General

Concrete & steel in legal perspective

Tekst en beeld Joost Haest, Severijn Hulshof Advocaten

Joost Haest, Severijn Hulshof Advocaten.
Joost Haest, Severijn Hulshof Advocaten.

In the wake of Covid, the outbreak of the war in Ukraine and the world’s unstable geopolitical relations, rising steel prices continue to stir (legal) debate. In a very recent judgment dated 28 October 2025, the Amsterdam Court of Appeal (ECLI:NL:GHAMS:2025:3021) issued a highly interesting ruling on whether substantial increases in steel prices may be passed on, where the contract includes an agreed ‘fixed-price clause’. Unlike the court of first instance, the Court of Appeal held that the contractor may pass on the sharp rise in steel prices to the client from the time the contractor warned of the need for a price increase.

The parties entered into a construction contract for a steel structure forming part of a chocolate factory, for a contract sum of € 2.85 million. The Metaalunie Terms and Conditions apply to the contract. A fixed-price clause was handwritten into the contract, stating: ‘The contract price is fixed until completion of the work. Construction starts May 2021’.

After the contract was signed, several major increases occurred in cost-determining factors. Prices for beam steel, sheet steel and hollow sections rose sharply, as did those for wall and roof panels. The contractor also faced increases in raw material prices, a sharp rise in the cost of steel preservation, steeply rising prices for fasteners and higher equipment costs. The costs claimed by the contractor exceed € 900,000.

The contractor first relies on Article 7 of the Metaalunie Terms and Conditions. This provides that a contractor may pass on to the client increases in cost-determining factors that occur after the contract has been signed. The Court of Appeal held that, by agreeing to the fixed-price clause in the contract, the parties had excluded the application of Article 7 of the Metaalunie Terms and Conditions. The Court considered it particularly significant that the documents established that the handwritten provision agreeing a fixed price was of great importance to the client. The correspondence also shows how important this was. According to the Court, the clause ‘construction starts May 2021’ cannot, for the purposes of Article 7 of the Metaalunie Terms and Conditions, be interpreted as meaning that the far-reaching entitlement under that article would revive if the intended start date were missed. The contractor’s reliance on Article 7 of the Metaalunie Terms and Conditions therefore fails in this case.

In the alternative, the contractor relies on Article 7:753 of the Dutch Civil Code. This provision allows the court to adjust the price in the event of cost-increasing circumstances that (i) arise or come to light after the contract is signed, (ii) cannot be attributed to the contractor, and (iii) are circumstances the contractor did not have to take into account when setting the price, provided that (iv) the contractor has met its duty to warn. The Court of Appeal found that the parties had not expressly excluded reliance on Article 7:53 of the Dutch Civil Code. Moreover, given the clause stipulating that construction was to start in May 2021, the client could not reasonably have expected the price to remain unchanged in every case if the start was delayed. 

The Court of Appeal went on to find that the contractor had to allow for some degree of price fluctuation, but was not required to anticipate a price increase 50% greater than the fluctuations in previous years. According to the contractor, the extreme price increases had already begun in January 2021. However, since the contractor did not explicitly fulfil its duty to warn until 19 May 2021, the Court held that the contractor would be compensated only for price increases from 19 May 2021 onwards. Finally, the Court held that the contractor must provide a further calculation of the alleged loss, to which the client may then respond. In any event, it is clear that this judgment represents a major victory for the contractor.   

Vraag over dit verhaal? Stel je vraag

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ThemaNormen, testen en aansprakelijkheid
  • OnderwerpGeneral
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.