Schalkstad car park gets ingenious steel structure: smart, slender and exceptionally strong

Tekst Lieke van ZuilekomFotografie Vic Obdam en Tullingh & Partners

Schalkstad car park gets ingenious steel structure: smart, slender and exceptionally strong

Exceptional buildings call for a high-quality frame.

The same applies to the new above-ground car park at Schalkstad, a residential and retail district in Haarlem. Vic Obdam Staalbouw is delivering a complete steel structure, including composite steel-deck floors, in collaboration with Tullingh & Partners and on behalf of BAM Wonen Speciale Projecten.

Steel structure with 16m-span beams and 60 minutes’ fire resistance.

Vic Obdam Staalbouw’s steel structures form the backbone of many projects. “We offer a comprehensive yet specialised service, from 3D surveying and scanning through to the full design, fabrication, corrosion protection and erection of the steel structure. Our projects range from housing to commercial buildings, and from new-build to renovation and transformation,” says project manager Bart van der Gulik. “We also excel at alternative construction projects, such as inserting new floors into existing buildings, adding extra storeys and creating flexible, adaptable building volumes. We are often awarded the complete steel structure, including stairs and balustrades, roof and façade cladding, and floors, for which we work with trusted partners. For the design and installation of the composite steel-deck floors, that partner is Tullingh & Partners, which also frequently calls on Vic Obdam Staalbouw for its steel construction projects.”

A total of 15,000 m² of slender composite steel-deck flooring is being installed.

Tullingh & Partners specialises in building engineering, material supply and the delivery of metal roofing and façade systems and composite steel-deck floors. “Over the past few years, our companies have developed a strong working relationship,” says Charles van Oldenbarneveld of Tullingh & Partners. “Good examples include the transformation of the former office building on Willem Witsenplein in The Hague, the extension of the Royal Flora Holland flower auction in Aalsmeer, the expansion of a chemical plant at Westpoort business park in Amsterdam, and the new-build Schalkstad car park.”

Better, faster and smarter

“We work closely together on projects,” he stresses. “Using the architectural and/or structural design as our starting point, we always develop our own proposal. What options are there for building lighter, using fewer materials and reducing the environmental impact?” Van der Gulik adds: “For the Schalkstad car park, too, we mapped out the structure and potential improvements at an early stage. The original design specified an alternative floor from a different manufacturer, with a different profile. Tullingh & Partners proposed a slender type of composite steel-deck floor instead, providing more clear headroom between levels. The floors also exceed the specified standard for strength. Our joint calculations convinced both the lead structural engineer, Pieters Bouwtechniek, and the contractor, BAM Wonen Speciale Projecten. They also led to a specification amendment, approved by the municipality of Haarlem. At the end of 2018, we were awarded the contract to fabricate, supply and erect the complete structure, excluding the reinforcement and concrete.”

After 1.5 years of intensive collaboration, the project is nearing completion.

500,000 kilos of steel

The above-ground car park provides space for 600 cars. The building has five storeys, the top four of which are being built in steel. “We are using a total of 500,000 kilos of steel,” says Van der Gulik. “The structure consists of steel columns and beams spanning 16 metres. The high fire-resistance requirement posed a major challenge.   

In the event of a fire, the entire steel structure must remain standing for 60 minutes. We achieved this in part by reinforcing and encasing the columns in concrete. The steel beams have also been given a special fire-resistant coating.”

The original design called for the beams to be attached to the columns, he explains. “However, this could have caused major problems if the column steel failed. So we worked out an alternative solution with Pieters Bouwtechniek. In the current design, the beams are integrated into the concrete, passing right through the steel columns. This brought new challenges, including for Tullingh & Partners, which could no longer make connections at those points. We worked together to develop a good alternative for this as well.”

15,000 m² of composite steel-deck flooring

“We are installing no less than 15,000 m² of composite steel-deck flooring,” says Van Oldenbarneveld. “Installation follows the progress of the steel structure. As soon as the structure for one storey is complete, our steel decking is installed. It is quite a challenge, as the sheets are 11 metres long and are lifted into place in batches of 15. Precise planning and coordination are essential.” The overlapping installation method makes it possible to work very quickly and efficiently, he stresses. “The composite steel-deck floors are installed in just one week. We then have another week for finishing, after which the contractor can pour the concrete and Vic Obdam Staalbouw can start on the next storey.” 

Compared with traditional floor systems, composite steel-deck floors require considerably less concrete, says Van Oldenbarneveld. “This delivers substantial weight savings for similar spans and loads. The floors are also considerably thinner. The original design for the Schalkstad car park specified a 16 cm-thick floor, which we managed to reduce to just 13 cm without changing the span. We also increased the load capacity from 2.0 kN/m² to 3.0 kN/m². This means the car park is well prepared for the future, as the proportion of heavier electric cars continues to grow.”

The composite steel-deck floors are installed on 16-metre-long steel beams and connected to them with welded steel shear studs (pins). “More than 3,500 welded studs are needed on each storey, 14,000 in total. The result is excellent composite action between the steel structure and the composite steel-deck floor.”

Strong teamwork on site, with direct communication

Thanks to close teamwork on site and direct communication, Vic Obdam Staalbouw and Tullingh & Partners can complete one entire storey every four weeks. In week 4, erection of the final storey of the steel structure began. The structure is being finished around the perimeter with steel frames and approximately 4,000 timber slats, also supplied and installed by Vic Obdam Staalbouw. The project is due to be completed by the summer holidays of 2021. 

Een zakelijke vraag aan Tullingh & Partners BV? Neem contact op

Wie eraan werkte

Parkeergarage Schalkstad in Haarlem

  1. staalplaat-betonvloerenTullingh & Partners
  2. staalconstructieVic Obdam Staalbouw
  3. aannemerBAM Wonen Speciale Projecten
  4. hoofdconstructeurPieters Bouwtechniek

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectParkeergarage Schalkstad
  • OnderwerpProjects
  • BedrijfTullingh & Partners BV
  • BedrijfVic Obdam Staalbouw
  • BedrijfBAM Wonen Speciale Projecten
  • BedrijfPieters Bouwtechniek
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.