Painting bridges while keeping the waterway open

Painting bridges while keeping the waterway open

Bridge Farmsum underwent major maintenance on the Lemmer–Delfzijl waterway. First, the existing rust was blasted away. The bascule bridge and drawbridge were then completely repainted. Sealteq carried out all the painting work in exactly three weeks.

Sealteq Group

When Rijkswaterstaat invited tenders for the work, it was clear that the execution time was an important factor. Bidders offering the shortest execution time and causing the least disruption to the surrounding area scored points on a notional basis, increasing their chances of winning the contract. This prompted Sealteq Noord and the Van de Herik–SPIE contracting consortium to focus strongly on these aspects. They presented a method statement with a lead time of three weeks. “It was really a mission impossible,” says Marcel Vrijs, project manager at Sealteq Noord. “We had to work extremely cleverly to deliver on that promise.”

Working at night

Sealteq was able to start work on the bascule bridge straight away, as the small lock was closed. The challenge was the drawbridge. “Around 50 to 100 vessels pass through here each day,” says Vrijs. “And the waterway had to remain open. That made it almost impossible to work from our vessel. What’s more, if we had to move our vessel out of the way 50 times a day to clear the waterway, we would hardly get any work done.” Sealteq therefore decided to carry out the work on the drawbridge at night, when the number of passing vessels falls to two or three.

Working at height

The high water level and favourable late-summer weather worked in Sealteq’s favour. To maintain a high pace of work safely, the workboat was equipped with heaters and air dryers, but these proved unnecessary in the high temperatures. “We first sprayed the underside of the bridge. Then we opened the bridge so we could work on the counterweight and the lifting towers from 20 m-high mobile elevating work platforms. That took a fair bit of courage. With six skilled workers on site throughout, we kept up a fast pace.”

High-quality work

The requirements for the paintwork were stringent. The coating had to protect the substrate against deterioration from all non-mechanical influences. After maintenance, the bridge was to show no signs of corrosion, loss of adhesion from the substrate, blistering, cracking or chalking. This had to be guaranteed for a period of seven years. Vrijs: “We chose PPG’s three-coat coating system. We’ve used it several times before and it has an excellent track record. The seven-year guarantee was provided by the paint supplier.”

The paintwork has significantly extended the service life of the bridges. Vrijs looks back on the project with satisfaction: “We completed the work exactly within the promised timeframe, and the waterway remained accessible throughout.”    

Words | Liliane Verwoolde   Image | Sealteq Noord

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Brug Farmsum

  1. schilderwerkSealteq Noord
  2. aannemingscombinatieVan de Herik
  3. aannemingscombinatieSPIE
  4. coatingsysteemPPG

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectBrug Farmsum
  • ThemaBruggen en kunstwerken langer mee
  • OnderwerpTreatment & protection
  • BedrijfSealteq Noord
  • BedrijfVan de Herik
  • BedrijfSPIE
  • BedrijfPPG
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.