Dust-free pile cropping on the Blankenburg Connection

On the Blankenburg Connection, Blijleven Koppensnellers has once again shown that cropping foundation piles really is a specialist skill.
Using a brand-new crane and a pile breaker fitted with dust suppression, the family business cropped 580 foundation piles in stages on one of the largest infrastructure projects in the Netherlands. The work was fully integrated into the schedule set by client BAAK, with the team balancing on trestles and track mats 150 centimetres above the working surface. Just before this issue of GWW went to press, Blijleven Koppensnellers secured a follow-on contract to crop an additional 3,600 piles.


Pile cropping has traditionally been arduous, labour-intensive work, but Blijleven Koppensnellers has turned it into a fine art. “The piles are now sawn into using machinery, cropped hydraulically with dust suppression, and the rubble is scooped up with a small crane,” explains John Blijleven. “So pile cropping no longer creates a dust nuisance. We are the first company in the Netherlands to have developed our own dust suppression system, fitted to all 40 of our pile breakers. Unfortunately, not every contractor makes dust prevention a priority, even though it is mandatory. Fortunately, BAAK appreciates its importance.”


Blijleven Koppensnellers was mainly involved in cropping the piles for the entrance ramp to the Hollandtunnel on the Blankenburg Connection. “We cropped the square vk450 precast piles, with eight or twelve reinforcing bars, 25 millimetres in diameter, at depths of between 1 and 2 metres. We worked from a flexible position on trestles and track mats, following the contractor’s schedule. In this case, BAAK could not excavate everything at once, as that would have caused the ground to break open. Excavation was therefore carried out in stages, as was the pile cropping. The crane never had to leave the excavation. That is our strength: as a company, we are highly flexible. All in all, it was a successful project. It is always a pleasure working with infrastructure contractors.” And the feeling is mutual: the innovative family business has also been awarded a contract to crop a further 3,045 piles of the same vk450 type on the other side of the Hollandtunnel, plus another 625 piles of the same type at the entrance ramp to the Maasdeltatunnel.
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Blankenburgverbinding
- koppensnellen van funderingspalenBlijleven Koppensnellers
- opdrachtgeverBAAK
- prefab betonconstructiesVan Dijk Beton
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectBlankenburgverbinding
- OnderwerpProjects
- BedrijfBlijleven Koppensnellers
- BedrijfBAAK


















