Teamwork and preparation take centre stage
Tekst Tjerk van DuinenBeeld Kandt en Tjerk van Duinen

Foundations and walls for RIF010
The lead-up was long, but in April 2023 the first sheet pile for RIF010 finally went into the Steigersgracht. Foundation specialist Kandt bv from Nieuwerkerk aan den IJssel had been brought on board by Mobilis to install the sheet piles for this exceptional project and drill the foundation piles for the underwater concrete slab. Close cooperation, especially with Mobilis and earthworks contractor Verboon, was of the utmost importance.

Kandt did not simply install 340 metres of sheet piling and drill 270 piles into the ground for RIF010 based on a drawing. “We were involved at a fairly early stage,” says project manager Bastiaan Verheul. “When the idea of a surf pool in Rotterdam city centre was being developed, co-initiator Mobilis was already in contact with Arie Kandt, founder of the foundation company that bears his name. At first, this was purely to explore, at a high level, the possibilities and limitations of building a wall, a floor and a turbine in the Steigersgracht. We all know that a lot of water had to flow down the Maas before the plans became concrete, but in August 2022 Mobilis began serious engineering work. This was an iterative process, with a lot of back and forth, in which Kandt had input on what was technically feasible in terms of construction, until a workable design was ready.”
Interconnected pontoons
The work began with the construction of an access ramp on the Markthal side and a lifting frame to get the pontoon sections into the water without damaging them. Verheul explains: “The interconnected pontoons we used, measuring 12.00 by 21.00 metres, were assembled from 20 separate sections transported by road. The frame was needed to lower the sections on a hinge from the quay into the water, which was 2.50 metres lower. The sheet piles and piles were installed from the interconnected pontoons.”
Battered piles
The sheet piles were driven into the canal using a high-frequency vibratory hammer with variable moment. Verheul explains: “Most of the sheet piles were installed at an angle to avoid hitting the existing quay wall’s foundation piles, which are also inclined. The existing quay wall, including its foundation, remained completely intact. The angle also helps maximise the width of the wave pool in the canal. We also had to take the trees along the canal into account. Pruning was only permitted to a limited extent, so it took careful planning, and in some places we had to install the sheets in several passes.”
Time savings
The next phase involved installing the pile foundation for the underwater concrete slab. “That’s when things really started getting busy inside the cofferdam,” Verheul continues. “As with many projects, the construction schedule here was under considerable pressure. To save time, we agreed with Mobilis and Verboon to carry out the piling and earthworks in phases. We had to drill the piles without vibration, while Verboon was responsible for clearing the cofferdam of silt. By bringing in a second piling rig and giving each other as much room as possible, we found an excellent balance and saved time without losing sight of safety.”
For RIF010, Kandt drilled 270 Leka piles, up to 23.00 m long, into the ground, both vertically and at an angle. All the piles were drilled to depths of 2.00 to 4.00 m below water level. Sheet piles ranging from 8.50 m to 10.00 m in length were installed. “To make the transition from the underwater concrete slab to the ‘beach’ on the Wezenbrug side, another sheet pile wall was installed so that a connecting slab could be built in a dry cofferdam,” Verheul adds. “This final stage brings to a close a great story in which preparation and cooperation with the contractors played a leading role.”
Een zakelijke vraag aan Kandt Aannemings- en Funderingsbedrijf BV? Neem contact op
Wie aan het golfbad RIF010 werkte
- grondwerkbedrijfVerboonIn dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectRIF010
- OnderwerpFoundation techniques
- BedrijfKandt Aannemings- en Funderingsbedrijf BV
- BedrijfVerboon