New French fries factory rests on 2,718 ground-displacement screw piles
Tekst Roel van GilsBeeld Votquenne Foundations

Aviko’s new French fries factory in Poperinge is founded on no fewer than 2,718 ground-displacement screw piles.
The foundations were installed by Votquenne Foundations, a relatively young Belgian foundation specialist that is rapidly becoming a market leader in total solutions for both foundation and shoring techniques.
Votquenne Foundations was established in 2006 by engineer Bart Cloet, with the aim of offering mechanised foundation techniques alongside manual methods, including ground-displacement screw piles, micropiles, Berlin walls and secant pile walls. “Votquenne Foundations is a regular partner of Alheembouw, and in that capacity we were asked to submit a proposal for the foundations of the new factory in Poperinge,” says project manager Youri Coucke. “We were very pleased to be awarded this contract, as the project is practically on our doorstep and many of our colleagues live in the area.”
An economical solution
“For Aviko, using ground-displacement screw piles proved to be the most economical foundation solution. It is also our speciality and core business,” says Coucke. “Another type of pile would have been more expensive and would also have delivered a lower output. For us, this was an all-round project of a good size. We carried out both the foundation work and the dewatering. Several machines were deployed for this work. The attractive project and clay-like ground conditions also made it suitable for using smaller equipment. In total, we set up four foundation rigs, although they were not all operational at the same time. We also deployed the necessary equipment to install and operate the wellpoint dewatering system.” Coucke explains that the ground-displacement screw piles are formed by laterally displacing the soil as the pile is drilled in without vibration, then immediately filling the space created during drilling with concrete and installing a reinforcement cage. “This technique does not bring any soil to the surface. In total, no fewer than 65 tonnes of reinforcement and 5,000 m³ of concrete were used.”

Total solutions
Votquenne Foundations positions itself firmly as a provider of total solutions for constructing excavations. Coucke says: “Where required, we can provide the complete package, covering all possible foundation techniques and dewatering operations. In 2019, 2Fund was established in partnership with Lameire Funderingstechnieken, driven by both companies’ ambition to become Belgium’s market leader in total solutions for both foundation and shoring techniques. This merger has also enabled us to offer soil mixing techniques.”
Personal commitment and making everything open to discussion and achievable are central to the company’s entire operation, says Coucke. “Time and again, we do our best to meet our clients’ needs and requirements without compromising on quality or safety. This also fits perfectly with Aviko’s philosophy. The company places great importance on safety and therefore maintained close supervision throughout the construction process. The result has satisfied both us and the client. None of this would have been possible without our employees, on whom we can rely 100% every day.”
Vraag over dit verhaal? Stel je vraag
Wie aan de nieuwe fritesfabriek van Aviko werkte
- prefab betonstructuur en prefab gevelpanelen
Valcke Prefab BetonGenoemd in Precast frame for sustainable chip factory - fundering van de nieuwe fabriekVotquenne FoundationsIn dit verhaal
- RVS-afwateringssysteemSandstra BelgiëGenoemd in 1,250 metres of stainless steel drainage channels and more
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectFritesfabriek Aviko
- OnderwerpFoundation techniques
- BedrijfVotquenne Foundations
- BedrijfLameire Funderingstechnieken NV