Projects

Brouwershaven rolling bridge delivered:

Brouwershaven rolling bridge delivered:

By expressing the wish to restore the cycle bridge over the lock in Brouwershaven, the town council of the same name launched the project to build a new rolling bridge. After the municipality of Schouwen-Duiveland set up a project team to examine the proposal to reinstate the bridge, work began at the marina. The project was closely guided and managed by Leen van den Boogert on behalf of technical staffing agency Inter Techniek from Hendrik-Ido-Ambacht (part of Inter Groep Bouw & Infra).

The path to a suitable solution with broad support

Illustration of the rolling bridge. (Source: business case DON Bureau)

According to Van den Boogert, several steps had to be completed before the final bridge could be designed. “First, the budget had to be established so that estimates could be drawn up. The bridge was not included in the municipality’s implementation budgets, so a business case was prepared in advance. To this end, the municipal project manager commissioned a study from DON Bureau in Bergen op Zoom. DON then drew up a preliminary design in consultation with the client. This design was based on similar bridges in the area around Schouwen-Duiveland.”

Stakeholders

On the basis of the preliminary design and its accompanying cost estimate, the municipality of Schouwen-Duiveland allocated a budget to build the desired infrastructure. The municipal project manager then drew up a schedule of requirements. “This sets out the technical and functional requirements the bridge would have to meet,” Van den Boogert continues. “To draw up a comprehensive schedule of requirements, it was essential to consult closely with the harbourmaster, harbour users and the Brouwershaven town council. The diverse and often conflicting interests of both shipping traffic and bridge users had to be taken into account as fully as possible. The schedule of requirements ultimately formed the basis for the tender invitations.”

The lock around 1966. (Source: Corina Jansen)

Local contractors

When the contract was being finalised, it was decided that the design and detailing of the bridge would be left to the contractor. As part of the tendering process, the municipality of Schouwen-Duiveland opted to conduct a market consultation. “The preference was to work with local companies to build the bridge,” says Van den Boogert. “A number of companies were then invited to give a brief presentation on their proposed approach and role, based on the schedule of requirements. The municipality ultimately chose the solutions and expertise of Hanse Staalbouw and Breston. Together, they undertook both the complete engineering and construction of the bridge.”   

Versatile access

The marina in Brouwershaven consists of two sections. After passing through the lock, alongside the harbour office, you first come to the Nieuwe Haven. Further on is the Stadshaven, located in the centre of Brouwershaven. The new rolling bridge will once again make it possible for cyclists, pedestrians and wheelchair users to complete the circuit around the harbour and, if they wish, continue through the polder. The connections to the regional cycle network also link up neatly here.

Vraag over dit verhaal? Stel je vraag

Wie eraan werkte

Rolbrug Brouwershaven in Schouwen-Duiveland

  1. technisch detacheringsbureauInter Techniek
  2. hoofdaannemerHanse Staalbouw
  3. machinebouwerBreston

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectRolbrug Brouwershaven
  • ThemaBruggen en kunstwerken langer mee
  • OnderwerpProjects
  • BedrijfInter Techniek
  • BedrijfJansen B.V.
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.