High precision with heavy elements
Tekst Tjerk van DuinenBeeld Van Dijk Beton, Tjerk van Duinen

4,000 tonnes of precast concrete for Zevenhuizen substation
Building substations requires precision work. The concrete foundations for the switchyard in particular demand exact dimensions and tight tolerances. Van Dijk Beton knows all about this. The company, based in Groot-Ammers, supplies precast foundation beams, cable trenches and blast walls for several TenneT substations, including the one in Zevenhuizen.

Van Dijk Beton is one of the companies selected by the SC&M construction consortium as a preferred supplier for a number of substations. “Our core business is precast concrete, with a specialism in larger elements,” says Henk Schaap, commercial director at Van Dijk Beton. “For example, we supply foundation blocks for Rijkswaterstaat gantries and blast walls for transformer stations. These are precast walls designed to direct the pressure of a transformer explosion upwards as far as possible, thereby limiting its impact.” For the station in Zevenhuizen, Van Dijk Beton supplied a special type of blast wall, as well as the foundation beams and all the cable trenches with their covers. “In total, that amounts to almost 4,000 tonnes of precast elements.”

500 beams
The electrical bays are supported by a grid of foundation beams. Schaap says: “A high degree of accuracy is required here. There are 500 beams, 3 to 7 metres long, some of which cross over one another. They are cast monolithically with the pile foundations and connected to each other. The anchors therefore have to line up precisely. Mobriq elements, which support the steel structure, are installed on this grid. For Zevenhuizen, we supplied almost three kilometres of foundation beams in total, amounting to 3,000 tonnes of precast concrete. Most of the elements contain special earthing reinforcement in addition to structural reinforcement, connected to the earth grid via earth plates.”

Cable trenches
Another important feature of the substation is the cable trenches in the switchyard. “The quantities involved are substantial here too,” says Schaap. “We supplied a total of 750 metres of trenching. This included straight sections, corner units and T-junctions, all with matching covers. We supply these trench units in various sizes, with either a single compartment or a two- or three-compartment layout. The covers can be made in different thicknesses, depending on the traffic loads the trench needs to withstand in each location.”
Blast walls with relief pattern
One special delivery was the blast walls for Zevenhuizen substation. These are arranged in a U-shape around TenneT’s two large transformers, which convert high voltage to medium voltage. Schaap says: “These walls ensure that any explosion is directed upwards. They are usually built from horizontal elements, but here the choice was 6.5-metre-high vertical elements, 2.5 metres wide. Each element weighs approximately 17.5 tonnes, and 30 were needed to build the walls. They taper towards the top, saving concrete without compromising their protective function. The client also requested walls with a relief pattern on the outside to give them some aesthetic appeal. This was achieved by placing a textured mat in the bottom of the mould. The relief does not extend to the edges, as that would make the elements more vulnerable to minor damage. The wall elements are connected to the foundations using starter-bar anchors. All sleeves for pouring concrete are on the inside. This prevents filled-in formwork tubes from spoiling the attractive relief wall. Even at an unmanned substation, you want things to look good.”
Een zakelijke vraag aan Van Dijk Beton? Neem contact op
Bedrijven in dit verhaal
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- OnderwerpProjects
- BedrijfVan Dijk Beton


















