Connections & connection techniques

Mini-polder in the Haarlemmermeer

Tekst Tjerk van DuinenFotografie Combinatie Leeghwater

Drone-opname van de piekberging, met op de voorgrond de inlaatconstructie en de woelkom.
Drone-opname van de piekberging, met op de voorgrond de inlaatconstructie en de woelkom.

​Ingenious peak storage facility designed to prevent flooding

One of the water board’s core responsibilities is to ensure that we all keep our feet dry. This requires continuous adjustments to the water system. A so-called peak storage facility is currently being built on behalf of the Hoogheemraadschap van Rijnland in the south-western tip of the Haarlemmermeerpolder. If the Rijnland boezem system, including the Ringvaart of the Haarlemmermeer, is at risk of flooding, it can temporarily hold more than a million cubic metres of water, helping to prevent the situation from getting worse. The peak storage facility is being built by Combinatie Leeghwater, comprising KWS (civil engineering and infrastructure) and Van Hattum en Blankevoort (civil engineering works). 

Jörg Dreyer is Environment Manager for Combinatie Leeghwater and explains the purpose of the peak storage facility. “During heavy rainfall, particularly in summer, there is a risk that the pumping stations will no longer be able to remove the water, and that high water levels will cause embankments, such as those along the Ringvaart of the Haarlemmermeer, to overflow or even fail. The polder would then flood. This is a particular risk in the area around the Kagerplassen, as this is the furthest point from the four Rijnland boezem pumping stations (Gouda, Halfweg, Spaarndam and Katwijk; ed.). As a result, it takes longest to control the boezem water level here. The solution is the peak storage facility, an intermediate storage basin with a capacity of more than a million cubic metres of water. It is expected to be needed on average once every fifteen years.”

Tilting sluice gates.

Inlet structure

The peak storage facility is essentially a polder within a polder. It consists of a 3.8-kilometre-long dyke with maintenance tracks, enclosing an area of 67 hectares between the Lisserdijk, the A44 and a new dyke on the north-eastern side. An inlet structure has been built at the southern tip, allowing excess water from the Ringvaart to flow in. The dyke also incorporates two culvert structures, which remain open under normal conditions, and an outlet structure and channel through which the water is discharged again after a peak load. The civil engineering works comprise these structures, the outlet channel, a road bridge over the channel and five agricultural bridges. The earthworks and waterworks include the 3.8 km of dykes and 7 km of ditches.

Still­ing basin

Berry Borgstein, Chief Site Manager at Van Hattum en Blankevoort and Technical Manager for Delivery, explains in more detail how the peak storage facility works. “Think of it as a basin holding more than a million cubic metres of water, which we gradually fill from the Ringvaart. First, culvert 1, culvert 2 and the outlet structure are closed. The temporary stoplogs are then removed from the inlet structure, and the four sluice gates are gradually tilted, allowing water from the Ringvaart to flow into a stilling basin at a rate of fifteen cubic metres per second. This is an elongated pond, twenty metres wide, where the flow is regulated before reaching the filling ditch. This ditch runs all the way around the site and fills with water over four hours. The two farmers in the area have that time to move their cows out of the polder. Once the filling ditch is full, the water eventually flows into the peak storage facility.” 

Culvert structure under construction.

Earthworks balance

Combinatie Leeghwater won the contract at the time by scoring highly not only for its ingenious design, but also for its approach to earthworks balance, sustainability and stakeholder management. Dreyer explains: “Our plan involved a balanced cut-and-fill operation, with no surplus or shortage of soil. This meant coming up with a logistics plan at the outset and making it feasible for all the clay, sand and soil on site. In the end, the dyke was built using soil excavated from the watercourses on either side of it, with clay as a water-impermeable layer and a layer of topsoil for the grass. The earthworks plan avoided the need to import or export materials, and we minimised soil movements by using various temporary stockpiles.”

Combinatie Leeghwater also scored well on sustainability, partly thanks to its use of electric equipment. Borgstein explains: “The five agricultural bridges in the middle of the peak storage facility and the culvert structures were built using battery packs wherever possible. These were used, for example, to power poker vibrators, site lights, circular saws and power trowels. For the formwork of the in-situ concrete bridges, we also used EPS blocks wrapped in timber. After use, the timber went to a social enterprise workshop, while the EPS was sent to a recycling company.”

Peak storage facility and its various components.

Unobtrusive

As part of the stakeholder management process, an agreement was reached through consultation with the intended tenants of the grassland within the peak storage facility. A sounding board group was also set up for local residents and other stakeholders. The facility was designed and built with careful consideration of the local community’s wishes, by limiting disruption and keeping the mini-polder available for farming and livestock almost continuously. In addition, the structures, such as the inlet, are barely visible in the landscape. The small concrete bridge abutments have also been finished with brickwork so that they blend in better. Some of the piling work was carried out using soil-formed piles because of the site’s proximity to a listed building.

This peak storage facility will be put to the test in the winter of 2024/2025. Borgstein explains: “We will be ready well before then, but we can only test it once the embankments are covered with vegetation, so we need to give them a growing season. Then let the water come.” 

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Piekberging Haarlemmermeer in Haarlemmermeer

  1. civiele werkenKWS (GWW)
  2. civiele werkenVan Hattum en Blankevoort

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectPiekberging Haarlemmermeer
  • OnderwerpConnections & connection techniques
  • BedrijfKWS (GWW)
  • BedrijfVan Hattum en Blankevoort
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.