, but it was completely blocked and no longer usable. We therefore devised a new duct in consultation with the Municipality of Schouwen-Duiveland. Specifically, this is an RVS316 pipe with a diameter of 220 millimetres, welded with 5D bends into a U shape measuring 4.5 by 11 metres. We fitted it with approximately 1,000 kilograms of counterweight and lowered it to the bottom of the lock basin using a crane vessel. Breston was then able to pull the required cabling through the pipe without any problems.”

Experience

Breston’s contribution, however, was not limited to pulling the cabling. This is clear from the comments of Peter Aarnoudse, electrical & assembly manager at the family business. Specialising in areas including the construction of a wide range of machines and control panels, Breston successfully followed up an earlier project in Goeree-Overflakkee with its work in Brouwershaven. “That project involved automating a cycle bridge,” explains Aarnoudse. “The experience we gained there enabled us to assess the Brouwershaven assignment accurately and tackle potential problems in good time, such as installing the cable duct to the other side of the lock basin.”

Access bollard

Breston’s work was varied and extensive. The company supplied the main control system and installed the cable route, detection equipment and signalling systems in accordance with the applicable NEN standards. It also carried out the mechanical engineering and strength calculations for the bridge. According to Aarnoudse, the control bollards, also supplied and installed by Breston, merit further explanation. “When parked in its standard position, the bridge allows shipping to pass freely. In this position, access to the bridge is completely blocked by a fence. When a cyclist, pedestrian or wheelchair user wants to cross the lock, they register by pressing a button on the stainless-steel access bollard. A screen with a toughened-glass front then allows users to follow the bridge operation as it takes place.” This process includes scanning the lock for any obstacles. If it is clear, the bridge rolls across the lock. The bridge deck is also scanned intensively as it moves. “To do this, we used 2D scanners, among other things,” says Aarnoudse. “The information they gather is then processed by a safety PLC. No movement takes place if anything is detected in the scanning field. In short, bridge safety is at a very high level, with nothing left to chance. The smart combination of drive, control, safety systems and operation makes a decisive contribution.”   

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Rolbrug Brouwershaven in Schouwen-Duiveland

  1. technisch detacheringsbureauInter Techniek
  2. hoofdaannemerHanse Staalbouw
  3. machinebouwerBreston

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectRolbrug Brouwershaven
  • ThemaBruggen en kunstwerken langer mee
  • OnderwerpProjects
  • BedrijfHanse Staalbouw
  • BedrijfBreston
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.