Projects

Living above Scheldeplein

Tekst Tjerk van DuinenBeeld Reppel

Afstorten met lichtgewicht beton.
Afstorten met lichtgewicht beton.

Adding extra floors with a lightweight flooring system

The complete renovation of the building once known as the Glaspaleis van Sieberg has recently been completed at Scheldeplein. Client Caransa Groep commissioned DOK Architecten to design a scheme that restored the building’s original appearance at this prominent location. In addition, nine luxury apartments have been added to the roof, some with a patio or roof terrace. To make this additional storey possible, Reppel of Dordrecht provided a lightweight floor structure for the new top floor.

The roof of Scheldeplein 1 at various stages.

Reppel specialises in flooring systems for new-build, renovation and transformation projects. The company supplies, among other products, the well-known LEWIS® dovetail sheets® and HODY® composite steel deck floors. “To create a strong but not excessively heavy floor at Scheldeplein, we opted for our OP-DECK® system,” says Niels de Bruin, Technical Manager at Reppel. “The building has a completely new steel roof structure, which was already additionally sound-insulated because of the bowling alley below. Earlier in the construction process, the building’s foundations had been strengthened to support the extra residential floor.” The rooftop residential scheme comprises four patio apartments on the Geulstraat side and five terrace apartments along Geleenstraat. 

Sandwich panel

OP-DECK® is a lightweight, insulated concrete flooring system with a shallow build-up that can accommodate long clear spans. The system consists of a sandwich panel made from thin profiled steel sheet with PIR foam insulation. The panels rest on the steel structure. “EPS blocks placed on the panel further reduce the weight and form the mould for the structural concrete floor with T-ribs,” explains De Bruin. “A top layer of reinforcement is placed on the EPS blocks, with the bottom reinforcement between them. This flooring system effectively combines the advantages of a composite steel deck floor with those of a ribbed floor, creating an extremely lightweight solution.”

3D rendering of the OP-DECK® system.

Even lighter

A C28/35 concrete grade with a weight of 24 kN/m3 is normally used for the concrete floor. De Bruin says: “But at Scheldeplein, this still put us just over the required weight. We addressed that by using lightweight concrete weighing 18 kN/m3. The spans on this roof are 5.5 metres, but this system can achieve spans of up to 10 metres. Those are considerable distances when you consider that the entire OP-DECK® floor package at Scheldeplein is just 288 mm thick! With this floor build-up, the OP-DECK® floor has an Rc value of 6.8. The design floor loads for this project are 2.25 kN/m² for the apartments and 2.5 kN/m² for the terraces.” 

A cross-section of the Scheldeplein roof. The self-weight of the OP-DECK floor is 1.59 kN/m².

Access hatches

The various service penetrations required for the apartments presented an additional challenge. “Water and electrical conduits were no problem, but routing and neatly finishing the soil pipes and drains beneath the floor required a little more attention. We also had to install 22 access hatches. A crawl space has been created beneath the entire roof floor, accessible from the apartments via these hatches for maintenance, for example.” 

According to De Bruin, the OP-DECK® system proved to be the perfect solution for this rooftop extension project. “We often use this system for parking decks, such as on top of a shopping centre. In those cases, we combine it with a Triflex system or Zoontjens parking deck tiles, for example. The floor specifications at Scheldeplein were similar: low self-weight, high insulation value, long spans, high permissible loads and 60 minutes’ fire resistance. The system can also be installed quickly and easily without props for spans of up to 5.5 metres. Its versatility made it a perfect fit for the design of this challenging project.” 

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Glaspaleis van Sieberg, renovatie

  1. OpdrachtgeverCaransa Groep
  2. ontwerpDOK Architecten
  3. lichte vloerconstructieReppel

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectGlaspaleis van Sieberg
  • ThemaBouwen in de bestaande stad
  • OnderwerpProjects
  • BedrijfCaransa Groep
  • BedrijfDOK Architecten
  • BedrijfReppel
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.