Projects

Heinenoordtunnel gains thousands of drilled anchors and tonnes of steel

Tekst Roel van GilsBeeld Interboor Midsland

Interboor Midsland is voor het plaatsen van de verankeringen BRL-gecertificeerd.
Interboor Midsland is voor het plaatsen van de verankeringen BRL-gecertificeerd.

Rijkswaterstaat has used the renovation of the Heinenoordtunnel as an opportunity to equip it with a two-level central tunnel gallery containing an escape route and service walkway. The service buildings and anti-glare louvres above the tunnel entrances have also undergone a major overhaul. Jos van den Bersselaar Constructie supplied the steel structures for all these elements, in turn calling on Interboor Midsland, a BRL-certified company, to drill thousands of anchors into the 55-year-old tunnel.

Interboor Midsland drilled thousands of anchors into the 55-year-old tunnel.

The biggest part of the renovation was undoubtedly the construction of the central tunnel gallery, a project completed last summer by the Savera III construction consortium during a closure lasting just four weeks. “The central tunnel gallery was built using a precast concrete wall, which was moved into position. We installed steel grating floors along its entire length to form an escape walkway and a service walkway,” explains John Verhoeven, project manager at Jos van den Bersselaar Constructie. Interboor Midsland drilled more than 3,000 anchors to secure the concrete wall and the grating floors.

Heavy angle sections

During construction of the central tunnel gallery in the four-week closure, Jos van den Bersselaar Constructie and Interboor Midsland worked side by side, following the construction consortium’s progress. “We worked section by section, from top to bottom,” says Wilko van Oosten, anchoring specialist at Interboor Midsland. “First, we installed the heavy angle sections to anchor the concrete wall to the tunnel ceiling. The construction consortium then used special vehicles to move the concrete elements into position, one section at a time. To avoid hitting and damaging the existing reinforcement in the tunnel, we were not allowed to use diamond drilling in the ceiling, so we used hammer drilling instead.” Verhoeven adds: “As this technique is less accurate, we provided four slotted holes in the angle sections, giving us an extra option for positioning the two anchors. The time pressure was immense, and we could not afford any delays.”

A structure for the new anti-glare louvres is being built above the tunnel entrances.

A well-oiled machine

Once a section of concrete walls had been installed, the Jos van den Bersselaar Constructie and Interboor Midsland team began installing the steel grating floors. “We built a working platform so we could install all the necessary components from top to bottom,” Verhoeven explains. “That meant first drilling the anchors for the upper walkway, then installing the steel structure and laying the grating floor. We then moved the working platform forward by a few metres so we could build the escape walkway. Together, we worked our way through the entire tunnel in three weeks, like a well-oiled machine. Seven days a week, with two shifts a day. The great thing was that the Interboor Midsland fitters also helped us build the walkways. The collaboration was excellent.” There is an escape door in the tunnel wall every few metres. At these locations, Jos van den Bersselaar Constructie installed heavy angle sections as additional impact protection. 

BRL-certified

Interboor Midsland is BRL-certified for installing anchors. “Rijkswaterstaat makes this a requirement for anyone wanting to work on its structures,” says Van Oosten. “We have also taken on the task of testing the connections in practice and maintaining the process certificate.” The work is not quite finished yet, as both companies are still active in and around the tunnel. “The service buildings are being given a makeover and fitted with a second skin, which requires a substantial steel structure. We are also converting the lift shafts into stairwells. In addition, we are building the structure for the new anti-glare louvres above the tunnel entrances. Interboor Midsland is anchoring all these structures to the existing tunnel structure using drilled and bonded anchors.” 

Een zakelijke vraag aan Interboor Midsland? Neem contact op

Wie eraan werkte

Heinenoordtunnel, renovatie

  1. de staalconstructiesJos van den Bersselaar Constructie
  2. bouwcombinatieSavera III
  3. OnderaannemersInterboor
  4. OnderaannemersVan den Bersselaar Constructie

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectHeinenoordtunnel
  • OnderwerpProjects
  • BedrijfJos van den Bersselaar Constructie
  • BedrijfSavera III
  • BedrijfInterboor Midsland
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.