Projects

Rotterdam Hes Hartel Tank Terminal | ‘Olympic challenge’ in the construction of Hes Hartel Tank Terminal (HHTT)

Rotterdam Hes Hartel Tank Terminal | ‘Olympic challenge’ in the construction of Hes Hartel Tank Terminal (HHTT)

Alongside the Mississippihaven on Maasvlakte and connected to the Hartelkanaal, Hes Hartel Tank Terminal is under construction on the last large available site on Maasvlakte 1. Port of Rotterdam is responsible for building the terminal’s maritime infrastructure: a 1,200-metre deep-water quay wall, an inner harbour with 1,000 metres of quay and a 350-metre jetty.

“We are building this infrastructure in close cooperation with the client, HES Hartel Tank Terminal (HHTT),” says Adriaan Smitsman, Project Engineer at Port of Rotterdam. “This is a high-quality, safe, state-of-the-art terminal for the storage and transhipment of clean petroleum products and biofuels. The 27-hectare site will accommodate 54 tanks with a capacity of 1.3 million m³. The tanks range in size from 5,000 to 50,000 m³.”

Excellent nautical access

Smitsman says the narrow Hartel strip is ideally suited to a terminal: “The site has excellent nautical access and deep water. Its direct connection to the open sea allows logistics operations to be handled very quickly. Products will be transported to and from the site partly by pipeline, but mainly by ship.” The terminal’s elongated shape means that 3 large seagoing vessels or 5 smaller ones can berth along the deep-water quay, with draughts of up to 21 metres. The inner harbour will have 9 berths for inland vessels: 5 along the quay wall and 4 alongside the 300-metre jetty in the middle of the harbour.

Construction from a temporary working platform

The design by engineering firm MariTeam (SBE, MUC and IV-infra), commissioned by Port of Rotterdam, was developed by Combinatie HHTT (Van Hattum en Blankevoort, Boskalis and Mobilis). “We produced all the production drawings for the formwork, reinforcement, quay furniture, fender systems and other elements,” says Marius van Rijckevorsel, Project Director at the consortium. “To build the deep-water quay wall, a narrow strip of the Mississippihaven was first reclaimed to create a working platform. From this temporary facility, the steel combi wall, designed to withstand the saltwater environment, and the MV piles were installed. The driven, soil-displacement steel H-sections were installed at an angle to withstand the tensile and compressive forces exerted by seagoing vessels.” The L-shaped concrete wall with relieving platform is then built on the combi wall. The slab and wall are cast in one pour using a steel system formwork supplied by Construx. The rear of the relieving platform is founded on screw injection piles.

The quay structure has a design life of 100 years. A sheet pile wall, known as a bund wall, has also been installed on the landward side of the quay to prevent oil from entering the water if one of the tanks leaks. Once the quay is complete, the temporary working platform will be excavated. The resulting sand will be used to backfill behind the quay, on the relieving platform. Dredging and earthworks will then be carried out, along with bank and bed protection works. The inner harbour must be dredged to a depth of -9 metres. The dredged sand will be used at a new harbour site yet to be developed on Maasvlakte 2. The project as a whole involves around 1.8 million m³ of dredging. After dredging, the combi walls of both the deep-water quay and the inland shipping quay will be fitted with impressed-current cathodic protection.

Access ladders

The quay walls in the inner harbour are being built on the same principle as the deep-water quay. However, they are anchored using grout injection anchors rather than MV piles. A distinctive feature is the access ladder integrated into the quay wall at each inland vessel berth, allowing safe access to and from the vessel at any loading level. The jetty consists of concrete piles with concrete pile caps and SJP beams supporting the deck. Steel fender systems will be installed around the jetty. Mattress units topped with riprap, partly grouted with colloidal concrete, will be laid on the harbour bed to protect it from propeller wash. 

A tight and demanding schedule

According to Van Rijckevorsel, the schedule is the project’s main ‘Olympic challenge’. “It is very tight and demanding, and Port of Rotterdam is pushing us to meet it.” Port of Rotterdam also holds weekly coordination meetings with HHTT and the contractors building the terminal for HHTT at the same time. Smitsman says: “Port of Rotterdam’s role is to ensure that the various work packages fit together properly, so that the separate construction processes do not disrupt one another.” Work on the nautical facilities will be completed by the end of 2019. The terminal is expected to become operational in the third quarter of 2021.     

Een zakelijke vraag aan CONSTRUX? Neem contact op

Wie eraan werkte

Hes Hartel Tank Terminal in Rotterdam

  1. bekistingsconceptConstrux
  2. maritieme infrastructuurHavenbedrijf Rotterdam
  3. ontwerpMariTeam

Blijf dit volgen

Bij een nieuw verhaal krijg je een e-mail. Geen account nodig.

Wat je volgt
  • ProjectHes Hartel Tank Terminal
  • OnderwerpProjects
  • BedrijfHavenbedrijf Rotterdam
  • BedrijfMariTeam
  • BedrijfCONSTRUX
Deel dit artikel

Advertentie

Volgen op Beton & Staalbouw

Volg

Bij een project of bedrijf krijg je een e-mail zodra er een nieuw verhaal over verschijnt, bij een thema of onderwerp één keer per week een overzicht. Geen account en geen wachtwoord: in elke mail staat een link naar wat je volgt.