Targeted technical investigation averts major jacking operation at Strijkviertel viaduct on the A12
Tekst Roel van GilsBeeld Concept Ingenieurs / Artjan Kwant

The condition of bridges and viaducts across the country is monitored through ongoing condition surveys. In some cases, a visual inspection alone is not enough to diagnose the state of maintenance of a structure. Further investigation can help gather the necessary information. However, conventional inspection tools are not always adequate, for example when structural elements are difficult to access, such as the space beneath expansion joints. Targeted technical investigation using specialist equipment can provide a solution. Recently, it even prevented a jacking operation at the Strijkviertel viaduct on the A12 near De Meern.

Concept Ingenieurs recognised the need for a better understanding of the condition of hard-to-reach structural elements. It therefore developed a range of inspection tools for use in confined spaces, such as around expansion joints and tooth-jointed connections. “Various fundamental elements of the main load-bearing structure come together beneath expansion joints,” says Ruud Meijer, director of Concept Ingenieurs. “These include bearings, prestressing anchorages and critical reinforcement details. Given the forces at work, it is particularly important to understand the condition of these elements in this location.”
Pitting corrosion
Expansion joints are regularly replaced. According to Meijer, this presents an excellent opportunity to investigate the concrete surfaces beneath them, because “sound management naturally requires the condition of these structural elements to be checked thoroughly on a regular basis. The need for inspection is all the greater because expansion joints can leak. De-icing salts (chlorides) then flow through the joint with rainwater, along these structural elements. Chlorides pose a threat to the reinforcement and other steel components beneath the expansion joint. In reinforcement, they can cause a form of corrosion (pitting corrosion) that can lead to a relatively rapid loss of strength. However, the space beneath an expansion joint is difficult to access for routine inspection and maintenance. As a result, these structural elements often do not receive the attention they deserve.”

Confined spaces
Leaks in expansion joints are identified during routine inspections, Meijer acknowledges. “The risk of deterioration to the structural elements below is often noted, but not quantified. At that point, the asset manager does not know what the situation is, making it difficult to assess which management measures are appropriate.”
The Strijkviertel viaduct is a typical example of a situation in which asset manager Rijkswaterstaat was compelled to take measures based on an unquantified risk. “There was an investigation report behind the decision, but it was limited in scope,” says Jan-Jaap van den Brink, technical adviser for structures at Rijkswaterstaat. “It was known that the expansion joints had been leaking for some time. The accessible sections of the abutments also showed extensive concrete damage and chloride contamination. On the basis of this information, it was decided to carry out large-scale concrete repairs. Partly in light of experience with similar viaducts, it was decided as a precaution to jack the viaduct by approximately 1 metre. This was the only way to carry out durable repairs to the suspected concrete damage in the hard-to-reach sections of the deck. The jacking operation was therefore included in the contract documents.”
Plan of approach
Heijmans Infra Civiele Specialisme saw potential in Concept Ingenieurs’ new tools. Their use was part of its plan for work on the Strijkviertel viaduct. This made it possible to carry out potential measurements, cover measurements, core sampling and a visual inspection of the reinforcement on the concrete surfaces beneath the expansion joints. The inspectors needed an opening of just 4 cm. The results presented a different picture from what had been expected. Compared with the accessible front face of the supports, the condition of the concrete deck beneath the expansion joints was remarkably good. A few minor (potential) areas of damage were found, but nothing on the scale anticipated. Jacking the deck proved unnecessary. This came as a huge relief to Heijmans and Rijkswaterstaat. Van den Brink says: “It is a huge relief not only from a technical point of view, but also for the surrounding area. The jacking operation would have required a 12-day road closure. That would naturally have had a major impact on traffic flow and the surrounding area.”
The investigation at the Strijkviertel viaduct has been completed. Maintenance work is still to be carried out, but the much-reduced scope means traffic on the viaduct will be little affected. Meijer concludes that the new tools have many more potential applications: “They are currently being used successfully on various other projects, including viaducts with tooth-nib bearings, which are known to be difficult to inspect.”
Vraag over dit verhaal? Stel je vraag
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ThemaBruggen en kunstwerken langer mee
- OnderwerpGeneral


















