Amsterdam Van der Valk Hotel | A project of extremes

Amsterdam Van der Valk Hotel | A project of extremes

At the easternmost edge of Amsterdam’s Zuidas, Van der Valk has ‘found’ a triangular plot that is being built on in its entirety. The hotel chain has appointed Pleijsier Bouw as main contractor. The structural frame comprises a section of in-situ concrete and a section of precast concrete, with a visible ‘break’ at the seventh floor. A project of extremes, featuring a prestressing method that is innovative by Dutch standards.

The first pile was driven in at the end of November 2017, recalls Mark Moerdijk, project coordinator at Pleijsier Bouw. “We are responsible for everything from the groundworks through to completion of the thirteen-storey structural frame (55 metres high to the roof edge). Or, more accurately, ‘structural frame plus’, because the internal walls, floor screeds, plastering and tiling in the hotel rooms are also within our scope. Once the piles had been drilled, we were able to start the concrete work in early 2018. The hotel’s first seven floors were cast in situ, while the seven floors of the 234-room accommodation block above were built using precast concrete.”

Transfer floor

Pleijsier Bouw worked on the first seven floors from early 2018 until February 2019, while the precast section was completed in just four months. “The two are completely out of proportion, but that is inherent in the design,” explains Moerdijk. “The reception and delivery areas are on the ground floor. Above them is the four-storey car park, with a few technical rooms dotted around. All the cores were cast in situ in fair-faced concrete, as were a number of precast columns. The car park is completely open and, unlike the ground floor, will not have a curtain wall. Above the car park are two commercial floors, including a restaurant on the fifth floor and the conference centre with meeting rooms on the sixth. The seventh-floor slab forms the so-called transfer floor, supporting the seven-storey accommodation block made from precast elements. The transfer floor is no less than 90 centimetres thick and is designed as a table structure that transfers all the loads from the accommodation block to the cores and columns below.”

Innovative prestressing.

Prestressing

The first seven floors of the new hotel feature an innovative prestressing system. Moerdijk explains: “Our subcontractor Van Muijen Beton outsourced the prestressing to Interspan, a UK company with a method of its own. The prestressing strands are not placed loose inside a duct, but are grouted in place. If you drill through a strand, the structure remains stable. This bonded system is quite innovative and not common in the Netherlands. Using bonded strands also means that much less additional reinforcement is needed. The car park floors, for example, have only prestressing strands and a shrinkage mesh on the underside of the slab, with no additional reinforcement. That is certainly unusual. The stressing of the floor after casting was just as spectacular. The strands were gradually stressed the day after the first pour, reaching the full 100% after two weeks, with the strands elongated by as much as 25 centimetres.”

According to Moerdijk, the new hotel was designed entirely in 3D using BIM. “As well as being technically unusual, it is also far from an everyday sight aesthetically, with its unique design. The official opening will take place in May 2020.”    

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Hotel Van der Valk Amsterdam in Amsterdam

  1. hoofdaannemerPleijsier Bouw
  2. onderaannemerVan Muijen Beton
  3. voorspanningInterspan
  4. hotelketenVan der Valk
  5. wapeningsstaalBalvert Betonstaal BV

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectHotel Van der Valk Amsterdam
  • OnderwerpProjects
  • BedrijfPleijsier Bouw
  • BedrijfVan Muijen Beton
  • BedrijfInterspan
  • BedrijfVan der Valk
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.