Kieldrechtsluis, Antwerp | Two new bridges for the Kieldrechtsluis

In July 2019, the Kieldrechtsluis will have been in operation for exactly three years. Four bridges were planned as part of its construction, but only two had been installed when it opened. THV Kieldrechtbruggen, a joint venture bringing together Aelterman, Engie Fabricom and Hye, has now been commissioned by nv Deurganckdoksluis to build and install the two remaining bridges, improving the flow of road and water traffic in the port.
Completed bridges transported from Ghent to Antwerp on a single pontoon
Each bridge is 100 m long, 15 m wide and 21 m high, weighs 1,500 tonnes and has two lanes. The fully completed bridges were transported together on a single pontoon from Kluizendok in the Port of Ghent, via the Ghent-Terneuzen Canal and the Western Scheldt, to Waaslandhaven.
The Kieldrechtsluis is the largest lock in the world, and the original plans provided for four bridges. However, in the first phase, only two combined rail and road bridges were completed. Moreover, the railway line has so far been used only for internal transport between the various container terminals. To improve the flow of traffic, nv Deurganckdoksluis decided to issue a new tender for the construction and installation of the two remaining bridges. Unlike the existing bridges, which were built in China, the contract was awarded to Belgian joint venture THV Kieldrechtbruggen.

The bridges were assembled in the Kieldrechtsluis over three weeks, keeping disruption to shipping to a minimum. They are now in a vertical position until they are commissioned this summer.
Clear division of responsibilities
The responsibilities were clearly divided from the outset. Aelterman delivered the steel construction, while Engie Fabricom was responsible for the electromechanical installation. Hye was tasked with ensuring that the bridges could be connected precisely to the concrete structure of the existing chamber. “We started building the steel structure in the summer of 2017. The steel plates were cut by flame to create the required pieces, which were then assembled like a jigsaw. As with all our other projects, this was entirely bespoke,” explains Aelterman project engineer Frederiek De Preetere. “The steel structure was complete by autumn 2018, when Engie Fabricom began the electromechanical installation. The shafts and bearings were fitted, along with all the electrical cabling and the elements required for shipping, such as the signalling. The bridges were also fitted with guardrails and a road surface.”

The THV Kieldrechtbruggen partners Aelterman, Engie Fabricom and Hye completed a remarkable feat, both in building the bridges in the workshop and in preparing the site.
The virtually identical bridges comprise many heavy components, some weighing as much as 20 tonnes each, which is highly unusual for a bridge. They are driven by three 200 kW hydraulic pump units and two hydraulic cylinders measuring 0.9 m in diameter and 15 m in length, and weighing 43 tonnes. It was also no easy task to fit the 1,400 mm diameter shafts accurately in a single operation. After the structure and shafts had been brought to the correct temperature, the components were pushed together, after which the parts were allowed to cool and warm respectively.

THV Kieldrechtbruggen was commissioned to build and install two bridges at the Kieldrechtsluis. The enormous steel structures are 100 m long, 15 m wide and 21 m high, and each weighs 1,500 tonnes.
A remarkable feat
The bridges were fully assembled at Aelterman’s site at Kluizendok in Ghent. At the same time, the partners carried out preparatory work at the Kieldrechtsluis. Engie Fabricom installed and tested the electrical and mechanical components to enable the bridges to be connected immediately. Hye, in turn, made modifications to the concrete structure of the existing chambers. Hydrodemolition, the removal or blasting of concrete using ultra-high-pressure water, was used to remove surplus concrete without damaging the reinforcement. “Building the bridges was a unique project, but transporting them was also a remarkable feat. Bridges are usually transported in sections and assembled on site, but for this project the bridges were shipped in one piece. A self-propelled modular transporter with sixty axles and two hundred and forty wheels moved the bridges onto a pontoon bound for the Kieldrechtsluis,” says De Preetere. “The bridges were installed in early April. We had just three weeks to assemble them. They then had to be raised to a vertical position so that shipping through the Kieldrechtsluis would be disrupted as little as possible. The bridges will remain in this position until they are commissioned in the summer.”
Vraag over dit verhaal? Stel je vraag
Wie eraan werkte
Kieldrechtsluis in Antwerpen
- bouwde en installeerdeTHV Kieldrechtbruggen
- staalconstructieAelterman
- elektromechanische installatieEngie Fabricom
- aanpassingen aan de betonnen constructieHye
Blijf dit volgen
Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.
- ProjectKieldrechtsluis
- ThemaBruggen en kunstwerken langer mee
- OnderwerpProjects
- BedrijfAelterman
- BedrijfEngie Fabricom
- BedrijfHye


















