Connections & connection techniques
Challenging renovation of the Heinenoord Tunnel
Tekst Roel van GilsBeeld Rijkswaterstaat/Studio Retouched

The Heinenoord Tunnel, built in 1969, is an immersed tunnel on the A29, an important link between the ports of Rotterdam and Antwerp and a key route into the Hoeksche Waard and Zeeland. Many of its technical installations have reached the end of their service life and need replacing. Structural work is also required. But how do you tackle this in a tunnel with two open tubes and no central service duct? And with as little disruption as possible to the 110,000 vehicles that use the tunnel every day?

“The Heinenoord Tunnel is quite a challenging tunnel,” says Stephan van der Horst, civil engineering project manager at Rijkswaterstaat. “Because there was no central service duct, all the installations, cables and pipes were simply housed in the tunnel tubes, behind fire-resistant cladding, but still. So they were difficult to access. During previous major maintenance work, the idea of building a central service duct had already been raised. First, it would provide a safer escape route than an open tunnel tube, and it would also make repairs and maintenance to the installations much more efficient. You would no longer have to close the tunnel for every job, and work could be carried out in the central service duct while traffic continued to flow. The tunnel tubes are also wide enough to accommodate a central service duct without having to give up any traffic lanes.” And so it came to pass.

No real diversion route
Building a central service duct is a major civil engineering undertaking, especially given that the tunnel must remain open as much as possible. “There is no really good alternative to the Heinenoord Tunnel for road users. Through traffic is diverted via the A16. Local traffic travelling to and from the Hoeksche Waard is diverted via the local N217 and the smaller Kiltunnel. That means local traffic has to take a 25-kilometre detour and pay a toll,” explains Van der Horst. “Alongside the many measures we are taking at Rijkswaterstaat, such as covering the Kiltunnel toll, we challenged the market to renovate the tunnel with as little disruption to road traffic as possible. That meant building a central service duct almost 700 metres long in the shortest time possible, replacing all systems and installations, and carrying out the necessary civil engineering renovations without closing the tunnel for an extended period, so that it would not need major maintenance for the next thirty years. At the same time, the service buildings and light screens at the tunnel entrances also needed work, as did the approach slabs and the asphalt.” The bid from Savera III, a construction consortium comprising Dura Vermeer, SWARCO (formerly Dynniq) and SPIE, offered the greatest added value and the best value for money. The contract was therefore awarded to the consortium.

Central service duct
The consortium’s biggest challenge was to schedule all the work within the shortest possible timeframe. “We had an extended closure available in the summer of 2023, as well as the necessary weekend closures,” says Martijn Koedood, civil engineering design manager at Savera III. “It was quite a puzzle to put together a workable schedule, including staffing at weekends and during holiday periods. It is also an old tunnel, and despite the preliminary investigations, you cannot always be sure of the condition of the structure, because the concrete structure and the cables and pipes, for example, are hidden behind the fire-resistant and visual cladding. As the project progressed, we therefore had to carry out further investigations to establish their condition.”
To overcome these challenges, Savera III came up with a number of smart solutions. The central service duct was fully prefabricated, the team practised installing the elements outside the tunnel, and the duct, comprising 86 large concrete wall elements weighing 30 tonnes each, was fully installed and completed during a closure of just four weeks. “In cross-section, the central service duct is a concrete wall installed in the westbound tube, the tube heading south, in front of the existing central wall. This creates both an escape passage and a service passage, because the tunnel is high enough to accommodate an additional level.”

Tolerances and expansion joints
Building the central service duct may look straightforward on paper, but it was not, Koedood assures us. “The Heinenoord Tunnel is an immersed tunnel made up of several sections, with numerous variations along its length. How do you deal with tolerances and expansion joints? We had to resolve a lot of specific details over those 660 metres. Thanks to thorough preparation, the work proceeded like clockwork. The heavy elements were transported one by one from the construction site to the tunnel and installed in sequence. As soon as the first elements were in place, work also began on installing the cables and pipes. Subcontractors Van den Bersselaar Constructie and Interboor kept neatly in step with the team.” The control systems for the installations, along with the cables and pipes, are now housed in the service passage of the central service duct. “This will make future maintenance and repairs to the installations easier, because the tunnel will no longer have to be closed every time.”
As well as the central service duct, the immersed joints have been a major focus of the renovation, as deterioration meant they would not reach their intended 100-year service life, says Van der Horst. “We therefore launched an extensive investigation, the results of which were shared through COB (Centrum Ondergronds Bouwen). In fact, the lessons we learned from this renovation regarding the immersed joints have even led to a change in the design of the Maasdeltatunnel further along the A24 Blankenburgverbinding.”
Although most of the renovation of the Heinenoord Tunnel has already been completed, Savera III will continue working until the end of the year. This includes installing the visual cladding and modifying the service buildings. The tunnel will be closed for a further two weeks this summer to switch over to the new installations and systems, followed by five weekends in the autumn to remove the old installations and systems. After that, the Heinenoord Tunnel will not need major maintenance for decades.
Een zakelijke vraag aan Interboor Midsland? Neem contact op
Wie eraan werkte
Heinenoordtunnel, renovatie
- de staalconstructiesJos van den Bersselaar Constructie
- bouwcombinatieSavera III
- Onderaannemers
Interboor - OnderaannemersVan den Bersselaar Constructie
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectHeinenoordtunnel
- OnderwerpConnections & connection techniques
- BedrijfInterboor Midsland
- BedrijfVan den Bersselaar Constructie


















