General

Smart combi wall shares real-time information

Tekst Roel van GilsFotografie ArcelorMittal en Topview Nederland

Smart combi wall shares real-time information

As container volumes at the Port of Rotterdam are expected to continue rising sharply in the coming years, the quay at Prinses Amaliahaven is being extended. The construction of new deep-sea and inland shipping quays will enable cargo-handling companies to further develop the undeveloped sites around this part of the port. To monitor the behaviour of the quay structure both during installation and in service, the Port of Rotterdam Authority is using a ‘smart’ combi wall supplied by ArcelorMittal Projects.

The pipe piles were tested by applying load to the pipe in several stages using a hydraulic jack.

ArcelorMittal is a familiar name in the port area. “In the past, we worked with the Port of Rotterdam Authority to assess the master specification for feasibility, drawing on our many years of experience. It sets out the quality requirements that the steel for the combi walls must meet,” begins Patrick Mulders of ArcelorMittal. “We are therefore familiar with all the requirements and have prepared standard quality documents, such as ITPs (Inspection and Test Plans), a quality plan and measurement reports. Additional requirements apply, for example, to the straightness of the pipes, and there is an additional testing regime that allows stock pipes to be used. Slot detection systems are used on a sample basis to verify that the sheet piles have indeed remained in the interlocks.”

20,000 tonnes of steel

The new deep-sea and inland shipping quays have been designed as a combi wall: pipes with interlocks and intermediate sheet piles. “Given the 2.4-kilometre length of the new quay wall, the quantities involved are enormous,” says Mulders. ArcelorMittal is supplying 15,000 tonnes of pipe material and 5,000 tonnes of sheet piles. “As ArcelorMittal Projects, we were able to meet the project’s very challenging schedule by combining stock pipes with newly manufactured pipes. All the steel was transported by ship from the production sites to a specially equipped unloading quay at Prinses Amaliahaven.”

The new deep-sea and inland shipping quays have been designed as a combi wall: pipes with interlocks and intermediate sheet piles. (Image: Topview Nederland)

Monitoring pipe piles

Besides its scale, the project has another distinctive feature. Five pipe piles have been fitted with a monitoring system. “The system consists of a fibre-optic cable bonded along both sides of the pipe pile, over its full length. A reference cable has also been installed to measure temperature,” Mulders explains. “A steel protective tube has been placed over it to prevent damage to the system during transport and installation on site. The system enables the port authority to monitor strain in the pipe pile while filtering out the effects of temperature. It provides insight into the load on the pile and whether any deformation is occurring. It can be used both to validate the design model and to track the condition of the structure over time. Increased loading on the structure, whether physically detectable or caused by corrosion, is reflected in the fibre-optic readings.”

A steel protective tube prevents damage to the monitoring system during transport and installation on site.

Testing the monitoring system

The monitoring system was thoroughly tested at ArcelorMittal’s site. Mulders says: “All five pipe piles were checked to confirm the system was working and their readings were compared with the predictions. First, baseline measurements were taken with the pipe piles placed on H-beams so they were supported without being loaded. They were then tested further by applying load to the pipe in several stages using a hydraulic jack. This enabled us to measure the deflection and the load in the pipe.” As a backup, the five pipe piles were fitted with two additional protective tubes. If anything goes wrong during installation, new fibre-optic cables can subsequently be installed by grout injection. The entire combi wall has now been installed successfully, including the five pipe piles fitted with the monitoring system and distributed along the 2.4-kilometre quay. 

SmartSheetPile

The smart combi wall concept at Prinses Amaliahaven dovetails seamlessly with ArcelorMittal’s recently launched SmartSheetPile concept. “We can tailor the concept to the specific project, depending on the client’s requirements,” says Mulders. “Sensors are used to capture all kinds of parameters, both during installation and throughout the sheet pile wall’s service life. These include measuring strain and deformation, as well as monitoring corrosion over the structure’s lifespan. It is also possible to detect impact loads and inclination. Data are monitored in real time and sent to an online dashboard. The aim is to gain an even better understanding of the behaviour and performance of steel structures. This could lead to the development of new models and calculation methods, and ultimately to optimised steel use.”   

Vraag over dit verhaal? Stel je vraag

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • OnderwerpGeneral
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.