Projects

New DC built entirely from precast concrete

Tekst Roel van GilsFotografie Goldbeck

Als totaalleverancier van prefab betonelementen leverde Preco het complete betoncasco voor het nieuwe distributiecentrum.
Als totaalleverancier van prefab betonelementen leverde Preco het complete betoncasco voor het nieuwe distributiecentrum.

The law of large numbers usually applies to the construction of a distribution centre. The new DHG Smartlog 9 in Rotterdam’s Botlek area is no exception, with a total floor area of just under 50,000 m². To maintain the pace of construction, contractor Goldbeck deliberately opted for extensive prefabrication. As a one-stop supplier of precast concrete elements, Preco delivered the complete precast concrete frame for the new distribution centre.

To maintain the pace of construction, contractor Goldbeck deliberately opted for extensive prefabrication.

Smartlog Rotterdam 9 is located at a unique, prominent site for the Port of Rotterdam, at Boyneweg 3-11 in the Botlek area. Botlek is a hub for many supraregional activities, with hinterland connections by rail, road and water. “Following Smartlog Rotterdam 8, we also supplied the complete precast concrete frame for number 9,” says Stefan Jongewaard, project manager at Preco. “It is a similar project for us, where we were able to supply virtually our entire range of precast concrete elements. This project shows what we can do: everything comes together here, and that is also our strength. We are one of the few companies in the Netherlands able to manufacture everything under one roof.”

Complete range

The new distribution centre comprises 40,921 m² of warehouse space, 3,445 m² of mezzanine, 1,828 m² of office space, plus around 4,000 m² of external area. “We supplied the columns, beams, hollow-core slabs, loading bays, façade panels, internal walls, stairs and landings,” Jongewaard explains. “The building is divided in two by a fire wall, which we also produced at our factory in Apeldoorn, along with the insulated hollow-core slabs for the ground floor. As we prepared the complete precast concrete frame, the work on site was simply a matter of assembly.” Preco carried out the project for Goldbeck, a company of German origin with operations across Europe. “We regularly work for its Dutch subsidiary, and since last year we have also been engaged by the parent company for projects in Germany.”

Logistical challenge

To keep pace with the rapid construction schedule, Preco began producing the first batch of concrete elements as early as October 2022. “We manufactured all the components in-house and did not have to outsource a single thing, despite also having another Goldbeck distribution centre under contract at the same time.” Asked about the challenges of the project, Jongewaard cites the calculations needed to accommodate the high loads on the sloping hollow-core slabs in the offices and mezzanine. “But above all, it was a logistical challenge. It is a huge building, while space on site is limited. For that reason, we had to increase storage capacity at our factory in Apeldoorn so we could deliver on call-off. And everything went smoothly, thanks in part to the good cooperation with the Goldbeck team.” Preco delivered the final precast concrete elements at the end of April.   

Een zakelijke vraag aan Preco? Neem contact op

Wie eraan werkte

DHG Smartlog 9 in Rotterdam

  1. totaalleverancier van prefab betonelementenPreco
  2. aannemerGoldbeck

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectDHG Smartlog 9
  • ThemaBouwen als productieproces
  • OnderwerpProjects
  • BedrijfPreco
  • BedrijfGoldbeck
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.