Connections & connection techniques

New Zaanbrug in Wormerveer pivots like a Swiss Army knife

Tekst Roel van GilsBeeld Harry Bax selected view

Om het architectonische ontwerp met drie vallen (!) maakbaar te maken, werd Ingenieursbureau Boorsma ingeschakeld; dé specialist in beweegbare bruggen.
Om het architectonische ontwerp met drie vallen (!) maakbaar te maken, werd Ingenieursbureau Boorsma ingeschakeld; dé specialist in beweegbare bruggen.

Work has been progressing at pace on a new steel bridge on the site of the old Zaanbrug in Wormerveer. And it is a very unusual bridge, with two pivot points that look just like a Swiss Army knife and cycle and pedestrian paths that curve around the outside of the bascule towers. To make the architectural design, with three leaves (!), buildable, Ingenieursbureau Boorsma was brought in, as the specialist in movable bridges.

The bridge uses a total of 350 tonnes of steel.

The existing Zaanbrug between Wormer and Wormerveer dated from the 1960s and was in urgent need of replacement. The new bridge has a wider and higher navigable opening. This allows ships to pass more easily and means the bridge needs to open less often and for shorter periods. The new Zaanbrug also provides more space for cyclists and pedestrians, improving safety. The renewal of the Zaanbrug is part of the provincial ‘Vaart in de Zaan!’ programme. Through this programme, the province of North Holland aims to improve the navigability of the Zaan, enabling businesses to continue using and expanding transport by water. 

Ultra-slender bascule

The province of North Holland itself describes it as a traditional Dutch bascule bridge, but the new Zaanbrug is undoubtedly an architectural feat. Anne Jan Breimer of Ingenieursbureau Boorsma knows this too. “Our scope covered developing the final design and the construction design, including the workshop drawings for the steel structure, on behalf of HSM Steel Structures. It was quite a challenge, given the underlying visual quality plan, with its ultra-slender bascule and a pivot point in each of the bascule towers, inspired by a Swiss Army knife with a recessed groove. The design also comprises three leaves: one for road traffic and two for cycle and pedestrian traffic. The latter two are double-curved and wind around the bascule towers, with a span of 20 metres.”

The two leaves for cycle and pedestrian traffic are double-curved.

Removable steel billets

The bridge uses a total of 350 tonnes of steel. “One of the design challenges was to keep the bascule as slender and light as possible,” says Breimer. “The total weight could not exceed 265 tonnes, because the bascule must be removable by a floating crane for future maintenance. However, moving the bridge requires more ballast. We optimised the design by using additional adjustable ballast. This is normally used only at the rear of the bascule, but it proved insufficient to keep the total weight below the limit. We therefore provided five additional compartments: large, heavy, removable ballast containers in which steel billets are neatly stacked. This brings the removable ballast to 88 tonnes in total and the non-removable ballast to 128 tonnes.”

Link coupling

Another requirement for which Ingenieursbureau Boors-ma devised a solution was that the leaf for non-motorised traffic had to be removable without affecting the bridge’s operation. “In the event of a collision, one of the two leaves must be removable for repairs. We solved this with a link coupling. Both leaves for cycle and pedestrian traffic are connected to the road traffic leaf by a link coupling,” Breimer explains. “When the leaf for non-motorised traffic is dismantled, the link coupling is released and the leaf can be lifted out of the main pivot points. Extra ballast is then added to the section beneath the tie rod to compensate for the weight of the removed leaf. This brings the bridge back into balance and allows it to operate as usual. The same principle applies to both leaves for cycle and pedestrian traffic.”

To prevent the three leaves from rattling, Ingenieursbureau Boors-ma designed the four bearings to maintain positive bearing pressure. “To achieve this, all three leaves have been given a camber, an additional deformation in the mould. After installation, they deform slightly, creating positive bearing pressure at all four bearings. Following the new Michiel de Ruyterbrug in Urk, which we engineered in detail and which opened earlier this year, the new Zaanbrug is another excellent reference project for our firm. It is a project we have thought through down to the very last bolt and nut,” Breimer concludes. 

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Zaanbrug in Zaanstad

  1. ingenieursbureauIngenieursbureau Boorsma
  2. staalconstructieHSM Steel Structures

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectZaanbrug
  • ThemaBruggen en kunstwerken langer mee
  • OnderwerpConnections & connection techniques
  • BedrijfIngenieursbureau Boorsma
  • BedrijfHSM Steel Structures
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.