Advanced foundation techniques: RTBF Média Square rests on 800 reinforced and anchored foundation piles
Tekst Philip DoutreligneFotografie Franki Foundations

Franki Foundations, headquartered in Saintes, specialises in pile foundations, retaining walls and ground improvement. Its range of pile foundation solutions includes displacement piles (installed without vibration or driven), vibration-free screw piles with soil extraction, bored piles and micropiles. Franki Foundations’ expertise in retaining walls covers diaphragm walls, soil-nailed walls, tangent or secant pile walls, and soil-mix walls.
Franki Foundations is part of the Belgian international BESIX Group and has its own branches in several European countries. It was selected for the foundation works for RTBF Média Square, the new headquarters of Belgium’s French-language broadcaster, both because of this presence and its many years of experience working on excavations in confined urban spaces.

Challenging conditions
Given the complexity of the project and the specific local ground conditions, several foundation techniques were used to construct the excavation. Project manager Olivier Vancoppenolle explains: “The site where we had to work was far from level, with a height difference of no less than 6 metres. This meant we had to work from several platforms at different elevations.”
“The ground conditions also posed a number of challenges. We were dealing with typical unsaturated sandy soil, characteristic of the Brussels region. This meant we had to stabilise the ground to construct the three underground levels. We did this using cased auger piles installed with a double rotary system. One in every two piles, with a diameter of 63 cm and lengths ranging from 7 to 18 m, was reinforced, with the reinforcement installed after concreting. A total of 800 such piles were installed around the 450 linear metre perimeter of the excavation.”

Complex techniques
Vancoppenolle: “By using this foundation technique, which stabilised the ground, we were able to construct the basement levels without resorting to the usual battered slopes. Given the depth of the excavations, the piles had to be additionally anchored from a certain height. This active anchoring with prestressing cables made it possible to stabilise the three underground levels in advance without difficulty, and then excavate them. In addition to constructing the excavation wall, 52 stabilising piles and 35 standalone piles were installed around a smaller perimeter. Some of these served as foundation piles for the tower cranes.”

Phased approach
“The foundation works on this large site ran in carefully planned phases from September 2020 to February 2021, including a short stoppage for administrative reasons. The well-planned sequencing meant that the other construction partners could continue working while we carried out our operations, without unnecessary downtime. Two foundation rigs were continuously at work on site, and more than 4,500 cubic metres of concrete and 550 tonnes of reinforcing steel were used for the foundation piles.”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
RTBF Média Square
- funderingswerkenFranki Foundations
- ontworpen doorMDW Architecten
- ontworpen doorV+
- tijdelijke handelsvennootschapValbesina
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectRTBF Média Square
- OnderwerpFoundation techniques
- BedrijfFranki Foundations
- BedrijfOlivier NV


















