Projects

New Waterworks Zoutkamp

Tekst Roel van GilsBeeld Strukton

De monumentale Hunsingosluis uit 1859 wordt gerestaureerd en omgebouwd naar een schutsluis.
De monumentale Hunsingosluis uit 1859 wordt gerestaureerd en omgebouwd naar een schutsluis.

Making Zoutkamp ‘heritage inclusive’

To cope with the effects of climate change up to 2050, greater pumping capacity is needed to protect the historic Groningen fishing village of Zoutkamp and its surroundings from high water. Waterschap Noorderzijlvest, Het Hogeland municipality and the province of Groningen identified opportunities to combine projects and are therefore working together on the Nieuwe Waterwerken Zoutkamp project. In addition to improving flood safety, the project will also give an immediate boost to quality of life, road safety and tourism in Zoutkamp and the surrounding area.

Strukton began work on site in May 2023.

The water authority initiated this unique project. “Up to 2050, we can see a number of challenges ahead that will affect our management area and require measures to keep it dry,” says Mark Pietersen, project manager at Waterschap Noorderzijlvest. “The western side of the city of Groningen is effectively the drainage point for the river basin. All the water that falls on the Drents Plateau (the area between the cities of Assen and Groningen, ed.) flows towards the western side of Groningen and then has to be carried north, to the Hogeland, the region north of the city. A number of water storage areas have already been created for this purpose. But that alone is not enough. Additional capacity is needed north of the city to discharge water towards Lauwersmeer. Excess surface water is temporarily stored there and, when the tide is favourable, discharged into the Wadden Sea under gravity through the R.J. Cleveringsluizen. To this end, we increased the discharge capacity of pumping station Schaphalsterzijl by 420 m3 per minute in 2022, and now the capacity of pumping station H.D. Louwes in Zoutkamp also needs to be increased by a further 600 m3 per minute.”

According to plan, all the structural work and most of the finishing work on the pumping station and lock should be complete by October 2025.

Sea dike

The challenge in Zoutkamp is even greater, because the regional flood defences would need to be raised by 60 to 80 centimetres to keep the area dry. As they run right through the village, this would mean turning the whole place upside down. That was clearly not desirable. The water authority therefore came up with an alternative that gives a central role to the former sea dike. Zoutkamp used to lie on the coast. After the Lauwerszee was dammed in 1969, following the 1953 North Sea flood disaster, it became a lake. Since then, the Hunsingosluis in the former sea dike has no longer served as a sea defence. “During the exploration phase in 2019, we weighed up both options: either upgrade the existing pumping station and raise the flood defences through the village, or move the whole package to the sea dike, including the construction of a new pumping station and restoration of the Hunsingosluis, which is a listed national monument,” says Pietersen. “The latter option was ultimately chosen, and from 2019 onwards we have been busy securing the funding and looking for opportunities to combine projects to make the business case stack up.”

A look inside the flow channels of the new pumping station.

A detailed design with no surprises

To develop a sound, carefully considered design, it was decided to involve the market at an early stage rather than wait until the specifications were complete. “We therefore put a two-phase contract out to tender. Two contractors submitted bids, and we then joined forces with Strukton for the first phase. The brief was to deliver a buildable detailed design with no surprises. This was finalised in December 2022, after which the General Board of Waterschap Noorderzijlvest approved the funding for the entire project in February 2023.” Marcel Kampman, project manager at Strukton, says: “We ultimately arrived at a design for a new pumping station with the planned capacity of 1,600 m3 per minute, alongside the historic Hunsingosluis, built in 1859. The lock is also being upgraded. We will restore it and convert it into a navigation lock, so that boats can pass through even when the pumping station is operating. That is not possible at present.” 

New pumping station to serve as a temporary bypass

Strukton began work on site in May 2023. “We started by creating a 100 by 20 metre construction pit for the substructure of the pumping station. We installed 407 combination piles with precast cores and grout casings,” says Kampman. “The pit was then excavated to a depth of around 8.5 metres, and we poured a 1-metre-thick underwater concrete floor. The pit was pumped dry and has stayed beautifully dry ever since.” The structural floor has now been poured, and Strukton is working on the external and dividing walls for the three flow channels. “The structural work on the pumping station should be complete around September this year, and we will then begin restoring the Hunsingosluis. At that point, the Hunsingokanaal will be completely dammed off by a cofferdam. The old H.D. Louwes pumping station still needs to pump water to Lauwersmeer during the coming winter, and this will be done via a bypass through the flow channels of the new pumping station. That means we will not need a temporary pumping installation.”

Strukton is currently working on the external and dividing walls for the three flow channels of the new pumping station.

Bringing old and new together

The Hunsingosluis is an old sea lock. When the H.D. Louwes pumping station is running, boats cannot pass through. “That will soon be a thing of the past,” Pietersen assures us. “For the restoration and design of the new lock, we also sought advice from the Cultural Heritage Agency of the Netherlands and a restoration architect. Their advice was not to make the mistake of making the new section of the navigation lock, which will literally be ‘bolted on’, look old. This will make the different periods clearly visible. The old will remain old, and the new will be unmistakably new. The wooden gates will also be reinstated in the flood lock, although they will be operated electromechanically, while the new section will have steel lock gates operated hydraulically. A fine combination of technologies. The lock will not be completely drained either, to avoid damaging its structure.”

Construction of the new pumping station alongside the listed Hunsingosluis.

According to plan, all the structural work and most of the finishing work on the pumping station and lock should be complete by October 2025. This will be followed by a period of commissioning and system coordination. Final handover is scheduled for March 2026. At the same time, Strukton is also delivering five associated projects for the municipality. According to Kampman, this was a deliberate choice, so that it is clear to the local community that a single contractor is carrying out the work and that there is one point of contact for any questions. Alongside flood safety, the project will improve road safety, expand tourism and recreation around Lauwersmeer, and strengthen recreational boating links towards the Hogeland and the city of Groningen. Pietersen concludes: “After handover, we will invite the market to come up with a sustainable, responsible and innovative way to decommission the old H.D. Louwes pumping station.”

Nieuwe Waterwerken Zoutkamp is co-funded by Nationaal Programma Groningen, Waddenfonds, Erfgoed Deal and Commissie Bodemdaling. 

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Waterwerken Zoutkamp in Het Hogeland

  1. uitvoerende partijStrukton

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectWaterwerken Zoutkamp
  • OnderwerpProjects
  • BedrijfStrukton
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.