Construction sequence at De Koepel: ‘The basement was built top-down’

Tekst Tjerk van DuinenFotografie Van Rossum Raadgevende Ingenieurs

Construction sequence at De Koepel: ‘The basement was built top-down’

A new basement is being built at De Koepel, which will include cinema screens, among other facilities.

The basement was built top-down. In this case, that means:

  1. Installing a sheet pile wall around the site from ground level to create a closed box.
  2. Installing 64 screw injection piles from ground level to support the deck/ground floor foundation.
  3. Installing 81 tension piles at a lower level to prevent the basement box from floating during the final phase. Installed from ground level.
  4. Constructing the ground floor slab, supported by the sheet pile wall and the screw injection piles. The ground floor slab also provides horizontal support for the sheet pile wall. 
  5. Excavating the basement beneath the ground floor slab, through an opening in the slab. This opening will become a void in the final phase. 
  6. Using the ground floor at the same time for work inside, including by vehicles weighing up to 50 tonnes. 
  7. Constructing the basement floor with a watertight connection to the sheet pile wall. In the completed structure, the basement floor is founded directly on the ground. The tension piles are activated to resist the upward water pressure. The sheet piles are welded together.
  8. Load-bearing calcium silicate block walls are erected on the basement floor to provide permanent support for the ground floor slab.
  9. Partly at the same time as the work beneath the ground floor slab, the steel structure and upper floor slabs are erected above it. 

Vraag over dit verhaal? Stel je vraag

Wie aan De Koepel in Haarlem werkte

  1. aanjager van dit projectStichting PanopticonGenoemd in Building beneath a monumental dome
  2. ArchitectenbureauJ. van StigtGenoemd in Building beneath a monumental dome
  3. constructiefVan Rossum Raadgevende IngenieursGenoemd in Building beneath a monumental dome
  4. adviesbureau voor geotechniekCRUXGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
  5. funderingsaannemerSterkGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
  6. spanningsbemalingMos GrondwatertechniekGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
  7. ontwerpteamArchitectenbureau J. van StigtGenoemd in Building beneath a monumental dome
  8. adviesbureau voor geotechniekCRUX Engineering BVGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
  9. ingenieursbureauVan RossumGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
  10. aannemerHBB Fides ExpertiseGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectDe Koepel
  • OnderwerpProjects
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.