Complex construction for powder-coating plant
Tekst Tamara BrouwersFotografie Reijrink Staalconstructie b.v.

In Wehl, Reijrink Staalconstructie is helping build Ansova’s new powder-coating plant. Project manager Tim van Dun: “Before Christmas, we erected just under 1,100 tonnes of steel. It’s a complex structure, but that’s no problem for us.”

Reijrink Staalconstructie is currently building the powder-coating plant where its own steel will soon be treated. “Yes, that is quite special,” says Van Dun with a laugh. “The fact that we produce the steel in a particular way and generate our own energy is important to Ansova, because the company will also be powder-coating in an environmentally friendly way. In general, we’re seeing sustainability become increasingly important to clients.”

The large production hall, 240 metres long and approximately 14,000 m2 in area, was completed in week 41. “Our core business is delivering projects of this size. We do our own engineering and our machinery is fully equipped for this kind of work. We’re good at putting in the metres and shifting the tonnes.” In week 50, Reijrink began work on the structure for the office, warehouse and loading and unloading hall.

Sections adapted to the internal structure
“To a layperson, large halls like these may look very similar, but that’s far from the case. We don’t sell any standard products and offer a bespoke solution for every client.” For Ansova, the role of principal structural engineer was assigned to another company, while Reijrink carried out the detailed calculations. “We largely realised the design as envisaged, with just a few minor changes. The production hall’s structure is quite complex, as required to accommodate the machinery that will be installed beneath it. There could be no columns in the open floor area, so the hall had to be designed accordingly. As a result, the choice and grade of sections were adjusted in some cases.”

Welding robot takes the strain
Reijrink also used the company’s Fabricator welding robot during production. “It’s great that it was able to contribute. We’re the first company in the world to use this welding robot. The Fabricator makes production of the various components much more efficient, and is operated by a single operator.”

Van Dun describes some of the challenges that arose during construction: “There was a transformer substation belonging to the network operator on the site, supplying part of the industrial estate. It was positioned in such a way that it would have been in the middle of the production hall’s side wall, and the network operator was unable to move it within the required timeframe. The façade therefore had to be adapted, and the steel structure was erected around the substation. The substation was eventually moved a few weeks after the side wall had been erected. We also had to build directly alongside high-voltage power lines. We opted to use a tower crane for the erection work, which meant we were working within the designated safe zone. Working safely always comes first, of course!”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Poedercoatfabriek Ansova
- staalconstructieReijrink Staalconstructie
- opdrachtgeverAnsova
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectPoedercoatfabriek Ansova
- OnderwerpProjects
- BedrijfReijrink Staalconstructie
- BedrijfAnsova