Geopolymer concrete fits Amsterdam’s sustainability ambitions
Tekst Tjerk van DuinenBeeld Gebr. De Koning, Van Dijk Beton, Tjerk van Duinen

Koffiefabriek quay renovation
In several countries, cement-free concrete is widely used. The Netherlands is somewhat of an outlier in this respect, but the tide is beginning to turn. Under the current NEN standard, concrete produced without hydration cannot be called concrete. This prevents many clients from using cement-free concrete. That is a shame, because the CO2 footprint of geopolymer concrete, for example, can be around 50 to as much as 75% lower than that of traditional Portland cement-based concrete. Gebr. De Koning, a civil engineering contractor, and producer Van Dijk Beton are not prepared to wait on the sidelines for the standards to change. They have joined forces to deliver projects using geopolymer concrete wherever possible. A fine example is the new quay wall at the former Koffiefabriek in Amsterdam.

Commissioned by the Municipality of Amsterdam, 200 metres of quay wall have recently been replaced as part of the redevelopment of the site on the Duivendrechtsevaart, near Overamstel metro station. Gebr. De Koning renewed the quay as far as Van der Valk Hotel Amsterdam-Amstel, prepared the Koffiefabriek site for construction of an apartment building and created new moorings for a number of houseboats. Precast concrete hanging panels were used for the quay, some of them made with geopolymer concrete.
The tender
The Municipality of Amsterdam, which has strong sustainability ambitions, put the project out to tender under a UAV-GC contract with an MEAT award criterion, with sustainability and BLVC (Accessibility, Liveability, Safety and Communication) as the main pillars. For Gebr. De Koning, it was a challenging project and an opportunity to put its expertise in quay walls to good use while sharing the sustainability ambitions. At the same time, Van Dijk Beton was taking part in a ProRail Innovation Partnership to develop a sustainable platform retaining wall. Van Dijk Beton joined the innovation programme with a geopolymer concrete element incorporating secondary aggregates and partial (basalt) fibre reinforcement. At TU Delft, Noah Wols had begun his graduation project on fibre-reinforced geopolymer concrete and approached Gebr. De Koning to ask whether he could carry it out there. Matthias Mast, project manager at Gebr. De Koning: “Sometimes the pieces of the puzzle fall into place perfectly. We already had a good working relationship with Van Dijk Beton, and then Noah and the Koffiefabriek project came along. Noah got a behind-the-scenes look at Van Dijk Beton during the Innovation Partnership for sustainable retaining walls, graduated successfully with a project on fibre-reinforced geopolymer concrete and now works at Gebr. De Koning as a work planner and structural engineer.”

Winning points
Gebr. De Koning ultimately won the Amsterdam tender with its own design and MEAT submission, which proposed the use of concrete hanging panels. Paul de Vries, Strategic Development and Sustainability Manager at Van Dijk Beton, is keen to raise the profile of sustainability and sustainable concrete. “The Betonakkoord states that the sector will take measures to improve concrete’s environmental profile. In 2021, Van Dijk Beton qualified for ProRail’s Innovation Partnership and began developing sustainable retaining walls made of geopolymer concrete. It was an excellent opportunity to gain experience with the material and investigate the possibility of certification.” De Vries smiles: you could think of a hanging panel as an inverted retaining wall, with largely the same product properties. “In its MEAT submission, Gebr. De Koning had stressed that it wanted to seize opportunities to make the project more sustainable as it progressed. We then jointly set the goal of building part of the quay wall using hanging panels made of cement-free concrete. The Municipality of Amsterdam approved this application.”
Geopolymers
The environmental benefits of geopolymer concrete are substantial. Wols: “Traditional cement-based concrete production has a double CO2 burden because of cement production. In geopolymer concrete, the cement is replaced by other binders. Alkaline activation triggers polymerisation, forming long chains that turn the mix into a stone-like material with the same properties as concrete. Thousands of years ago, the Romans were already using volcanic ash to make concrete. This building material has long been widely used and certified in Australia, the UK and Eastern Europe. In other Western countries, however, the concrete industry has been based on cement for almost 100 years, and all the standards are built around it. For example, hydration must take place. This does not happen with geopolymer concrete, so it cannot be called concrete, which deters many clients from using it. Fortunately, more and more clients, including ProRail and local authorities, are taking up the challenge. As sustainability becomes increasingly important, I expect the prospects to improve. We still have to assess the product ourselves for each project, because it has not yet been certified.”



An ambitious client
That is why contractor Gebr. De Koning is pleased to work with a client such as the Municipality of Amsterdam. Mast: “If we want to take this further, we need ambitious partners. The Municipality of Amsterdam is strict and thorough, and wants everything to go smoothly, but it is also ambitious when it comes to sustainability. As a result, the preliminary process with the municipality and the Environmental Service went very smoothly. We have also found scope for innovation at other major municipalities, such as Rotterdam and Utrecht, which have considerable expertise in sustainable development, with additional resources available to support research.”
Given a second life, with zero emissions
The Koffiefabriek project was completed last June after ten months of work. It began with preparing the future building plot for construction, followed by demolition and the construction of 80 metres of quay wall along the plot. Mast: “The Koffiefabriek had been demolished down to the floor much earlier. That floor also had to be removed, along with the old pile foundation down to four metres below ground level, because it was anchored to the quay wall. A temporary cofferdam was installed in the water beside the quay using a silent piler, and at the end of the project it could be extracted electrically. The existing quay wall was then demolished, with the reinforcing steel and concrete separated and removed for recycling. A steel sheet pile wall was installed for the new quay wall and secured with tie rods. The AZ18 sheet piles were sourced from other projects, inspected for condition and given a second life at the Koffiefabriek. Structurally, this construction will last for 100 years. The second phase of the quay works, approximately 120 metres, was carried out in a similar way. This section extends to near Van der Valk Hotel.”
Dowel connection
To finish the quay, the sheet pile wall was fitted with a steel capping plate. Wols: “The 1.20-metre-high hanging panels were supported on it using dowel connections. Grout fills the gap and bonds the hanging panels to the foundation. The precast hanging panels were faced on site with genuine bricks in a mix of colours. That is the only downside of projects like this: the precast polymer concrete elements are invisible, and all you see is a beautiful 200-metre-long brick-faced quay.” Meanwhile, all the houseboats have been reconnected to their original locations, with access via steps or walkways between the new mooring posts. De Vries is positive about the use of polymer concrete. “Hundreds of kilometres of quay walls in Amsterdam are awaiting renovation. Geopolymer concrete is ideal for these quay projects. It has a substantially lower CO2 profile, in keeping with the sustainability ambitions of the Municipality of Amsterdam. Gebr. De Koning and Van Dijk Beton are keen to take this further.”
Een zakelijke vraag aan Van Dijk Beton? Neem contact op
Wie eraan werkte
Koffiefabriek in Amsterdam
- producentVan Dijk Beton
- aannemerGebr. De Koning
- opdrachtgevergemeente Amsterdam
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectKoffiefabriek
- ThemaMinder CO2 in beton en staal
- OnderwerpConcrete
- BedrijfVan Dijk Beton
- BedrijfGebr. De Koning
- Bedrijfgemeente Amsterdam


















