A bridge on a bridge: Champions League-level steel construction
Tekst Roel van GilsBeeld Civiele technieken deBoer

One of the most complex rail projects in the Netherlands is about to get under way in Vught: Vught Verdiept. The railway will be lowered below ground level. To allow this work to proceed without disruption, the existing railway must be diverted via a temporary bypass. At one point, the bypass crosses the N65. This is where sister companies Rijnstaal Nieuwegein and Civiele technieken deBoer play a key role. They literally built a bridge on a bridge. Twice, in fact.
Since 2024, BAM has been working on diverting the railway through Vught, including a new railway alignment, a temporary station and a pedestrian footbridge over the railway. Only once this work is complete, scheduled for the end of 2025, will the existing railway be available for the construction of the sunken section: a concrete tunnel in which trains will run beneath Vught. Sister companies Rijnstaal Nieuwegein and Civiele technieken deBoer were responsible for all the steelwork on the project. Their contract covered the engineering, manufacture and installation of the footbridge, railway bridge and cycle bridge. All three structures are temporary. The last two run parallel to each other and cross the N65.

Circular steel
“We started by engineering and manufacturing the cycle bridge, which is largely made from circular materials,” says Bjarne Snel, work planner at Rijnstaal Nieuwegein. “The girders are made up of 1.40-metre-high steel sections that had served as temporary support structures on earlier projects. They were waiting on our site for their next assignment. This circular approach earned BAM valuable points in the tender.” The cycle bridge consists of four girders, connected in pairs along their length. The girders on either side are joined by a cast-in-place concrete deck. “That is also the only connection, and the combination of concrete and steel made the design structurally challenging.”

Sliding tracks
The cycle bridge was assembled on the deck of the underpass beneath the N65. So, literally, a bridge was built on a bridge. “Before construction began, we installed sliding tracks on the bridge deck and placed jacks on the wall of the underpass,” explains Anton Gorter, project manager at Civiele technieken deBoer. “Once the concrete of the cycle bridge had cured, the structure was lowered onto the sliding tracks using jacks. The cycle bridge was then moved forward by one span, and a crash deck was attached to serve as a working platform for the next phase. The cycle bridge was then slid into its final position. It now hangs above the N65. Thanks to the crash deck, we did not need to close the N65, and the entire underpass deck was clear for construction of the temporary railway bridge.”

Challenging structure
The railway bridge, too, was built on the underpass and will remain there. “After building our temporary support structures, 16-tonne C-section girders were delivered to the underpass deck. Rijnstaal Nieuwegein’s specialists fully welded them together on site to form two structures, each 51 metres long,” Gorter explains. “We then positioned the jacks, and two heavy-duty cranes lifted the structure into place, after which the truss sections and arch structures were added. The connections use M36 and M42 prestressing bolts, which were retightened using electronic torque wrenches. Every weld was also non-destructively tested to guarantee absolute safety. It was truly Champions League-level steel construction, with temporary bracing for stability throughout the installation.”
Once fully assembled, the railway bridge was jacked up by 120 centimetres by Civiele technieken deBoer. “This allowed BAM to build the formwork for casting the concrete deck,” Gorter explains. “New abutments were built at either end of the underpass. The entire structure was eventually lowered onto them by 180 centimetres, and the permanent bearings were installed at the same time.” Although the structures are temporary, Gorter says they meet all the requirements for new-build structures. “The bolted connections mean that large sections can be reused in the future. All in all, this is a valuable project reference for us as sister companies. The complex phasing, involving the controlled lowering and sliding of technically challenging structures, allowed us to make the most of the synergy between our companies.”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Vught Verdiept in Vught
- engineering, productie en montageRijnstaal Nieuwegein
- engineering, productie en montageCiviele technieken deBoer
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectVught Verdiept
- ThemaBruggen en kunstwerken langer mee
- OnderwerpSteel
- BedrijfRijnstaal Nieuwegein
- BedrijfCiviele technieken deBoer


















