Building beneath a monumental dome
Tekst Tjerk van DuinenFotografie Auke Balder/CRUX Engineering BV

A long-held ambition is finally becoming a reality for Haarlem: the city is to have an institution of higher education. The former De Koepel prison has been selected for conversion into a University College. Stichting Panopticon is driving the project, which will also transform the surrounding site into a place for student accommodation, social housing, retail and hospitality.
HBB Groep is currently hard at work renovating De Koepel, a listed prison building designed by architect Willem Metzelaar. The dome was built according to the panopticon principle: a large, circular hall surrounded by stacked rings of cells, which could be monitored from the centre of the dome. For its new use, architectural practice J. van Stigt has drawn up plans for a cinema in a new basement and a ring structure with two floors for workspaces, businesses and startups.
Good condition
HBB Bouw engaged Van Rossum Raadgevende Ingenieurs to ensure the structural work goes smoothly. Shanti Brahmatewari, project manager and structural engineer at Van Rossum, says: “From day one, we have been working with Van Stigt’s design team to find an effective, intelligent way to integrate the new design into the existing building, taking account of the existing ground conditions, foundations and structures. A survey of the existing foundations by Fugro showed that De Koepel was very solidly built and in good condition, as was its timber pile foundation. The steel structure of trusses and tie rods that forms the dome is also well maintained. The dome has since been insulated and rooflights have been installed.”
Top down
The main structural challenges were at and below ground-floor level. Brahmatewari explains: “The building is to have a new basement level, 50 metres in diameter, at -5.70 metres below ground level. It will be accessed via a staircase from a circular opening in a new ground-floor slab. On projects like this, you would normally work from the bottom up: install the sheet piles, excavate, dewater the excavation, pour the basement slab and then construct a ground-floor slab. In this case, in consultation with HBB and CRUX Engineering BV (see next article), we decided to pour the ground-floor slab after installing the sheet piles, then construct the basement slab by excavating from a kind of pit. This means building the basement from the top down. During construction, the ground-floor slab will carry construction traffic, while in use it will support the new steel structure for the upper floors. This means it must withstand traffic loads of 40 to 50 tonnes up to the opening.”
Ground-floor slab
Construction work inside the dome began several months ago. First, a trench was cut into the old ground-floor slab alongside the ring of cells. A sheet-pile wall was then installed without vibration just 1.5 metres from the cell ring. Brahmatewari says: “The sheet-pile wall serves as a watertight excavation enclosure, but also supports the ground-floor slab with a series of screw-injection piles. At the same time, the slab braces the top of the sheet-pile wall. We have taken a number of measures to keep the slab as thin as possible. A thicker ground-floor slab would mean excavating deeper, more dewatering and even greater upward groundwater pressure on the basement slab. We ultimately opted for a cast in-situ ground-floor slab with unbonded prestressing, combined with local thickening to distribute the forces effectively.”
Basement slab
The soil beneath the new slab was then excavated through the opening, and grout-injected tension anchors were installed from the basement and from ground-floor level to secure the basement slab, which is partly founded on soil and partly on piles. “This 50-metre-diameter slab has to hold back around 5.5 metres of groundwater. To achieve this, 85 radially positioned tension anchors have been installed,” Brahmatewari explains. “The groundwater table in Haarlem is high. That is why it is so important to keep the ground-floor slab as thin as possible. Every centimetre less excavation depth helps.”
Lightweight structure
Once the slabs have been installed and have cured, construction of the above-ground section can begin. Van Rossum’s team has designed a lightweight steel structure for the circular galleries, comprising HEB160 columns, HEA260 beams and Comflor 100, a lightweight, shallow steel composite floor system. Brahmatewari says: “This will be an elegant, slender structure in steel and glass, with floor levels exactly matching those of the prison cells. The circular shape is achieved by installing the beams of the inner ring in segments. The steel ring that closes off the centre of the ground-floor slab is curved. The entire superstructure has been designed to be 100% demountable, so that, if required, it can be removed at a later stage and reused elsewhere.”
Vraag over dit verhaal? Stel je vraag
Wie aan De Koepel in Haarlem werkte
- aanjager van dit projectStichting PanopticonIn dit verhaal
- ArchitectenbureauJ. van StigtIn dit verhaal
- aannemerHBBGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
- constructiefVan Rossum Raadgevende IngenieursIn dit verhaal
- adviesbureau voor geotechniekCRUXGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
- funderingsaannemerSterkGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
- spanningsbemalingMos GrondwatertechniekGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
- ontwerpteamArchitectenbureau J. van StigtIn dit verhaal
- adviesbureau voor geotechniekCRUX Engineering BVGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
- ingenieursbureauVan RossumGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
- aannemerHBB Fides ExpertiseGenoemd in Underground extension of De Koepel in Haarlem: design, monitoring and collaboration
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectDe Koepel
- ThemaBouwen in de bestaande stad
- OnderwerpProjects
- BedrijfStichting Panopticon
- BedrijfJ. van Stigt
- BedrijfVan Rossum Raadgevende Ingenieurs
- BedrijfArchitectenbureau J. van Stigt