Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
Tekst Tjerk van DuinenFotografie CRUX Engineering BV en Architectenbureau J. van Stigt

CRUX Engineering BV’s advisers have no shortage of exciting and unusual projects to work on.
The Rijksmuseum, the Conservatoriumhotel, the University of Amsterdam Library and high-profile new-build projects such as NHOW Amsterdam RAI Hotel, The Valley, Sluishuis (Amsterdam) and Wonderwoods (Utrecht): they all seem like the cream of the crop. For CRUX, a consultancy specialising in geotechnical engineering, hydrogeology and soil, they are all part of the day job. And the same goes for De Koepel in Haarlem.
The collaboration with engineering consultancy Van Rossum is certainly proving fruitful. Almost all the projects listed above are joint ventures with Van Rossum, says Auke Balder, whose work as Senior Specialist focuses mainly on excavation support, effects on the surrounding area and monitoring. “Our long-standing collaboration makes designs more efficient and eliminates risks at the interface between geotechnical engineering and structural design. De Koepel is, of course, a fantastic project to work on, one that warms your heart as an engineer. On behalf of Stichting Panopticon, we designed the foundations for the basement floor and the circular excavation pit.”
Minimising impact
The collaboration began at an early stage. Balder: “Van Rossum and we started by taking stock: what condition were the existing timber foundation piles in? And were the old drawings we had still accurate? As Shanti Brahmatewari mentions in the previous article, the building was in surprisingly good condition. The next step, working closely with Van Rossum, was to construct an excavation pit and basement floor in such a way as to have minimal impact on the listed building. The effects of deformation on the building were assessed in advance using computer models for various construction options. The option ultimately chosen involved installing sheet piles first, then pouring the ground-floor slab, a circular disc fifty metres in diameter, and excavating beneath the new floor. Once the required depth had been reached, the basement floor was poured against the sheet piles, forming a sealed basement box.”

Monitoring plan
Such a major underground renovation, however, starts with a carefully prepared plan. Balder: “We drew up a monitoring plan with threshold values for deformation of the excavation pit and the building at each construction stage. Deformation was monitored every five metres on the building’s internal and external façades. Inclinometer measurements were also taken every ten metres along the excavation pit. These measure the deflection of the sheet piles. The contractor, HBB, commissioned Fides Expertise to carry out the monitoring. We were regularly on site during sheet-pile installation and excavation to analyse and discuss the measurement results. This keeps the risk of damage from construction work to a minimum and means you can intervene if threshold values are exceeded.”
Jetting
The excavation pit was designed with sheet piles installed without vibration down to the watertight clay layer, at a depth of thirteen to fourteen metres. Balder: “But this is happening right next to the building’s interior façade, which is more than a hundred years old. At the foundation contractor Sterk’s recommendation, the piles were pressed in using a silent piler in combination with jetting, which uses water to reduce the resistance of the sand. A pile can encounter all sorts of things underground, from timber to old foundations, and these can cause vibrations. The ground was therefore cleared of obstacles as far as possible in advance. When the excavation pit was dug, the sheet piles deformed slightly less than expected, probably thanks to the beneficial effect of the circular excavation pit.”
Relief well dewatering
The advisers had to account for the high groundwater pressure in Haarlem when designing the basement floor. Balder: “The basement is about six metres deep, and relatively little weight will bear down on it. The water pressure is greater than the downward pressure, so tension anchors were needed to compensate. In addition, Mos Grondwatertechniek designed and implemented relief well dewatering for the final metres of excavation for the pile caps, to lower the water pressure beneath the deepest clay layer. The pressure can build up enormously, and you do not want the bottom of the excavation pit to burst upwards as a result.”
The project has now reached its deepest point, and the basement floor with tension anchors has been poured successfully. The deep excavation inside the building had no significant impact on De Koepel, causing at most a few millimetres of movement. CRUX’s work is now complete. “But I’d be happy to come back and admire the finished result,” Balder concludes. “De Koepel was an impressive building even before the renovation. The renovation, with its view through to the new underground courtyard, makes it even more impressive.”
Vraag over dit verhaal? Stel je vraag
Wie aan De Koepel in Haarlem werkte
- aannemerHBBIn dit verhaal
- adviesbureau voor geotechniekCRUXIn dit verhaal
- funderingsaannemerSterkIn dit verhaal
- spanningsbemalingMos GrondwatertechniekIn dit verhaal
- adviesbureau voor geotechniekCRUX Engineering BVIn dit verhaal
- ingenieursbureauVan RossumIn dit verhaal
- aannemerHBB Fides ExpertiseIn dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectDe Koepel
- OnderwerpProduct information
- BedrijfHBB
- BedrijfCRUX
- BedrijfSterk
- BedrijfMos Grondwatertechniek
- BedrijfVan Rossum