Flexible formwork system and the right engineering for the construction of a new bridge over the Essche Stroom

The old bridge over the Essche Stroom in the municipality of Haaren is being demolished and replaced by a new ‘white bridge’.
Roel Schmidt, site manager at contractor Strukton Civiel Zuid, says that PERI was brought in to help find the right formwork solution for the project.

Working together as construction partners
After removing the old bridge, Strukton installed steel tubular piles as a temporary steel structure for the new bridge. “The PERI deck formwork is placed on this, and the new bridge is cast on top of it,” Schmidt explains. “We have worked with PERI on previous projects. As a major player in the formwork market, we asked them to help us find a suitable solution.” Theo Vereijken, project manager at PERI, adds: “There is very little space between the steel structure and the underside of the bridge, so the limited clearance for erecting and striking the formwork had to be taken into account. Strukton made it clear what needed to be done, and we incorporated all the factors into the formwork engineering. That is what collaboration looks like when the aim is to achieve the best possible end result.”
Versatile formwork system
“Using our versatile VARIOKIT formwork system, and in close consultation with the contractor, we delivered 18 complete, pre-assembled elements to the site. This also helps keep the project moving at a good pace.” Vereijken explains that the pre-assembled elements were supplied to the correct radius to accommodate the camber in the bridge deck. “Our flexible VARIOKIT system makes it possible to build all kinds of different structures. The system is cost-effective and ideally suited to short-term projects. Expert engineering also enables complex challenges to be solved.”
Striking the formwork quickly and safely
“The success of a project like this depends on its execution,” Vereijken says. “Strukton has skilled professionals who handle PERI equipment well on site.” Schmidt adds: “That is only possible with careful preparation by PERI.” Once the PERI formwork system had been installed, the reinforcement work began and the edge forms were set up. The 110 cm-thick deck, including its prestressing, is then cast in situ using no less than 250 cubic metres of concrete. To strike the formwork, PERI built a formwork removal trolley using the VARIOKIT system, so no one has to enter the space between the steel structure and the pontoon. “The elements are struck using lowering pots, and the trolley allows the deck to be rolled out.” The new bridge, with a span of 34 metres and a width of 6 metres, once again fully meets the new standards and the current traffic class.
Een zakelijke vraag aan PERI BeNeLux B.V.? Neem contact op
Bedrijven in dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ThemaBruggen en kunstwerken langer mee
- OnderwerpFormwork
- BedrijfPERI BeNeLux B.V.



















