70-metre strand anchors stabilise quay wall
Tekst Tjerk van DuinenBeeld Hakkers Funderingstechniek

Moerdijk multimodal terminal
At the start of 2025, Van der Vlist Transportgroep will have a fully operational new multimodal terminal in Moerdijk. In addition to a large hall and offices, the terminal includes a large transhipment area with no less than 650 metres of quay on the Hollands Diep and at the Roode Vaart spur harbour. This will significantly increase Van der Vlist’s capacity to berth inland vessels and seagoing ships. The quay was built by Gebr. De Koning, which subcontracted Hakkers Funderingstechniek to provide the quay wall with robust anchoring. Unusually long anchors, up to 70 metres, were used.

For Van der Vlist Transportgroep, the Moerdijk site is a strategically located hub offering congestion-free connections to the hinterland by both rail and water. Its services are aimed primarily at the construction and energy sectors. This involves the storage and transhipment of project cargo such as wind turbine components, large structures and rolling stock. “The quay needs to be designed to handle that,” says Arnoud Hoeve, Head of Procurement, Foundation Technology at Hakkers Funderingstechniek. “The latest machinery carrying heavy loads will be moving around here, and large mobile cranes will be positioned to load and unload them. This required extra attention to the construction and anchoring of the quay. It also ends in an acute point, which called for a different approach to anchoring this section.”

Optimisation
Gebr. De Koning designed and built the quay as an anchored combi-wall structure consisting of tubular piles and sheet piles. “We joined the project during the detailed design phase to optimise the design together, with the aim of finding the most cost-effective and sustainable solution,” Hoeve continues. “Gebr. De Koning installed a total of 211 tubular piles, averaging 35 metres in length. The first 23 metres were driven using a high-frequency variable-moment vibratory hammer; the remaining length was impact-driven to provide even greater load-bearing capacity and strength. We then anchored the walls, a process that began in early April. The final anchor was in place before the construction holiday, and all the anchors had been prestressed by mid-September.”
Paired anchors
There was still a lot to be done before that could happen. “During the design phase, alongside the base option of two strand anchors per tubular pile, we also considered an option using one grout-injection anchor per pile,” says Wouter de Graaf, Project Manager at Hakkers Funderingstechniek. “We often use that option because it can withstand heavy loads and is quicker to install. After considering factors including cost and sustainability, we decided to develop the base design using pairs of strand anchors drilled into the ground at an angle of 40° to 45°. Lengths of 50 to 70 metres were used to achieve the required tensile force. These are exceptional dimensions, and we had not previously used strand anchors of this length.”

Tangle
Another challenge was the angled end of the quay wall. De Graaf: “This gave us quite a few headaches, because the anchors cross over one another there or even pass through the sheet piles. We solved this by installing an additional sheet-pile wall about twenty metres behind the quay and connecting it to the quay wall with tie rods. Combined with the strand anchors, this creates quite a tangle of steel, but by varying the angle slightly and drilling accurately, everything is now neatly in place.”
Working platform
The anchors were installed using a Klemm 807-7GP anchor drilling rig from a working platform six to ten metres wide, which ran a few metres lower along the outside of the quay. De Graaf: “To handle the exceptionally long strands quickly and safely, we made an XL strand reel especially for this project. The angled end of the quay wall was drilled from one of our own self-propelled workboats. The working platform has since been excavated so that the client’s vessels can berth there. Only now is the quay really functioning as a retaining wall.”
Future
The experience gained on the Moerdijk project has been positive. Hoeve concludes: “First of all, our collaboration with Gebr. De Koning was constructive and enjoyable, both during the design phase and on site. We speak the same language, which leads to the best results. Using strand anchors saved a considerable amount of steel on this project, which is certainly relevant when it comes to making projects of this scale more sustainable.”
Vraag over dit verhaal? Stel je vraag
Bedrijven in dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectMultimodale terminal Moerdijk
- OnderwerpFoundation techniques
- BedrijfGebr. De Koning



















