Kieldrechtsluis, Antwerp | Greater operational reliability for bridges in the Port of Antwerp

The opening of the Kieldrechtsluis brought benefits to the Port of Antwerp and the country as a whole. Although the original planning application provided for four bridges, only two were actually built. The rail infrastructure was also not yet in place, meaning that only internal transport between the port terminals was possible. Under the leadership of the Maritime Access Division, the THV Kieldrechtbruggen has now built and installed the two remaining bridges to improve the flow of road traffic and shipping in the port.

Both bridge chambers had already been built during the first phase. The biggest challenge was fitting the bridges into these chambers.
The Kieldrechtsluis was officially opened on 10 June 2016. In terms of volume, it was, and still is, the largest lock in the world: 500 metres long, 68 metres wide and 17.8 metres deep. But however enormous the dimensions, construction had to be precise down to the smallest detail: the two lock gates at each head, the lock chamber, eleven buildings, two bascule bridges, four bridge chambers, and the mechanisms for opening and closing the gates and bridges.
“The Kieldrechtsluis enabled the Port of Antwerp to respond appropriately to the increasing scale of shipping and thereby strengthen its position in Europe,” says Sofie Nullens, project manager at the Maritime Access Division. “We manage and operate the maritime access routes to the Flemish seaports, along with the civil engineering structures and properties alongside them. We are also responsible for building and maintaining the basic infrastructure in the seaports, such as locks, dams, jetties, railway embankments and green buffers, including the access roads to and from the port area.”

Kieldrechtsluis completed with two bridges
To further improve traffic flow, and also to avoid problems if one of the bridges needed maintenance or developed a fault, it was decided to build and install the two remaining bascule bridges. “The original planning application provided for four bridges. A road bridge and a combined rail and road bridge were to be built at each lock head. However, the two road bridges were never built, although the bridge chambers were provided,” says Nullens. “The brief was now to build and commission the two missing road bridges, one at each head and each right next to the existing bridges. Each bridge is 100 m long, 15 m wide and 21 m high, weighs 1,500 tonnes and has two lanes.”

The bridges were installed with great precision in the existing chambers. Transporting both bridges and positioning them correctly was a real feat of engineering.
A highly challenging project
This was a project full of challenges. The biggest was fitting the bridges into the existing chambers, where there was only a clearance of a few centimetres. The bridges also had to be transported in one piece on a pontoon from the construction site at Kluizendok in Ghent to Deurganckdok.

After installation, THV Kieldrechtbruggen was given three weeks to complete the assembly, after which the bridges were raised to a vertical position, ready to enter service in the summer.
“When the pontoon arrived at the dock, the bridges first had to be rotated 90°, as they had been laid lengthwise for balance. This was done using a self-propelled modular transporter with sixty axles and two hundred and forty wheels,” explains Nullens, describing this feat of engineering. “On 8 April, the Arenbergbrug was installed alongside the existing Prosperbrug. The bridge was first jacked up until it was above the quay wall. The pontoon then moved into the lock chamber to the position where the bridge was to be placed. Once it had been accurately positioned, the team lowered it gently into place. The Sint-Annabrug was installed alongside the Ketenisbrug on 11 April using the same procedure.”
After installation, THV Kieldrechtbruggen was given three weeks to complete the assembly, after which the bridges were raised to a vertical position, ready to enter service in the summer.
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Kieldrechtsluis in Antwerpen
- bouwde en installeerdeTHV Kieldrechtbruggen
- staalconstructieAelterman
- elektromechanische installatieEngie Fabricom
- aanpassingen aan de betonnen constructieHye
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectKieldrechtsluis
- ThemaBruggen en kunstwerken langer mee
- OnderwerpProjects
- BedrijfTHV Kieldrechtbruggen


















