Reused steel sections, bio-based primer and integrated collaboration create a model of circular construction
Tekst Kris VandekerckhoveBeeld Dijkstaal

Visitors to the refurbished Gouwehal in Waddinxveen today see more than a sports complex. The project is an example of circular construction, with steel reuse and integrated collaboration at its heart. Dijkstaal played a key role. Project manager Roy van den Berg looks back on a project that required craftsmanship, patience and passion.
One of the biggest challenges on this project was using so-called ‘donor steel’: sections salvaged from demolished buildings. “We received an entire batch of steel covered in mud, leaves and old paint. There were usable pieces in among it, but also sections that were permanently deformed, had plates or angle sections welded to them, or were full of holes. So we first carried out a thorough assessment of what we could use and what we couldn’t,” explains Van den Berg. There was another complication: some of the steel had been treated with chromium-6 and lead-based paint. “You can’t just weld or grind that. In the end, we decided to have all of it grit-blasted and then coated with a bio-based primer. From that point on, we could process the material further. Much of the work was done by hand: cutting, grinding and adding plates. We could barely use machines because of the welded-on parts already in place. This meant more production hours in the factory, but the result was unique.”

Circularity on display
Reuse has deliberately been made visible in the hall. The stands, changing rooms and corridor to the new gym contain components made from donor steel, identified by QR codes that visitors can scan to find out where the materials came from. “That makes it tangible: you can see where the steel came from and how it is getting a second life,” says Van den Berg.
As not all the donor steel planned for the project became available, Dijkstaal worked with architect Topos and contractor Aannemersbedrijf Den Dubbelden on a creative solution: treating new steel to look reused, so the appearance remained consistent. “That way, the whole thing stays consistent, and you can’t see the difference between old and new.”

Collaboration and BIM
The complexity of this circular project called for close collaboration. Topos acted as BIM coordinator, while the contractors, façade builders and installers each contributed their 3D models. “BIM used to be a luxury, but now it’s an absolute necessity,” says Van den Berg. “Especially when you’re working with reused materials, everything has to be coordinated exactly.” Although there were a number of discussions along the way, he describes the collaboration as positive. “No friction, no shine. In the end, you look back together on a special process that was only possible with good teamwork.”

Added value through sustainability
The project shows that circularity is not always cheaper in practice. Extra hours, manual work and treatments all added to the cost. Even so, Dijkstaal sees the added value. “You make the transition visible. Back in 2018, we won the National Steel Prize in the Sustainability category from Bouwen met Staal for our contribution to the first truly circular construction project in the Netherlands: the Temporary Courthouse in Amsterdam. That motivates us to take on projects like this again. Sustainability is becoming increasingly important, and we want to, and must, do our bit for our children and future generations.”

Proud of the complete picture
What is Van den Berg personally most proud of? “When you walk into the hall, you see the complete picture: the stands with visible old steel, the corridor and the QR codes that tell its story. It wasn’t a standard project. A year of blood, sweat and tears went into it, which makes the result all the more rewarding.”
The Gouwehal is more than a sports hall. It is ‘living’ proof that circular steel is not only technically feasible, but also gives a building character. Thanks to the commitment of its partners and their craftsmanship, Waddinxveen now has a sports facility with sustainability literally embedded in its structure.
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Gouwehal in Waddinxveen
- architectTopos
- AannemersbedrijfDen Dubbelden
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectGouwehal
- ThemaMinder CO2 in beton en staal
- OnderwerpSteel
- BedrijfTopos
- BedrijfDen Dubbelden


















